This Statement of Work (SOW) describes refuse and recycling collection and disposal services required at USCG Base Borinquen, Puerto Rico. The contractor must provide collection and disposal services for the Housing Complex, Hangar Complex, Ramey School, and Lighthouse Areas over a base period of 12 months (01 MAY 26–30 APR 27) with four optional 12-month renewal periods. The contract is structured as Firm Fixed Price (FFP) services. Container inventory includes 243 95-gallon plastic containers (government-furnished), ten 6-cubic-yard (cy) plastic containers (government-furnished), one 20-cy steel container for bulk items, and three 20-cy containers for recycling centers and vegetative material/wooden pallets (contractor-furnished). The contractor must provide three additional 20-cy containers and recycling centers with at least three labeled compartments for paper, aluminum cans, plastic, and cardboard separation.
Collection schedules vary by location: 95-gallon containers require weekly Monday-through-Friday pickup (excluding Federal Holidays) between 7:00 am and 6:00 pm; 6-cy containers at Ramey School require twice-weekly pickup (Tuesday and Friday); the Lighthouse 6-cy container requires monthly pickup; and the three 20-cy containers require pickup when full within two working days of COR notification. The contractor must submit multiple deliverables including a Technical Plan, Safety Plan, Quality Control Plan, Contractor Quality Control Plan, schedule of assignments, list of employed personnel, recycling/refuse center specifications within 10 days of award, and monthly reports documenting collected materials. All work must comply with Federal, Puerto Rico Commonwealth, and local laws; EPA and OSHA regulations; Puerto Rico Environmental Quality Board requirements; and USCG regulations. Personnel requirements include a designated Project Manager/point of contact available at all times with one-hour response time to COR calls, security passes for all workers, compliance with OSHA safety standards, and professional conduct standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATT 2 Schedule of services price.xlsx | XLSX spreadsheet | |
| ATT 3 WD 20025-5695 REV 27 12032025.pdf | ||
| 70Z08426QDL930002 COMBINED SYNOPSIS BORINQUEN REFUSE.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
REFUSE & RECYCLING COLLECTION & DISPOSAL SERVICES
USCG BASE BORINQUEN, PR.
1. INTRODUCTION
The U.S. Coast Guard (USCG) Logistics Command (LOGCOM) is procuring Refuse and Recycling Collection and Disposal Services as required by the USCG Base Boringuen, Puerto Rico. The contractor shall ensure that these services are performed in a manner that ensures the health and safety of federal employees and members of the public and all federal buildings and property. The results anticipated by the USCG is the full and complete provision of these services furnished in a manner that provides superior customer service that presents a comfortable, healthy and safe environment for all in accordance with the Statement of Work (SOW) herein.
2. BACKGROUND:
Mission: The mission of the Coast Guard is to provide and maintain a safe, clean and healthy environment for all residents, military/civilian personnel and members of the public. To accomplish this mission, it is essential that the properties and facilities of the areas specified herein have qualified refuse and recycling collection and disposal services as required. The purpose of this SOW is to provide support to the CG installation to accomplish its mission
2.1. The table below identifies the Location, Size and Number of Refuse Containers:
Refuse Container Size Location of Container Quantity
Various Areas 6-cv plastic/cover Hangar Area 2 6-cy plastic/cover School Drive Road - La Plaza 1 6-cy plastic/cover Medical-NE 1 6-cy plastic/cover Community Center 2 6-cv plastic/cover Facility Maintenance Area 1 6-cy plastic/cover Ramey School 2 6-cy plastic/cover Lighthouse 1 Total 10
20-cy steel* Building 410/Hangar Road 1
Housing Area 95-gal plastic/cover** Housing Quarters 219 95-gal plastic/cover Central Park Playground 2 95-gal plastic/cover Circle F Playground 2 95-gal plastic/cover Cliff/Hook Playground 2 95-gal plastic/cover Basketball-Tennis Area 2 95-gal plastic/cover Ray Park Area 4 95-gal plastic/cover Intersection 5w & Cliff 1 95-gal plastic/cover Intersection 6m & Cliff 1
95-gal plastic/cover Intersection NE & Cliff 1 95-2al plastic/cover NE Road Soccer Field 2 95-gal plastic/cover Cliff Road Soccer Field 2 95-gal plastic/cover Swimming Pool 2 95-eal plastic/cover Housing Gate Guard 1 95-gal plastic/cover Grounds Maintenance Shop 1 Hangar Area 95-gal plastic/cover Hangar Gate Guard 1 Total 243
2.2 The Table below identifies the Location, Size and Number of Recycling Containers:
NOTES:
• The 20-cubic yards (cy) container to place bulk items (Section 5.2.3).
*****Each house collection point for container pick up is accessible from either an alley or main road.
••• The Contractor shall provide a Recycling Center to the Hangar Area and shall have at least 3 containers or compartments to allow recyclables (paper, aluminum cans, plastic) to be separated/classified. Each container or compartment shall be properly labeled to each specific item to be disposed (paper, aluminum cans, plastic). Contractor shall coordinate with the COR the location where the container will be located. Container location will vary as needs change. The Contractor shall submit the containers for approval to the COR, including the date of delivery. not later than 10 days after award.
•••• The Contractor shall provide a Recycling Center that shall have at least 3 containers or compartments to allow recyclables (paper, aluminum cans, plastic, and cardboard) to be separated/classified. Each container or compartment shall be properly labeled to each specific item to be disposed (paper, aluminum cans, plastic, and cardboard). Contractor shall coordinate with the COR the location where the container will be located. Container location will vary as needs change. The Contractor shall submit the containers for approval to the COR. including the date of delivery. not later than 10 days after award.
••••• The 20-cubic yard (cy) container to collect all vegetative material (Section 5.3.3). The container shall be properly labeled to specify its purpose.
****** The 20-cubic yard (cy) container to collect all wooden pallets (Section 5.3.4). The container shall be properly labeled to specify its purpose.
3. SCOPE
The objective of this effort is to acquire Refuse and Recycling Collection and Disposal Services as required for the healthy and sanitary conditions and safety of personnel, property, facilities and land at the USCG locations as described in the SOW. The service requirements and performance objectives
Recycling Container Size Location of Container QTY Cardboard Recycling Area Hangar Parking 1 Recycling Center***** Hangar Area 1 Recycling Center***** Housing Area 1 20- cubic yard steel***** Building 410/Hangar Road 1 20- cubic yard steel****** Hangar Parking 1 relate directly to mission essential items as identified in the SOW, the Contractor Quality Control Plan (QCP) providing for the highest level of service delivery performance critical to mission success. The contractor shall furnish all labor, material, equipment, supplies, transportation, management and supervision, unless otherwise specified herein, necessary to perform all refuse and recycling collection at the Base Borinquen locations, consisting of the Housing Complex, Hangar Complex, Ramey School and Lighthouse Areas.
SCHEDULE of SERVICES
The contractor will provide is procuring Refuse and Recycling Collection and Disposal Services as required by the USCG Base Boringuen, Puerto Rico. The contractor shall ensure that these services are performed in a manner that ensures health and safety of federal employees and members of the public and all federal buildings and property. The services will be for a Base Period of 12 months and four (4) 12-month Option Periods, as described hereto, in accordance with the following (1) Statement of Work (SOW); (2) Terms and Conditions (clauses/provides); and (3) Schedule of Services
Firm Fixed Price (FFP) services as described below:
Performance Period
Base Period 01 MAY 26-30 APR 27
Option Period One 01 MAY 27-30 APR 28
Option Period Two 01 MAY 28-30 APR 29
Option Period Three 01 MAY 29-30 APR 30
Option Period Four 01 MAY 30-30 APR 31
4. APPLICABLE DOCUMENTS
4.1 The contractor shall comply with all applicable Federal, Puerto Rico Commonwealth and local laws and regulations and environmental and hazardous laws and regulations and applicable instructions and directives pertaining to the services required herein and to the conduct and qualifications of personnel in performance of this contract. Such pertinent regulations shall include the applicable regulations and pertaining provisions of the Puerto Rico Environmental Quality Board (EQB) and Puerto Rico Solid Waste Management Authority. The contractor shall utilize safe products and equipment and qualified personnel to ensure the health and safety of all in compliance with the Environmental Protection Agency (EPA) and the Occupational Safety and Health Administration (OSHA). The Contractor shall also follow all the safety requirements established by the Puerto Rico Occupational Safety and Health Office (PROSHO), which operates under the Commonwealth Department of Labor. "The Puerto Rico Occupational Safety and Health Act" (No.
16) declares that it is the public policy of the Commonwealth of Puerto Rico to guarantee safe and healthy working conditions to each employee. Prior to starting work under this contract, the contractor shall obtain the necessary permits and licenses to perform Refuse and Recycling Collection and Disposal Services.
4.2 The contractor shall comply with the USCG Regulations listed in the table below, which will be provided upon request or at time of contract award, applicable to the performance of the contract and to contractor personnel. The Government may issue supplements or amendments to the publications from any organizational level during the life of the contract. The Contractor shall keep all publications up-to-date and shall immediately implement those changes that result in a decrease or no change in the contract price. Before implementing any change that will result in an increase in contract price, the Contractor shall submit to the Contracting Officer a price proposal for approval within 30 calendar days from the date the Contractor receives notice of the revision, supplement, or amendment-giving rise to the increase in cost of performance.
PUBLICATION TITLE
COMDTINST M16478.l (series) Hazardous Waste Management Manual COMDTINST M5100.29 Safety and Occupational Health Manual COMDTINST M5100.47 (series) Safety and Occupational Health Manual
COMDTINST M5530.l C Physical Security and Force Protection Program
Drawing Refuse Collection and Recycling Base Borinquen Hangar, Housing, CGES & Lighthouse Areas Site Plans
5. TECHNICAL REQUIREMENTS
5.1 General
5.1.1 Schedule: The contractor shall schedule and perform all refuse and recycling collection and disposal services of garbage and trash for the USCG Base Borinquen (Hangar, Housing, Lighthouse, and Ramey School) areas at Aguadilla, PR in accordance with the approved task, frequency and work schedule; the approved Contractor Quality Control Plan; and, the required reports of the SOW. The Contractor shall collect, remove and dispose of all refuse and recycling materials as scheduled in the SOW in accordance with local, state and federal requirements. All areas, which are involved in the collection and disposal services, shall be maintained in a neat, clean, uniform and safe condition at all times.
5.1.2 Bonds. The contractor shall provide any official bond required and pay any fees or cost involved or related to the authorization for any employees engaged in providing services specified under this contract. The contractor shall provide proof of compliance of "El Fondo del Seguro del Estado", translated as "The State Insurance Fund", which provides Workman's Compensation for the employees working under this contract, as mandated by Puerto Rico Law, as specified in Section 6, Deliverables, of the SOW.
5.1.3 Pre-Start Meeting: Not less than 3 days prior to the start of the refuse collection work, the Contractor/Project Manager shall schedule a pre-start meeting. This meeting shall include the Contracting Officer Representative (COR), the Environmental Technician and the Housing Office Representative. The Contractor shall be prepared to discuss the following tasks:
a. Schedule of the work.
b. Safety measures (safety/ environmental plan).
c. Inspection methods by the Quality Control Inspector.
d. Method of recycling and refuse collection, including the vegetative material procedures.
e. Points of contact (phone numbers) in case of emergencies; and, a list of persons employed under the contract.
f. Coordination of access to the working areas.
g. Verification of the quantities and location of refuse collection areas.
h. All licenses required by the local, state and federal to operate the refuse collection operation.
i. The landfill area to be used to dispose the refuse/recycling for this project, including all required permits.
j. The Workman’s Compensation Insurance, "El Fondo del Seguro del Estado". A certified copy.
I. Submittal of all 20-cy and Recycling Centers. Delivery day of containers.
5.1.4 Safety: All equipment shall be operated within the safety parameters as defined by OSHA.
Equipment shall be operated with particular care when near pedestrians and especially near children.
Equipment shall be in working, safe, and good mechanical condition to operate on USCG property.
There shall be no visible oil or refuse spills on the road due to carelessness of contractor or inadequate equipment. Contractor shall submit a Safety Plan for approval as specified in Section 6 Deliverables, of the SOW.
5.1.5 Technical Plan: The contractor shall submit a Technical Plan, as specified in Section 6, Deliverables, of the SOW. The Technical Plan shall contain the following:
An emergency backup plan in case the landfill area designated is closed by the regulatory agencies; and procedures to collect vegetative material and shredded in compliance with the regulatory agencies.
5.2 Special Collection Situations
5.2.1 Incendiaries/ Explosives: If incendiary or other explosive material is found at a collection station, or at any location on AIRSTA Borinquen, the refuse collection workers shall immediately call the COR or the base security staff on duty at the moment and provide the exact location.
5.2.2 Hazardous Materials: The Contractor shall inform the COR of any hazardous materials (i.e.
batteries, tires, paints, chemicals) found in the performance of this project and ensure they are not disposed of until coordinated by the Government Environmental Technician. The contractor shall comply with all Federal, State and Local environmental laws and regulations when handling hazardous materials.
The Contractor shall immediately contain and clean up the release or spill of a hazardous material and report the incident to the COR or the Environmental Technician.
5.2.3 Large/Bulk y Items: The contractor is not required to pick up bulk items left near the 95-gallon containers at each house. Bulk items could be trees, appliances, metal items, construction material, vehicle parts, etc. or any item that is larger than l cubic yard (cy). The contractor shall provide one 20-cy container near Bldg. 410 where the USCG may place bulk items. Contractor could be required to provide other 20cy container in any part of the Air Station (Hangar Area), the housing area, lighthouse area, the CGES area, the Ramey school area.
5.2.4 Refuse Collection: The contractor shall collect refuse in all containers according to the schedule of items. All other loose refuse such as tree branches, palm fronds, not limited to, which are placed adjacent to the containers, shall be picked up by the contractor during collection except for bulk or hazardous materials as identified in the SOW.
5.2.5 Private Areas: The contractor shall only go on grass area and around family quarters to pick up loose trash. The contractor shall not use family quarter's driveways or drive a vehicle in any area that is not specifically designated for use by vehicular traffic.
5.3 Disposal - Submit location for approval.
5.3.1 Refuse Disposal: All refuse and bulk items shall be disposed of to a location licensed by the government of Puerto Rico and following all Federal, State and local licenses and regulations for such purposes. The Contractor shall obtain all necessary permits for disposing of refuse. Copies of these permits shall be submitted to the COR for approval. If the contractor changes the location of the site, a new permit must be obtained and a copy again shall be submitted to the COR for approval. All payments for the permit will be at the Contractor's own expense. A report shall be submitted to the COR by the end of every month documenting the total amount of refuse materials that were collected the prior month. This report shall be submitted with the invoice.
5.3.2 Recycling Disposal: At a minimum, the contractor shall collect plastic, aluminum beverage cans, paper products and cardboard as recyclable materials. All items (i.e. cardboard, cans, papers, metal) shall be taken to a recycling operation licensed by the government of Puerto Rico. The Contractor shall comply with all Federal, State and local licenses and regulations for such purposes. The contractor shall obtain all necessary permits for handling recyclables, and copies shall be submitted to the COR for approval. All payments for the permits will be at the Contractor's own expense. A report shall be submitted, to the COR, by the end of every month documenting the total type and amount of recycled materials that are collected.
5.3.3 Vegetative Material: Contractor shall collect all vegetative material using a special 20-cy container.
Contractor shall coordinate with the .COR the location where the container will be located. Container location will vary as needs change. Location could be at Hangar, Lighthouse and Housing areas.
Material, when collected, shall be shredded in accordance with the waste regulatory agencies. Contractor shall submit a technical plan of procedures to be used to comply with latest laws and regulations of vegetative material collection and recycling. Such pertinent regulations shall include the applicable regulations and pertaining provisions of the Puerto Rico EQB and Puerto Rico Solid Waste Management Authority.
5.3.4. Wooden Pallets: Contractor shall collect all wooden pallets using a 20-cy container. Contractor shall coordinate with the COR the location where the container will be located. Container location will vary as needs change. Location could be at Hangar, Lighthouse and Housing areas. Such pertinent regulations shall include the applicable regulations and pertaining provisions of the Puerto Rico EQB and Puerto Rico Solid Waste Management Authority.
5.4 Pick-Up Schedules
5.4.1 Refuse Schedule:
a. Refuse collection from all 95-gallon containers shall be accomplished Monday through Friday, excluding Federal Holidays, between the hours of 7:00 am and 6:00 pm. Pick-up shall be made weekly. The COR shall be notified in advance of any deviations from the regular schedule.
b. Refuse collection from the 6-cy containers located at Ramey School shall be accomplished twice a week on Tuesday and Friday between the hours of 7:00 am and 6:00 pm. The COR shall be notified in advance of any deviations from the regular schedule.
c. Refuse collection from the 6-cy container located at the Lighthouse shall be accomplished once a month on the first week of the month between the hours of 7:00 am and 6:00 pm.
The COR shall be notified in advance of any deviations from the regular schedule.
d. All three 20-cy containers (Bulk Items, Vegetative Material and Wooden Pallets) shall be picked up when full. The COR shall notify the contractor, and the contractor shall make arrangements to have the refuse picked up not later than 2 working days after notification.
5.4.2 Recycling Schedule:
a. The recycling collection from the Housing Recycling Center shall be accomplished Monday through Friday, excluding Federal Holidays, between the hours of 7:00 am and 6:00 pm. Pick up shall be made two times a month. The COR shall be notified in advance of any deviation from the regular schedule.
b. The recycling collection from the Hangar Recycling Center shall be picked up when full. The COR shall notify the contractor, and the contractor shall make arrangements to have the recycling picked up not later than 2 working days after notification.
5.4.3 Inclement Weather Schedule: The contractor shall collect refuse in all weather conditions unless there is a warning during a hurricane condition. Operations shall resume to normal within 24 hours after threat has terminated and roads have been cleared.
5.4.4 Holidays: The contractor shall schedule holiday pick-ups so that the number of pick-ups per week for refuse and recycling will remain the same as required in the SOW.
5.4.5 Emptied Containers: When emptied, the refuse containers shall be returned to their original position with lids placed in the closed position.
5.5 Contractor Furnished Supplies, Material and Equipment: The contractor shall furnish in good condition all necessary supplies, material and equipment, of the size and type customarily used in work of this kind, needed for the performance of the work, unless otherwise specified herein.
a. The Contractor is not required to furnish any 95-gallon green refuse containers.
b. 20-cy: The Contractor shall furnish three 20-cy containers properly labeled to be used by the USCG for the duration of the contract. The contractor shall replace or repair these containers if damaged. The containers will be the contractor's property. These large containers do not require fixed lids or covers, but the Contractor shall provide a means of temporarily covering (i.e. tarp) the container contents during transportation to the disposal site.
c. Recycling Centers: The Contractor shall furnish three 20-cy containers properly labeled to be used by the USCG for the duration of the contract. The contractor shall replace or repair these containers if damaged. The containers will be the contractor's property.
5.6 Government Furnished Equipment, Facilities. Utilities
5.6. l. Containers:
95-gallon Containers: The Government shall provide all 243 95-gallon green containers to be located at each of 219 houses (except 1 Cliff which has two 95-gallon green containers) and at the locations designated in the drawings. The containers are Government property.
Unserviceable containers shall be reported to the COR and replaced or repaired at Government expense unless the damage is due to negligence by the contractor.
b. The Contractor is not required to furnish any of the 6-cy containers. The Government will provide them.
5.6.2. Storage Area: No storage, recycling disposal or refuse disposal area is allowed on USCG property for this project.
6.0 DELIVERABLES
The contractor shall submit the following deliverables in accordance with the table below, as required by SOW and via the following electronic media, Microsoft Office Word, when applicable. The format should be PC compatible and submitted on a CD-ROM or via email.
Deliverables Frequency No. of Copies and to
Whom Date Required
Technical Plan As revised Contracting Officer /
COR
15 days After award, and as updated.
Name(s), telephone number(s) and address(s) of the Point(s} of Contact for Contractual Issues.
As needed Contracting Officer /
COR
15 days After award, and as updated.
Certificate of Insurance as required by FAR 52.228-5 and HSAR Clause 3052.228-70
Annually on each Anniversary Year Officer
Contracting Officer 5 days After award, and as updated.
Small Business Subcontracting Plan as required by FAR Clause 52.219-9 and HSAR Clause 3052.219-70.
Pursuant to FAR Clause 52.219-9
Contracting Officer With quote (Large Business only)
Schedule for all necessary assignments by dates and areas for each location
As needed Contracting Officer /
COR
Five days after contract award
Safety Plan As needed Contracting Officer /
COR
Five days after contract award
Fondo del seguro del Estado certificado (Workman’ s compensación) as requiere by Puerto Rico
Annually Contracting Officer /
COR
Five days after contract award
A list of people employed under the contract
Update as necessary
Contracting Officer /
COR
Five days after contract award
20-cy Container and Recycling Center Submittal
Contracting Officer /
COR
No later than 10 days after contract award
Quality Control Plan As Revised Contracting Officer /
COR
15 days After award
Monthly Report Documenting Collected Refuse Materials
Monthly COR End of every month
Monthly Report Documenting Collected Recycle Materials
Monthly COR End of every month
Contract Discrepancy Report As needed Contracting Officer Within 5 days of receipt
Service Contract Report Requirement FAR 52.204-14
Annually by October 31
Management System for Award (SAM) / Contracting Officer
Annually by October 31
7.0 Personnel Requirements
7.1 The Contractor, or designated qualified personnel, and any substitute(s), shall be able to effectively communicate with all Government and non-government personnel and shall have full authority to act for the Contractor on all contractual matters relating to the daily performance of the contract; and, to receive, accept and sign for any notices, inspection reports and all other correspondence on behalf of the Contractor from the Contracting Officer or COR.
7.1.1 This individual, who shall serve as the central point of contact for the Government, shall oversee the collection operations and monitor and ensure all work is performed in accordance with the SOW and maintain the work specification requirements, scheduling, inspections and safety standards. This individual shall be available at all times when the contract work is in progress, if needed; and, shall have the ability to respond to the site, when needed, to monitor work progress; and, for any other emergency, as required.
7.1.1 The Contractor, or designated qualified personnel, shall return calls to the COR within one (1) hour of being contacted. This individual shall provide the COR his/her cellular phone and an e-mail address to be reached during normal workday hours.
7.2 Workers Safety, Security and Use of Premises: The refuse collection workers will be working on a USCG Military installation and shall be familiar with and obey established fire, safety, environmental and security regulations. All workers shall wear a distinctive uniform at all times. The contractor shall ensure all workers look neat and wear safety equipment/clothing while collection is in progress. The Contractor shall provide a list of employees' names as specified in Section 6, Deliverables, of the SOW.
7.2.1 Security Passes: Contractor's employees shall obtain security passes from the Security Office prior to beginning work and must carry this ID at all times while working under this contract. Each employee must show a valid driver's license, birth certificate or company ID card in order to be issued a security pass.
Contractor personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Contractor personnel may be required to a background check in accordance with Homeland Security Department and USCG policy. Contractor personnel shall make available all required information established for this requirement (such as birthplace, social security, previous employment, etc.).
7.2.2 Safety Practices: Contractor's employees shall ensure that the work area is clearly marked at all times and take necessary precautions to ensure safety hazards are minimized and mitigated; and, shall perform and conduct the work so as to minimize obstruction to the paved driveways and parking and walkway area, and other interference with USCG operations. Contractor's employees shall follow the latest OSHA regulations on this project.
7.2.3 Protection of Property: Contractor's employees shall protect the existing surrounding equipment, personal belongings and property during the course of this work. Any damage caused by the contractor's employees shall be corrected at the Contractor's own expense. The Contractor shall be responsible for repair of any damage incurred to turf, landscaping, vehicles, equipment, buildings, utilities or pavement as a result of work performed under the contract at no additional cost to the Federal Government.
7.2.4 The Contractor’s employees shall observe and comply with all applicable USCG, local unit and higher headquarters regulations, policies and procedures, (fire department, safety, sanitation, environmental protection, smoking, security, gratuities, flag courtesy, “off limits” area, wearing of parts of military uniforms, and possession of firearms or other lethal weapons, possession or consumption of controlled substances and/or alcoholic beverages, etc.). The Contractor shall ensure that their employees’ conduct shall not reflect discredit upon the USCG. Sexual or personal harassment, including horseplay, pranks, and practical jokes, is strictly prohibited. The Contractor is responsible for educating employees in the proper conduct and prohibited actions. All personnel, employed or representing the Contractor, entering the installation shall abide by all applicable safety and security regulations and shall be subject to such security checks as may be deemed necessary by the Government. The Commanding Officer of a Coast Guard facility may remove a contract employee for misconduct or security reasons, following debarment procedures in federal law, regulation and Coast Guard policy. The Contracting Officer may request removal of a contract employee for performance reasons. The KO will provide the Contractor with a written explanation to support any request to remove an employee for performance-related issues. Regardless of the reason, removal does not relieve the Contractor from the contract performance or result in an equitable adjustment to the contract.
8 CONTRACTOR QUALITY CONTROL (QC) REQUIREMENTS
8.1 General. The quality control program is the driver for service/product quality in this contract. The contractor is required to develop a comprehensive program of inspections and monitoring actions. The first major step to ensuring a "self-correcting" contract is to ensure that the quality control program approved at the beginning of the contract provides the measures needed to lead the contractor to success. Once the quality control program is approved, careful application of the process and standards presented in the remainder of this document will ensure a robust quality assurance program.
8.2 Contractor Qualit y Control Plan (QCP): The Contractor shall develop, maintain and implement a complete QCP delineating the contractor's Quality Control Program/Inspection System to monitor and control their performance of services and to ensure that the requirements of the contract are performed and provided in accordance with the SOW, established standards, and with commonly accepted commercial practices. The QCP shall include and address the following items: timely and effective corrective action for all deficiencies identified by the Government addressing the areas identified in the SOW; inspection procedures; an action plan for correction of discrepancies; a strategy for retaining qualified personnel; and, management's role in its commitment to quality performance. The QCP shall be submitted as specified in Section 6.0, Deliverables, of the SOW. After initial approval, if the plan is updated or changed, it shall be re-submitted to the Contracting Officer and COR for approval.
8.3 Quality Control (QC) Program/Inspection System. The QC Program/Inspection System shall encompass all functions of the contract addressing the areas identified in the SOW; and, shall implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor's management and the USCG shall be informed of all issues affecting quality to include timely and effective corrective actions. QC records shall, in part, consist of checklists of inspections and shall indicate the nature, frequency and number of observations made; the number and type of deficiencies found; and, the nature of corrective action taken as appropriate.
8.4 Contents of the QC Program/Inspection System. As a minimum, the contractor shall develop quality control procedures addressing the areas identified in the Service Delivery Summary of the Government Quality Assurance Requirements. The inspection system shall include, but is not limited to, the following:
I. Introduction to the Quality Control System:
A. Background and Rationale for the System B. Objectives in using Quality Control C. Successes with and updates for the System
Il. Refuse and Recycling Collection and Disposal Services Quality Control Process
A. Steps and Flow Diagram - Includes checklists used in inspecting contract performance during regularly scheduled/unscheduled inspections/testing; method of documenting and enforcing quality control operations.
B. Inspection Procedure - Includes checklists used by the contractor, identifying the items, frequency, conformance indicators and actions taken if nonconformance found covering all the service requirements of this contract.
C. Means of Identifying and Resolving Problems - A system for identifying and correcting deficiencies in the quality of services before the level of performance becomes unacceptable and/or the Government inspectors point out the deficiencies.
D. Roles and Responsibilities - The name(s) of the individual(s) who will perform the inspection.
III. Specific Quality Control Functions:
A. Plans that identifies all assignments for each pickup.
B. An annual schedule for all pickups by dates and areas for each piece of container.
C. A system for identifying and correcting deficiencies in the quality of services performed before the level of performance becomes unacceptable and/or the Government inspectors point out the deficiencies.
D. An inspection system that covers all the service requirements of the contract. A checklist used in inspecting contract performance during regularly scheduled or unscheduled inspections. The name(s) of the individual(s) who will perform the inspection.
E. A file of all inspections conducted by the contractor and the corrective action taken. This documentation shall be available to the COR/Contracting Officer during the term of the contract.
F. Waste Management (including recycling) G. Security & Safety Compliance w/OSHA H. Compliance with EPA
IV. Contingencies for Emergency Situations - Procedures to be used; obtaining additional employees.
8.5 Performance Evaluation Meeting. The Contractor may be required to meet at least weekly with the COR the first two months of the contract. Thereafter, meetings will be held as often as necessary, as determined by the COR. However, if the contractor requests, a meeting will be held whenever a Contract Discrepancy Report is issued. The written minutes of these meetings will be prepared by the COR and shall be signed by the Contractor and COR, and whoever else is in attendance. Should the contractor not concur with the minutes, the contractor shall so state any areas of non-concurrence, in writing, to the COR/Contracting Officer within 10 calendar days of receipt of the signed minutes.