Att_1_-_Specifications.pdf
PDF 168 KB Posted
- Solicitation number
- 140L0624R0038
About this file
This document contains the specifications for the Morgan Bridge Riparian Restoration Design-Build project, related to the federal contract opportunity solicitation number 140L0624R0038.
The key details are:
- The contractor is responsible for designing and constructing riverbank stabilization, riverbank recontouring, riparian vegetation plantings, and replacement of an existing culvert with a fish-friendly structure capable of supporting vehicular traffic.
- The work will take place on BLM-managed lands in the Morgan Bridge Riparian Restoration Project area in Bingham County, Idaho.
- The period of performance is 485 calendar days after the notice to proceed.
- The contractor must submit design plans in phases for government review and approval, obtain required permits, and provide as-built drawings.
- The contractor shall provide warranties for all materials and equipment furnished under the contract.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MORGAN BRIDGE RIPARIAN RESTORATION
DESIGN‐BUILD SPECIFICATIONS
PART 1: GENERAL
1.1. SUMMARY
A. Description of Work: All work shall occur in the BLM, Idaho Falls District, Pocatello Field Office, Morgan Bridge Riparian Restoration Project Area. The Contractor is responsible for furnishing labor, equipment, supplies, and materials to design and construct riverbank stabilization, riverbank recontouring, riparian vegetation plantings, and replacement of an existing culvert with a fish friendly structure capable of withstanding vehicular traffic.
1. Bank Stabilization: Design and construct bank stabilization and rehabilitation plan. The
Contractor shall be responsible for identifying areas in need of stabilization along the riverbank within the project location. The Contractor shall submit the identified areas for Government selection and approval. Work shall be focused on BLM managed lands within the Morgan Bridge Riparian Restoration Project north of Morgan Bridge Campground. Design shall not exclusively include traditional hardened armoring of the riverbank to diminish the erosion along the acquired parcel. The design shall focus on non‐traditional non‐hardened armoring bank stabilization methods and vegetation plantings to alleviate erosive pressures located along the river’s bank.
The Contractor is responsible for the following:
a. Performing a site survey of the riverbank and channel along the Blackfoot River within the boundaries of the Morgan Bridge Riparian Restoration Project Area as identified on included maps,
b. Ensuring that all work is conducted on BLM managed lands, and
c. Filing for and obtaining appropriate permits for in‐stream work, such as the
USACE 404 permit.
2. Bank Recontouring: Design and construct riverbank recontouring and rehabilitation along the BLM, Idaho Falls District, Pocatello Field Office, Morgan Bridge Riparian Restoration Project Area north of Morgan Bridge Campground. The Contractor shall be responsible for identifying areas in need of recontouring along the riverbank within the project location. The Contractor shall submit the identified areas for Government selection and approval. The design shall focus on recontouring the existing riverbank and vegetation plantings to alleviate erosive pressures located along the river’s bank.
The Contractor is responsible for the following:
a. Performing a site survey of the riverbank and channel along the Blackfoot River within the boundaries of the Morgan Bridge Riparian Restoration Project Area as identified on included maps,
b. Ensuring that all work is conducted on BLM managed lands, and
c. Filing for and obtaining appropriate permits for in‐stream work, such as the
USACE 404 permit.
3. Riparian Vegetation Plantings: Design and install riparian vegetation plantings. The Contractor shall be responsible for identifying areas in need of vegetation plantings along the riverbank within the project location. The Contractor shall submit the identified areas for Government selection and approval. Plantings may consist of approved herbaceous and/or woody species. Riparian vegetation plantings may be completed in concert with either bank stabilization and/or bank recontouring work, though is not limited to those locations.
4. Culvert Replacement: Remove existing culvert and design and construct a fish friendly structure capable of supporting full sized vehicular use.
The Contractor is responsible for ensuring that all work conducted and infrastructure installed is on BLM managed lands.
B. Location: Work under this contract is located in Bingham County, approximately 23 miles Southeast of Blackfoot, Idaho near the intersection of the Blackfoot River Road and Lincoln Creek Road. Site entrance coordinates, 111.9269204° W, 43.0600066° N. The work locations are shown on the maps.
C. Period of Performance: 485 Calendar Days after the issuance of the Notice to Proceed (NTP).
Local conditions (weather conditions, road conditions, etc.) that may affect work are included in the performance period. Contractor shall coordinate work hours with the COR/CO 48 hours in advance of beginning work.
1.2. REFERENCES
A. Referenced Specifications/Standards with Abbreviations and/or Acronyms:
Migratory Bird Survey date reference: DOI. April 2012. U.S. Bureau of Land Management.
Record of Decision and Approved Pocatello Resource Management Plan. Idaho Falls District, Pocatello Field Office. Pocatello, Idaho.
Attachment 3: National Marine Fisheries Service: National Oceanic and Atmospheric Administration Northwest Region 2011. (Please see attached documents.)
Attachment 4: Design for Fish Passage at Roadway‐Stream Crossings: Federal Highway Administration 2007. (Please see attached documents.)
Attachment 5: H‐9113 – 1 – Roads Design Handbook: DOI. 10‐21‐2011. Bureau of Land Management. (Please see attached documents.)
1.3. DEFINITIONS
A. Approvals: Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Government's attention in writing. After approval of an item, submit a substitute for approval when the approved item cannot be purchased or delivered in time to avoid delay in completion of the project.
B. Acronyms: The following is a list of acronyms with their definition that are referenced in this project:
BLM Bureau of Land Management CO Contracting Officer COR Contracting Officer Representative SCR Special Contract Requirements USACE US Army Corp of Engineers
1.4. SUBMITTALS
A. Scope: Submittals include initial surveys, design specifications, final design drawings, as‐ built drawings, and manufacturers' literature or samples. Maximum size of drawings shall be no greater than 11”x17”.
B. Requirements: Refer to specifications for submittals required. Allow at least 10 working days for review. The Contractor is required to provide one (1) hard copy of each submittal and one electronic copy. Hard copy of the submittals shall be delivered to Jerry Burrows, 1405 Hollipark Drive, Idaho Falls, Idaho 83401. Electronic copies shall be emailed to the Government.
C. Identification of Submittals: Completely identify each submittal by showing at least the following information:
1. Name and address of submitter, plus name and telephone number of the individual to contact for further information.
2. Name of project as it appears in these specifications.
3. Contract number, drawing number, and specification section number to which the submittal applies.
4. Whether this is an original submittal or re‐submittal.
5. Each item shall clearly note the manufacturer's name and address, trade name, product, lot, style, color, catalog designation or model number, and locations of use.
1.5. CERTIFICATES OF CONFORMANCE
A. Requirements: The Contracting Officer may permit use, prior to sampling and testing, of materials when accompanied by Certificates of Conformance. Materials used on the basis of a Certificate of Conformance may be sampled and tested. Installation of materials on the basis of Certificates of Conformance shall not relieve the Contractor of responsibility for incorporating materials, which conform to the requirements of the drawings and specifications. Material not conforming to those requirements is subject to rejection, whether in place or not.
B. Format: The Certificate of Conformance provided by the supplier shall:
1. State that the named product conforms to the Contract requirements.
2. Either be accompanied with a certified copy of the test results or certify that such test results are on file with the manufacturer and is furnished to the Contracting Officer upon request.
3. Provide the name and address of the manufacturer, the testing agency, and the date of tests.
4. Set forth the means of identification, which will permit field determination of the product delivered as being the product covered by the certification.
1.6. QUALITY ASSURANCE
A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.
B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.
C. Measurements: Where approved manufacturer's diagrams and shop drawings give specific measurements or rough‐in dimensions for equipment, these dimensions shall take precedence over dimensions indicated on the drawings.
1.7. DELIVERY, STORAGE, AND HANDLING
A. Delivery: Protect products incorporated into the work from damage while in transit to the site. Products must be delivered in original unopened containers with manufacturer's name, brand designation, and contents legibly indicated.
B. Storage: Provide temporary storage facilities for products. Storage shall comply with the manufacturer's instructions. The storage area shall permit access for inspection and handling.
C. Handling: Load and unload products in a manner that protects them from damage.
1.8. PROJECT/SITE CONDITIONS
A. Access to the Work sites: Access is generally provided by two‐track trails; cross‐country travel is permitted for local access. Steep side slopes, rocks, and brush will make some sections of the riverbank inaccessible to highway vehicles. Where access to work crosses private property, potentially the northeast portion of the Blackfoot River Corridor, the Contractor is responsible to obtain permission for access.
1.9. SEQUENCING AND SCHEDULING
A. Work Schedule: The schedule shall be submitted at the pre‐work conference. When requested, submit an updated schedule within 3 calendar days. As a minimum, the estimated start and completion dates shall be shown in the estimate.
B. Timing of in‐water work will occur only within the preferred work window of September 1 through April 30.
C. The Contractor shall notify the Government if ground disturbing activities within the project area will occur between February 1 through August 15. Ground disturbing activities within listed dates shall have a migratory bird survey completed by the Government within 7 working days.
PART 2: PRODUCTS
Section N/A
PART 3: EXECUTION
3.1 PROJECT MEETINGS
A. Pre‐Work Conference:
1. A Pre‐Work Conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
2. The Contractor, subcontractors, and the persons responsible for coordination of the work shall be present at the meeting.
3. Be prepared to summarize and explain procedures planned for the project and present the submittals requested in the specifications.
B. Progress Meetings:
1. To be held at the project site, or as determined by the government.
2. May be called by either the government or the Contractor. Request shall state who should attend and include an agenda.
C. Final Inspection:
1. To be held at the project site, or as determined by the government.
2. Notify the government in writing at least 5 working days before the completion date so the Government can schedule final inspection.
3. The superintendent shall be present during this inspection.
3.2 SURVEY
A. Requirements: The Contractor shall be responsible for identifying areas to perform topographical surveys for design needs. Areas for the topographical surveys shall include the Blackfoot River riverbank, river channel, and replacement culvert location within the Project Area. Locations for surveys of the bank stabilization, bank recontouring, and culvert replacement can be found on the corresponding attached maps. The Contractor is required to set at least two permanent control points that will be referenced in the design and used during construction. Survey monuments or benchmarks disturbed or removed during construction shall be reset by the Contractor at the Contractor's expense.
B. Design: The Contractor shall develop design plans. The Contractor shall submit the design plans to the government within the following allotted days for review and approval of each design element listed (3.3 to 3.6):
1. NTP to 30% ‐ 90 days
2. 30% to 60% ‐ 45 days
3. 60% to 95% ‐ 90 days
4. 95% to 100% ‐ 45 days
The Contractor shall use the design plans to prepare a USACE 404 permit application, and any other required permits, allowing for sufficient time for USACE permit review and approval before the anticipated start of construction. Final plans shall be stamped by a registered Professional Engineer in the State of Idaho.
C. Submittal: The Contractor is required to submit an AutoCAD Civil3D .dwg file, and .txt file of the surveys to the Government for approval.
3.3 BANK STABILIZATION DESIGN
A. Plans: Bank Stabilization designs shall include a plan which includes the kind, number, and location of bank stabilization structures proposed. Bank stabilization may occur on either bank throughout the Project Area on BLM managed lands north of Morgan Bridge. The designs plans shall, at a minimum, include the following:
1. Existing Site Plan
2. Proposed Site Plan
3. Flood Plain Details
4. Constructed Channel Element Details
3.4 BANK RECONTOURING DESIGN
A. Plans: Bank recontouring may occur on either bank throughout the Project Area on BLM managed lands north of Morgan Bridge. These plans may be submitted in conjunction with the Bank Stabilization Design. The designs plans shall, at a minimum, include the following:
1. Existing Site Plan
2. Proposed Site Plan
3. Flood Plain Details
4. Constructed Channel Element Details
3.5 RIPARIAN VEGETATION PLANTING DESIGN
A. Plans: Riparian vegetation plantings may occur on either bank throughout the Project Area on BLM managed lands north of Morgan Bridge. Riparian vegetation plans and plantings may be completed in concert with either the bank stabilization and/or the bank recontouring work, though is not limited to those locations. The design plans shall, at a minimum, include the following:
1. Proposed Site Plan
2. List of Proposed Riparian Species Intended for Use on Site
3. Constructed Riparian Vegetation Planting Details
3.6 CULVERT REPLACEMENT DESIGN
A. Plan: Contractor shall develop design and plan for the removal of and replacement of existing culvert on Deadman Creek using reference Attachments 3, 4, and 5. Replacement structure must be fish friendly (i.e., open bottom culvert and be capable of supporting and allowing for travel by full sized vehicles). The design shall, at a minimum, include the following:
1. Proposed Site Plan
2. Constructed Culvert Replacement Details
3.7 GENERAL CONSTRUCTION
A. The contractor is responsible for ensuring that all work is conducted on, and infrastructure is installed on BLM managed lands.
B. Permits: The Contractor will submit a USACE 404 permit application, and any other required permits. The Contractor’s design and construction shall comply with all requirements of the 404 permit.
C. Health and Safety Plan: Before construction commences, the Contractor shall submit a health and safety plan to the government for approval. The health and safety plan shall include the location of the nearest hospital and procedures to follow in case of an emergency.
D. Disposal of debris: Debris shall become the property of the Contractor. Dispose of materials in a legal manner and payment of fees required is the Contractor's responsibility.
Sale of material onsite is not allowed unless authorized in writing by the government.
Burning of removed materials is not permitted on the work site. Disposal of woody debris, such as shrubs and limbs, may be disposed of by scattering.
E. As‐Built Drawings: The Contractor is required to keep a full‐sized copy of the design plans on‐site throughout the duration of the project. As the job progresses, continuously maintain as‐built drawings of the work. The changes shall be noted legibly in red pencil or red ink. These drawings shall be submitted to the government prior to final inspection. Should final inspection reveal changes in the project not so noted on the as‐ built drawings, record these changes on the as‐built drawings within 5 working days of final inspection and deliver completed as‐built drawings to the government.
3.8 WARRANTY
A. Requirements: Materials and equipment furnished under this Contract shall be covered by the most favorable commercial warranties given to customers for such materials or equipment. The rights or remedies provided herein are in addition to and do not limit rights afforded to the Government by other clauses of this Contract. With respect to warranties, expressed or implied, from manufacturers or suppliers for materials or equipment furnished under the Contract the Contractor shall:
1. Obtain warranties that would be given in normal commercial practices.
2. Require warranties to be executed, in writing, for the benefit of the Government.
3. Submit warranties to the government prior to the final inspection.
| A. Referenced Specifications/Standards with Abbreviations and/or Acronyms: |
| Migratory Bird Survey date reference: DOI. April 2012. U.S. Bureau of Land Management. Record of Decision and Approved Pocatello Resource Management Plan. Idaho Falls District, Pocatello Field Office. Pocatello, Idaho. |
| Attachment 3: National Marine Fisheries Service: National Oceanic and Atmospheric Administration Northwest Region 2011. (Please see attached documents.) |
| Attachment 4: Design for Fish Passage at Roadway-Stream Crossings: Federal Highway Administration 2007. (Please see attached documents.) |
| Attachment 5: H-9113 – 1 – Roads Design Handbook: DOI. 10-21-2011. Bureau of Land Management. (Please see attached documents.) |
| A. Plans: Riparian vegetation plantings may occur on either bank throughout the Project Area on BLM managed lands north of Morgan Bridge. Riparian vegetation plans and plantings may be completed in concert with either the bank stabilization and/or the... |
| 1. Proposed Site Plan |
| 2. List of Proposed Riparian Species Intended for Use on Site |
| 3. Constructed Riparian Vegetation Planting Details |
| A. Plan: Contractor shall develop design and plan for the removal of and replacement of existing culvert on Deadman Creek using reference Attachments 3, 4, and 5. Replacement structure must be fish friendly (i.e., open bottom culvert and be capable of... |
| 1. Proposed Site Plan |
| 2. Constructed Culvert Replacement Details |