Att_1_SOW__Const_Install_11_27_2023_redacted_2_1.pdf

PDF 150 KB Posted

Attached to
WY-Buffalo Bill Shop Power Service Install
Solicitation number
140R6024Q0028
Issued by

About this file

This document outlines a federal contract opportunity for electrical utility installation services. The Bureau of Reclamation intends to award a sole source, firm fixed price purchase order to the local utility company to connect the Bureau's Buffalo Bill Maintenance Shop in Wyoming to the utility's nearby electrical lines. The utility company is considered the sole source able to complete the work as they are the sole provider of electricity in the Buffalo Bill area. Interested parties may identify their interest and capabilities by February 5, 2024 to be considered, though the work will be awarded non-competitively due to the utility's sole source status. The installation must be completed within 60 days of award and involves installing transformers, meters, underground cabling and associated equipment to provide power to the maintenance shop.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Electrical Service WY - BHB Buffalo Bill Maintenance Shop Utilities

1.0 Background

Electrical services, provided by ... are required at the Bureau of Reclamation’s facilities located Buffalo Bill Project, Wyoming Area Office.

2.0 Scope

The Bureau of Reclamation requires connection of an electric line and all associated hardware and equipment to receive electricity services from .... The Contractor shall install and deliver all hardware and electrical equipment necessary to connect the Buffalo Bill Maintenance Shop to the existing ... electrical utility lines. The work performed by the Contractor shall include removal of the pullbox, nstallation of 35KV 3PH UG SECTIONALIZER, 100' 3PH I/0- AL 35KV UG PRIMARY, 300KVA 34.5KV 3PH 480V TRANS, 600 MP CT Meter, and (2) 100' Runs of 350-QX UG Service. The installation and hardware shall conform to the specifications in Attachment #1, Placement of Line and Attachment #2 .

3.0 Delivery

The electrical line and all associated hardware and equipment shall be delivered and installed no later than 60 days from award of purchase order.

4.0 Period of Performance

60 Days from award of Purchase Order.