ATT 1 SCHEDULE OF ITEMS.xlsx
XLSX spreadsheet 31 KB Posted
- Solicitation number
- 12363N25Q4040
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Schedule of Items spreadsheet for a dredging project at the Munising Ranger District/Hiawatha National Forest spanning 2025-2029. The project involves annual dredging work scheduled for approximately one month each spring (late April to late May) over five years, with consistent requirements each year.
The scope includes dredging of a main path (1,100 cubic yards) and passenger ferry areas (40 cubic yards), with requirements for turbidity curtain installation, material stockpiling in 13-15 foot high piles, and four barge runs per year for the main path. Three optional items are included each year: admin dock installation (36' x 5' dock), admin dock removal, and admin dock adjustment to accommodate lake levels. The work is administered by the USDA Forest Service, with dredged amounts to be verified by Forest Service Engineering Staff surveys. The project is set aside for small businesses under NAICS 237990 with a size standard of $37 million, and quotes will be accepted starting around March 3, 2025, with no bid bonds required for quotes under $150,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATT 2 STATEMENT OF WORK.pdf | ||
| 12363N25Q4040 HIA Grand Island Dredging.pdf | ||
| ATT 5 Wage Determination.pdf | ||
| ATT 3 PLANS.pdf | ||
| ATT 4 VICINITY MAPS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DREDGING 2025 SCHEDULE
SCHEDULE OF ITEMS / BID FORM
MUNISING RANGER DISTRICT/HIAWATHA NATIONAL FOREST/DREDGING PROJECT
| Period of Performance | 28APR2025--21MAY2025 | ||||||
| Anticipated Start Date | 29APR2025 | ||||||
| SCHEDULE OF ITEMS / BID FORM | |||||||
| ITEM | |||||||
| NUMBER | DESCRIPTION | PAY UNIT | EST QTY | UNIT PRICE | EXTENDED PRICE | ||
| Dredging Main Path | |||||||
| 1001AA | Mobilization | Lump Sum | 1 | ||||
| 1001AB | Set up/removal turbidity curtain and silt fence | Lump Sum | 1 | ||||
| 1001AC* | Hauled and pushed into piles no less than 13 feet high and no more than 15 ft high at designated spoils locations | Cubic Yard | 1100 | ||||
| 1001AD* | Dredging and stockpiling | Cubic Yard | 1100 | ||||
| 1001AE | Barge Runs | Each | 4 | ||||
| Main Path Total | $ | ||||||
| Dredging Passenger Ferry Areas | |||||||
| 1001AF | Mobilization (Accomplished during dredging) | Lump Sum | 1 | Are we allowing MOB line item for this or would it be incidental to the Main Path Dredging? | |||
| 1001AG | Set up/removal turbidity curtain | Lump Sum | 1 | ||||
| 1001AH* | Hauled and pushed into piles no less than 13 feet high and no more than 15 ft high at designated spoils locations | Cubic Yard | 40 | ||||
| 1001AI* | Dredging and stockpiling | Cubic Yard | 40 | ||||
| 1001AJ | Barge Runs | Each | 0 | Are there Barge Runs for this area? | |||
| Passenger Ferry Total | $ | ||||||
| *Option Item A - Admin Dock Installation | |||||||
| 1002AA | Install 36’ x 5’ dock and adjust legs to allow for easy | ||||||
| loading and unloading of the Forest Service vessel. | Lump Sum | 1 | |||||
| *Option Item B - Admin Dock Removal | |||||||
| 1002AB | Mobilization | Lump Sum | 1 | ||||
| 1002AC | Remove 36’ x 5’ dock from landing and stage at specified | ||||||
| location following public closure for the season. | Lump Sum | 1 | |||||
| *Option Item C - Admin Dock Adjustment | |||||||
| 1002AD | Adjust legs of already in place admin dock to accommodate | ||||||
| fluctuating lake levels. | Lump Sum | 1 | |||||
| 2025 OPTION TOTALS | $ | ||||||
| 2025 BASE TOTALS | $ | ||||||
| 2025 GRAND TOTAL | $ | ||||||
| *-Dredged amount will be based upon survey data performed by US Forest Service Engineering Staff |
DREDGING 2026 SCHEDULE
SCHEDULE OF ITEMS / BID FORM
MUNISING RANGER DISTRICT/HIAWATHA NATIONAL FOREST/DREDGING PROJECT
| Period of Performance | 27APR2026--26MAY2026 | |||||
| Anticipated Start Date | 28APR2026 | |||||
| SCHEDULE OF ITEMS / BID FORM | ||||||
| ITEM | ||||||
| NUMBER | DESCRIPTION | PAY UNIT | EST QTY | UNIT PRICE | EXTENDED PRICE | |
| Dredging Main Path | ||||||
| 2001AA | Mobilization | Lump Sum | 1 | |||
| 2001AB | Set up/removal turbidity curtain and silt fence | Lump Sum | 1 | |||
| 2001AC* | Hauled and pushed into piles no less than 13 feet high and no more than 15 ft high at designated spoils locations | Cubic Yard | 1100 | |||
| 2001AD* | Dredging and stockpiling | Cubic Yard | 1100 | |||
| 2001AE | Barge Runs | Each | 4 | |||
| Main Path Total | $ | |||||
| Dredging Passenger Ferry Areas | ||||||
| 2001AF | Mobilization (Accomplished during dredging) | Lump Sum | 0 | |||
| 2001AG | Set up/removal turbidity curtain | Lump Sum | 1 | |||
| 2001AH* | Hauled and pushed into piles no less than 13 feet high and no more than 15 ft high at designated spoils locations | Cubic Yard | 40 | |||
| 2001AI* | Dredging and stockpiling | Cubic Yard | 40 | |||
| 2001AJ | Barge Runs | Each | 0 | |||
| Passenger Ferry Total | $ | |||||
| *Option Item A - Admin Dock Installation | ||||||
| 2002AA | Install 36’ x 5’ dock and adjust legs to allow for easy | |||||
| loading and unloading of the Forest Service vessel. | Lump Sum | 1 | ||||
| *Option Item B - Admin Dock Removal | ||||||
| 2002AB | Mobilization | Lump Sum | 1 | |||
| 2002AC | Remove 36’ x 5’ dock from landing and stage at specified | |||||
| location following public closure for the season. | Lump Sum | 1 | ||||
| *Option Item C - Admin Dock Adjustment | ||||||
| 2002AD | Adjust legs of already in place admin dock to accommodate | |||||
| fluctuating lake levels. | Lump Sum | 1 | ||||
| 2026 OPTION TOTALS | $ | |||||
| 2026 BASE TOTALS | $ | |||||
| 2026 GRAND TOTAL | $ | |||||
| *-Dredged amount will be based upon survey data performed by US Forest Service Engineering Staff |
DREDGING 2027 SCHEDULE
SCHEDULE OF ITEMS / BID FORM
MUNISING RANGER DISTRICT/HIAWATHA NATIONAL FOREST/DREDGING PROJECT
| Period of Performance | 26APR2027--25MAY2027 | |||||
| Anticipated Start Date | 27APR2027 | |||||
| SCHEDULE OF ITEMS / BID FORM | ||||||
| ITEM | ||||||
| NUMBER | DESCRIPTION | PAY UNIT | EST QTY | UNIT PRICE | EXTENDED PRICE | |
| Dredging Main Path | ||||||
| 3001AA | Mobilization | Lump Sum | 1 | |||
| 3001AB | Set up/removal turbidity curtain and silt fence | Lump Sum | 1 | |||
| 3001AC* | Hauled and pushed into piles no less than 13 feet high and no more than 15 ft high at designated spoils locations | Cubic Yard | 1100 | |||
| 3001AD* | Dredging and stockpiling | Cubic Yard | 1100 | |||
| 3001AE | Barge Runs | Each | 4 | |||
| Main Path Total | $ | |||||
| Dredging Passenger Ferry Areas | ||||||
| 3001AF | Mobilization (Accomplished during dredging) | Lump Sum | 0 | |||
| 3001AG | Set up/removal turbidity curtain | Lump Sum | 1 | |||
| 3001AH* | Hauled and pushed into piles no less than 13 feet high and no more than 15 ft high at designated spoils locations | Cubic Yard | 40 | |||
| 3001AI* | Dredging and stockpiling | Cubic Yard | 40 | |||
| 3001AJ | Barge Runs | Each | 0 | |||
| Passenger Ferry Total | $ | |||||
| *Option Item A - Admin Dock Installation | ||||||
| 3002AA | Install 36’ x 5’ dock and adjust legs to allow for easy | |||||
| loading and unloading of the Forest Service vessel. | Lump Sum | 1 | ||||
| *Option Item B - Admin Dock Removal | ||||||
| 3002AB | Mobilization | Lump Sum | 1 | |||
| 3002AC | Remove 36’ x 5’ dock from landing and stage at specified | |||||
| location following public closure for the season. | Lump Sum | 1 | ||||
| *Option Item C - Admin Dock Adjustment | ||||||
| 3002AD | Adjust legs of already in place admin dock to accommodate | |||||
| fluctuating lake levels. | Lump Sum | 1 | ||||
| 2027 OPTION TOTALS | $ | |||||
| 2027 BASE TOTALS | $ | |||||
| 2027 GRAND TOTAL | $ | |||||
| *-Dredged amount will be based upon survey data performed by US Forest Service Engineering Staff |
DREDGING 2028 SCHEDULE
SCHEDULE OF ITEMS / BID FORM
MUNISING RANGER DISTRICT/HIAWATHA NATIONAL FOREST/DREDGING PROJECT
| Period of Performance | 24APR2028--24MAY2028 | |||||
| Anticipated Start Date | 25APR2028 | |||||
| SCHEDULE OF ITEMS / BID FORM | ||||||
| ITEM | ||||||
| NUMBER | DESCRIPTION | PAY UNIT | EST QTY | UNIT PRICE | EXTENDED PRICE | |
| Dredging Main Path | ||||||
| 4001AA | Mobilization | Lump Sum | 1 | |||
| 4001AB | Set up/removal turbidity curtain and silt fence | Lump Sum | 1 | |||
| 4001AC* | Hauled and pushed into piles no less than 13 feet high and no more than 15 ft high at designated spoils locations | Cubic Yard | 1100 | |||
| 4001AD* | Dredging and stockpiling | Cubic Yard | 1100 | |||
| 4001AE | Barge Runs | Each | 4 | |||
| Main Path Total | $ | |||||
| Dredging Passenger Ferry Areas | ||||||
| 4001AF | Mobilization (Accomplished during dredging) | Lump Sum | 0 | |||
| 4001AG | Set up/removal turbidity curtain | Lump Sum | 1 | |||
| 4001AH* | Hauled and pushed into piles no less than 13 feet high and no more than 15 ft high at designated spoils locations | Cubic Yard | 40 | |||
| 4001AI* | Dredging and stockpiling | Cubic Yard | 40 | |||
| 4001AJ | Barge Runs | Each | 0 | |||
| Passenger Ferry Total | $ | |||||
| *Option Item A - Admin Dock Installation | ||||||
| 4002AA | Install 36’ x 5’ dock and adjust legs to allow for easy | |||||
| loading and unloading of the Forest Service vessel. | Lump Sum | 1 | ||||
| *Option Item B - Admin Dock Removal | ||||||
| 4002AB | Mobilization | Lump Sum | 1 | |||
| 4002AC | Remove 36’ x 5’ dock from landing and stage at specified | |||||
| location following public closure for the season. | Lump Sum | 1 | ||||
| *Option Item C - Admin Dock Adjustment | ||||||
| 4002AD | Adjust legs of already in place admin dock to accommodate | |||||
| fluctuating lake levels. | Lump Sum | 1 | ||||
| 2028 OPTION TOTALS | $ | |||||
| 2028 BASE TOTALS | $ | |||||
| 2028 GRAND TOTAL | $ | |||||
| *-Dredged amount will be based upon survey data performed by US Forest Service Engineering Staff |
DREDGING 2029 SCHEDULE
SCHEDULE OF ITEMS / BID FORM
MUNISING RANGER DISTRICT/HIAWATHA NATIONAL FOREST/DREDGING PROJECT
| Period of Performance | 23APR2029--23MAY2029 | |||||
| Anticipated Start Date | 24APR2029 | |||||
| SCHEDULE OF ITEMS / BID FORM | ||||||
| ITEM | ||||||
| NUMBER | DESCRIPTION | PAY UNIT | EST QTY | UNIT PRICE | EXTENDED PRICE | |
| Dredging Main Path | ||||||
| 5001AA | Mobilization | Lump Sum | 1 | |||
| 5001AB | Set up/removal turbidity curtain and silt fence | Lump Sum | 1 | |||
| 5001AC* | Hauled and pushed into piles no less than 13 feet high and no more than 15 ft high at designated spoils locations | Cubic Yard | 1100 | |||
| 5001AD* | Dredging and stockpiling | Cubic Yard | 1100 | |||
| 5001AE | Barge Runs | Each | 4 | |||
| Main Path Total | $ | |||||
| Dredging Passenger Ferry Areas | ||||||
| 5001AF | Mobilization (Accomplished during dredging) | Lump Sum | 0 | |||
| 5001AG | Set up/removal turbidity curtain | Lump Sum | 1 | |||
| 5001AH* | Hauled and pushed into piles no less than 13 feet high and no more than 15 ft high at designated spoils locations | Cubic Yard | 40 | |||
| 5001AI* | Dredging and stockpiling | Cubic Yard | 40 | |||
| 5001AJ | Barge Runs | Each | 0 | |||
| Passenger Ferry Total | $ | |||||
| *Option Item A - Admin Dock Installation | ||||||
| 5002AA | Install 36’ x 5’ dock and adjust legs to allow for easy | |||||
| loading and unloading of the Forest Service vessel. | Lump Sum | 1 | ||||
| *Option Item B - Admin Dock Removal | ||||||
| 5002AB | Mobilization | Lump Sum | 1 | |||
| 5002AC | Remove 36’ x 5’ dock from landing and stage at specified | |||||
| location following public closure for the season. | Lump Sum | 1 | ||||
| *Option Item C - Admin Dock Adjustment | ||||||
| 5002AD | Adjust legs of already in place admin dock to accommodate | |||||
| fluctuating lake levels. | Lump Sum | 1 | ||||
| 2029 OPTION TOTALS | $ | |||||
| 2029 BASE TOTALS | $ | |||||
| 2029 GRAND TOTAL | $ | |||||
| *-Dredged amount will be based upon survey data performed by US Forest Service Engineering Staff |