Att 1 - Frequency Converter Repair SOW.pdf

PDF 118 KB Posted

Attached to
Troubleshoot Frequency Converter
Solicitation number
FA452826QPKB7
Issued by

About this file

This is a Statement of Work (SOW) for the repair of a Piller Power Systems Solid State APOJET AJS static frequency converter at Minot Air Force Base, North Dakota, dated 5 August 2026. The contractor must provide all management, tools, specialized equipment, supplies, technical data, and labor necessary to inspect, troubleshoot, and repair the frequency converter, model AJS C8-1R-90-480/200-6/40-G-B (serial #9506019540), which currently displays an Earthing Failure code R0704 and No Load Delay Start code E0957. The converter has a 480V, 3-phase, 60 Hz input and a 200/115V 3-phase, 400Hz, 90 kVA output. All work must comply with the manufacturer's specifications.

The contractor must perform exterior housing inspection for deterioration, troubleshoot and repair identified fault codes, and conduct an operations test following manufacturer-approved procedures to verify correct output. The Government will provide an appropriate receptacle for testing. The contractor must submit documentation of all required repairs, completed work, and applicable warranties; any repairs beyond the initial fault codes require Government and contracting officer approval before proceeding. Contractor employees must possess qualified experience with the 400 Hz AJS frequency converter. Work must be scheduled within 14 days of contract award and completed within seven working days from start. Normal operating hours are Monday through Friday, 8:00 a.m. to 4:00 p.m., excluding federal holidays. The contractor is responsible for daily site cleanup, off-base disposal of waste and unserviceable parts in compliance with Federal, State, local, and base environmental laws, and hazardous waste disposal coordination with the Government. Personnel accessing Minot AFB must present current REAL ID-compliant identification, state-issued identification, or U.S. passport, along with current automobile insurance and vehicle registration documentation. Contractor personnel are restricted to work areas only and cannot enter restricted areas without authorized escort.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

DOCK 8 FREQUENCY CONVERTER REPAIR

MINOT AFB, ND

5 August 2026

1.0 DESCRIPTION OF SERVICES. The contractor will provide all management, tools, specialized equipment, supplies, technical data, and labor necessary to inspect, troubleshoot, and repair a Piller Power

Systems Solid State APOJET AJS static frequency converter, serial # 9506019540. All work must be in accordance with the manufacturer’s specifications.

2.0. REQUIREMENTS.

2.1. Troubleshoot and Repair. The Contractor will troubleshoot and repair faults and error codes on the

AJS C8-1R-90-480/200-6/40-G-B frequency converter with a 480V, 3 phase, 60 Hz input and a 200/115V

3 phase, 400Hz, and 90 kVA output. The frequency converter is currently showing an Earthing Failure code R0704 and No Load Delay Start code E0957. The discovery of any issue requiring extensive parts or labor beyond the initial fault codes will be presented to the Government for approval before proceeding.

2.2. Inspection and Operations Test. The Contractor will perform an exterior inspection of the housing for any deterioration. Upon completion of inspection, the Contractor will follow the manufacturer’s approved procedures to perform an operations test. The operations test will consist of the testing of the frequency converter on an appropriate receptacle to ensure correct output. In the event further repairs are required, approval shall be coordinated with the Government and contracting officer prior to proceeding.

The Government will provide appropriate receptacle for testing.

2.3. Parts and Repair Documentation. The contractor will provide documentation identifying all required repairs and upgrades as well as any repairs and upgrades completed and applicable warranties provided. Any required repairs that are outside the scope of this contract must be coordinated with the

Contracting Officer. No additional repairs may be completed without a modification to this contract.

3.0. MANAGEMENT.

3.1. Contractor Employees. The contractor employees must be qualified to work on and possess the required experience to work on the 400 Hz AJS C8-1R-90-480/200-6/40-G-B frequency converter listed in this SOW. The contractor shall ensure the work is completed to the manufacturer’s specifications.

3.2. Hours of Work. Normal operating hours of the site are Monday through Friday, 8:00 a.m. to 4:00 p.m., excluding federal holidays.

3.3. Schedule. Work will be scheduled within 14 days of contract award. Work must be completed within seven (7) working days from work start.

3.4. Site Cleanup and Waste Disposal. The contractor will ensure the worksite is cleared of all debris and surplus material at the end of each working day. Equipment and materials required to complete the work effort may remain on site if they are organized/ stored in a manner that does not cause a safety hazard. The contractor will dispose of waste to include unserviceable parts from this project off base and

IAW Federal, State, local, and base environmental laws, and regulations. Disposal of any hazardous waste must be coordinated with the Government POC.

3.5. Installation Access and Security. A current REAL ID-compliant driver’s license, state-issued identification card, or U.S. passport, and a current automobile insurance document and vehicle registration will be required to a to gain access to Minot AFB. Contract personnel will not enter restricted areas without escort from authorized personnel. The contractor must restrict personnel to only those areas required to perform work.