Att 02_SOW and Specifications (250515).pdf
PDF 439 KB Posted
- Attached to
- Kawishiwi Garage roof repair
- Solicitation number
- 12445525Q0066
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a detailed specifications file for the Kawishiwi Garage Roof Replacement Project 2025 located in the Superior National Forest, St. Louis County, Minnesota. The project involves completely replacing the roof of the Kawishiwi District Office fleet garage, which has been experiencing leaks during spring melt and rainfall events. The scope of work includes removing all existing asphalt shingle roofing, underlayment, vents, and other components, and installing new roofing materials from GAF, including Timberline UHDZ shingles in Weathered Wood color, Timbertex ridge shingles, ridge vents, ice and water shield, drip edge, and roof decking.
Key specifications include a 90-day contract completion timeline, work limited to Monday-Friday from 8 a.m. to 4:30 p.m., and compliance with 2021 International Building Codes and OSHA regulations. The estimated quantities include 113 squares of shingles, 160 linear feet of ridge cap shingles, 156 linear feet of ridge vent, and 96 square feet of roof decking. Additional requirements include daily cleanup, use of a magnet to remove nails, disposal of debris in a licensed landfill, and payment of Davis Bacon wages. Final payment is contingent on submitting certified payroll, a contract release form, and a landfill receipt.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Att 03_Wage Rates (250613).pdf | ||
| Att 01_Schedule of Items (250728).docx | DOCX document | |
| Sol_12445525Q0066.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KAWISHIWI GARAGE ROOF
REPLACEMENT PROJECT 2025
SPECIFICATIONS
SUPERIOR NATIONAL FOREST
ST. LOUIS COUNTY, MINNESOTA
Background
The Kawishiwi Ranger District within the Superior National Forests has a need to replace its fleet garage roof located in Kawishiwi, MN. The roof has been leaking in several different locations during spring melt and rainfall events.
PART 1 GENERAL
1.01 SUMMARY
A. Description of Work:
1. Work Covered by Contract Documents:
a. Provide for and furnish all labor, superintendence, materials, tools, equipment, transportation, certificates, insurance, temporary protection, and other items designated under provisions of this contract necessary to completely reroof with new materials the roof at the following location:
Kawishiwi District Office 1393 Highway 169 Ely, MN 55731
b. The project shall consist of removing all existing asphalt shingle roofing, underlayment materials, vents, drip edge, valley flashing, rotted fascia etc.
and removal and proper disposal of all debris from the sites. The contractor shall inspect with the COR (Contracting Officer’s Representative) all existing conditions of the roof. Contractor is to supply sufficient decking material to repair 96 square feet of plywood roof deck where needed. If new substrate boards and/or framing more than 96 square feet is required, the COR shall prepare a change order for CO approval prior to any change order work being performed. Contractor shall provide and install ice and water shield, felt, drip edge, shingles, sheathing clips, and incidentals needed to provide a finished project. New roofing materials shall not be installed on defective or rotten members. The deck must be smooth, dry, and free of surface imperfections when the new roofing materials are applied. Repairs, if any, shall be made to the existing roof surface to ensure an adequate substrate for the new roofing.
Manufactures application instructions shall be followed. All exposed roofs must be covered every night and in bad weather to protect the roof boards and structure underneath. See below for a more detailed explanation for the Description of Work and the Estimated Quantities.
Specifications
Contract to be completed by: 90 days after the award of the contract.
Hours of operation are limited to Monday-Friday from 8 a.m. and 4:30 p.m.
No work shall be performed on a Federal holiday.
All work shall meet Manufacturers Specifications, the 2021 International Building Codes, and Forest Service Specifications. In the case of conflict use the requirement which is more protective. Copies of manufacturers product specifications and installation instructions shall be submitted to the CO prior to the start of work.
All work shall be performed in compliance with OSHA Regulations.
Work area shall be cleaned up at the end of each workday. Sidewalks shall be cleaned of debris continuously. A magnet shall be used to remove all nails/staples from the grounds daily and at the end of the project.
All employees working on project shall be paid in accordance with applicable Department of Labor Regulations Davis Bacon Wages which are attached to this bid package.
Remove all existing roofing material from the roof down to the roof deck to correctly install the new roofing material. Disposal of ALL debris from the project shall be at the Contractor’s expense and shall be disposed of in a licensed landfill or recycling facility. A copy of the receipt(s) shall be provided for the CO’s records.
Inspect substrate and framing and bring to the attention of CO any problems. Do not install any new roofing products until approval is received from CO or designated inspector/representative.
Shingles will only be permitted to be installed in a diagonal pattern that corresponds with the manufacturer’s installation instructions.
Preapproved products are listed below. If the contractor chooses to use an “or equal” product, product data sheets must be submitted a minimum of 2 weeks prior to start of work period for review and approval.
Kawishiwi Fleet Garage Roof
Shingles - Manufacturer: GAF, or approved equal.
Line: GAF Timberline UHDZ, Color: Weathered Wood
Ridge Shingles – Timbertex Weathered Wood to cover ridge cap and ridge vent. Ridge shingles shall be the same color and manufacturer as the roof shingles.
Ridge Vent – Manufacturer: GAF Cobra Snow Country or Air Vent Inc. ShingleVent II or approved equal. Ensure existing roof is cut ~ 2” on either side of ridge line and install ridge vent.
Ice and Water Shield – Minimum 55-mil thick. Manufacturer: GAF Weatherwatch Leak Barrier or CertainTeed WinterGuard or approved equal.
Drip Edge - Style 2-5/8” x 1-11/16”, 24 gauge galvanized steel, Style-D, Color: Almond
Underlayment – Synthetic underlayment or 30# felt.
Roof Decking – 5/8” plywood, APA rated roof sheathing: Exterior exposure class, Structural 1, Span rating: 32/16.
Photo Kawishiwi Fleet Garage
KAWISHIWI GARAGE ROOF
ESTIMATED QUANTITIES
STRIP EXISTING ROOFING MATERIALS AND DISPOSAL 1 LS
SHINGLES 113 Square RIDGE CAP SHINGLES 160 Lin. Ft.
RIDGE VENT 156 Lin. Ft.
ICE & WATER SHIELD 20 Square ROOF DECK PROTECTION/UNDERLAYMENT 93 Square DRIP EDGE (2-5/8” x 1-11/16”, Almond) 460 Lin. Ft ROOF DECKING 96 Square Ft
DISPOSAL 1 LS
Photo Kawishiwi Fleet Garage
NOTE:
These ESTIMATED quantities were compiled to give the Contractor an idea of the scope of the work requested. The Contractor shall be responsible for the generation of their own quantities upon which to base their bid to provide a completed roofing system.
Payment:
The quantities shall be paid for as lump sum quantities or by other methods of measure as listed in the SCHEDULE OF ITEMS. Such payment shall be considered full compensation for constructing the complete project in accordance with the plans and specifications. Invoices must be inputted into the IPP System.
Additional Documents required to be prior to final invoice processing are:
Certified Payroll
Contract Release Form
Copy of landfill receipt
Final payment will not be processed until all 3 documents have been received by the
CO.
Site Visit:
A site visit is highly recommended and can be arranged by contacting:
James Anderson 1393 Highway 169 Ely, MN 55731 218-365-2044 James.b.anderson@usda.gov mailto:James.b.anderson@usda.gov
File details come from the government source that posted it. Updated .