This document is a Statement of Work (SOW) for the reconstruction of the Bog Dam 4 Road Bridge superstructure in the White Mountain National Forest, Coos County, New Hampshire.

The SOW outlines the government's requirements for the contractor to demolish the existing 41-foot multi-beam steel stringer bridge and construct a new 41-foot superstructure using steel stringers, a timber deck, and a wearing surface. Additional work includes armoring the shore with riprap, installing guardrail, and approach surface treatment. The contractor must obtain all necessary permits, coordinate with utilities, establish erosion control measures, and comply with environmental regulations. The government has already obtained an Army Corps permit, but the contractor is responsible for any additional permits required.

The period of performance is May 30, 2024 to June 28, 2025. Key submittals required include the contractor's safety plan, traffic control plan, spill prevention plan, construction schedule, and material certifications. The project will be awarded under Solicitation Number 12445524R0008 by the U.S. Department of Agriculture Forest Service.

View the file

Other files for this federal contract opportunity

Other files attached to Bog Dam 4 Bridge replacement, newest first.
File Type Posted
Sol_12445524R0008.pdf PDF
Att 01_Schedule of Items (240614).docx DOCX document
Att 05_Project Location Map (240326).docx DOCX document
Att 08_Brass Girder (230428).pdf PDF
Att 04_Plans (240417).pdf PDF
Att 03_FSSS (240603).pdf PDF
Att 06_Load Rating (230603).pdf PDF
Att 07_Design Analysis (230602).pdf PDF
Att 09_Wage Rates (240105).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents

Project3
General Information3
1.0 Scope of Work3
2.0 Background3
Contractor Requirements3
3.0 Technical Requirements / Tasks3
4.0 Government Furnished5
5.0 Drawings5
6.0 Deliverables / Schedule6
7.0 Specifications7
Attachment7

Project White Mountain National Forest, Bog Dam 4 Road Bridge Replacement, FR 15, MP. 7.9

General Information

1.0 Scope of Work

The Forest Service (FS) is soliciting bids for reconstruction of Bog Dam 4 Road Bridge superstructure, Coos County, New Hampshire, within the White Mountain National Forest, Andro District.

The contractor shall provide all expertise, labor, supervision, services, equipment, tools, supplies, permits (as applicable), coordination with utilities, transportation, and incidentals necessary to complete the work described. The desired outcome is completed installation per the standards attached to this solicitation, and adherence to the contract awarded. The awarded contract shall constitute the entire agreement including all terms and conditions applicable to the contract. Work shall be completed as shown in the drawings, maps, specifications, and exhibits as referenced or included in this contract, and in accordance with applicable federal, state, and local regulations.

Work will include demolition of existing 41’ bridge superstructure and dispose of all materials off FS lands without damaging the existing abutments. Construction of the new 41’ superstructure. Bridge plans provided show that is structure will use; steel stringers, a timber deck and wearing surface. Additional work includes but not limited to armoring shore with riprap, guardrail, and approach surface treatment. All construction will be following the attached plan set.

2.0 Background

The existing structure is 41’ multi-beam steel stringers with reinforced concrete cast in place deck and abutments. The bridge spans Upper Ammonoosuc River.

Contractor Requirements

3.0 Technical Requirements / Tasks

Permits- the Government has acquired an Amy Corp permit. The contractor shall obtain additional permits, or amendments to Government obtained permits, as necessary for their operations as required by local, state, and federal regulations.

Trees shall be cut between November 15th and March 31st.

Staging Area- The Contractor shall coordinate with the CO on a staging area location(s). The Contractor shall operate all equipment and store, transport, and handle material in a manner that will not damage existing roads, parking lots and landscaping.

Landscaping Preservation- The Contractor shall confine operation to within the clearing limits designated, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside these limits.

Equipment shall be clean and properly maintained. Leaking or faulty equipment shall be repaired or removed. Refueling, greasing, or servicing of equipment shall be in controlled areas away from surface waters.

If, prior to or during excavation work, items of archaeological, paleontological, or historic value are reported or discovered, or an unknown deposit of such items is disturbed, the Contractor shall immediately cease excavation in the area so affected. Contractor will then notify the Forest Service and will not resume excavation until written approval is given by the authorized officer.

Erosion Control- The Contractor is responsible for implementing temporary erosion control. Establish erosion protection and dewatering methods prior to conducting excavations. Maintain erosion control measures, and improve and replace immediately any non-functioning measures, throughout the course of the project and until site stabilization has been established.

Schedule and conduct operations to minimize erosion of soils and to prevent silting or muddying of stream, rivers, irrigations systems, or impoundments.

Dewatering – The Contractor is responsible for all dewatering activities. Conduct dewatering suitable to protect the landscape from the activities, and as needed to isolate the work from streams and protect the work from damage.

Spill Prevention- The Contractor shall prepare for approval, and adhere to, a Spill Prevention, Control, and Countermeasures Plan suitable to protect environment from the Contractor’s operations.

Pollutant such as fuels, lubricants, bitumens, sewage, hazardous, or otherwise harmful shall be controlled at the site and prevented from release to the environment. All contaminated soil, vegetation or debris resulting from Contractor’s operation shall be immediately contained and within 24 hours shall be removed from site and legally disposed.

Control the discharge of non-hazardous wash water through sufficient siltation treatments, such as filters, barriers, or settlements. Dispose of and materials containing hazardous-substances legally off national forest system lands.

Electrical- There is no electrical service on this project.

Services – Potable Water and Toilet Facilities are not available in this location. The Contractor is responsible for providing temporary sanitation facilities as necessary.

Existing Utilities – The Contractor shall ensure locations of any utilities prior to excavation, trenching, or other ground disturbing activity. The Contractor shall be responsible for materials that are stored on site. Secure completed work as required to prevent loss.

Maintenance of Traffic- The Contractor shall have all temporary construction signs and traffic control measures in place prior to beginning work. Plans contain a proposed plan. Traffic Control plans to be approved by White Mountain Forest Service. The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to limitations and authorizations shown on the Plans or specified under this contract, when such use will not damage the roads or National Forest resources, and when traffic can be accommodated safely.

Security and Protection – Security is the Contractor’s responsibility. Limit access to the construction area to persons involved in the work. Provide secure storage for materials that are stored on site. Secure completed work as required to prevent loss.

Barricades, warning signs, and lights shall comply with standards and code requirements for erection of structurally adequate barricades. All road warning signs, barricades, and traffic control devices shall conform to MUTCD. Where appropriate and needed, provide lighting, including flashing red or amber warning lights.

The Contractor shall barricade and block all access to holes with orange plastic fence, flashing amber lights, or warning signs. Holes or trenches shall not be left open more than 24 hours unless approved by the CO.

Protection of Improvements- The Contractor shall complete sequences of construction activity in order to prevent damage to equipment, material, and articles incorporated into the work covered by this contract. Contractor shall replace, or repair, as approved by the CO any improvements, covered under this contract or already existing, damaged by contractor’s operations.

Before shutting down operations, take all necessary precautions to prevent damage to the project, such as temporary detours, approaches, crossings, or intersections; and provide for protection of surface drainage and minimization of erosion and prevention of spills.

Site Cleanup- The Contractor shall be responsible of solid waste disposal and personnel sanitation. The Contractor shall always keep the area in a clean, neat, and orderly condition. Construction related debris including, but not limited; to used motor oil, oil cans, grease cartridges and refuse shall be removed promptly from the site and disposed of in a lawful manner off National Forest System lands. Fees for the use of landfills or transfer stations shall be paid for by the Contractor if there is a change.

Other Operations- The Contractor shall avoid interference with the operations of other contractors or projects in the area.

4.0 Government Furnished

None

5.0 Drawings

Drawings The following drawings are applicable to this project and included as attached,

SHEET NO.
TITLE

Replacement – Bog Dam 4 15-7.9 0922

1-16
General Layouts, Work Descriptions, and Details
1 of 16
Title Sheet -- USFS
2 of 16
Design Data & General Notes
3 of 16
Quantities & Miscellaneous Details
4 of 16
Temporary Traffic Control
5 of 16
Typical Sections
6 of 16
Plan of Site
7 of 16
Profile of Site
8 of 16
Plan of Structure
9-10 of 16
Structure Details
11 of 16
Soil Borings
12-13 of 16
Cross Sections
14-16 of 16
Guardrail Details

Prosecution of Work The Contractor shall conduct work within the work periods shown below, and in accordance with applicable permits or regulations. Activities not otherwise restricted may be scheduled at contractor’s preference, when consistent with material limitations, manufacturer’s instructions, and in accordance with approved work schedule and suitable advance notification as required. Work shall be conducted safely, performed diligently, in a workmanlike manner adhering to Plans and Specifications and instructions, and be completed promptly. Contractor shall not suspend work area prior to implementing appropriate stabilization and site protection measures, and without approval of COR.

6.0 Deliverables / Schedule

Pre-bid Tour No pre-bit tour is scheduled at this time.

Prospective bidders wishing to visit the site on their own may obtain directional information by contacting Bryanne Thompson at the Forest Supervisor’s office, White Mountain National Forest, Campton, Start Work It is estimated that work will begin around May 30th, 2024, or as allowed by contracting. Site disturbing activities shall be performed consistent with the periods of restrictions noted in the Plans, Permits, or other instructions.

Period of Performance Work shall be completed by June 28th, 2025. The period of performance includes pre-construction and construction activities such as: obtaining permits approvals, submittal of fabrication and manufacturing proposals, ordering and delivery of materials; and performance of the work.

Submittal and Notifications In addition to submittal of permits, bonds, and other forms required under the contract provisions; below is summary of key submittals and timeline, contractor shall refer to and adhere to applicable submittals and certifications noted in the Plans and Specifications for complete requirements.

Submittal Schedule:

ITEM
TIMELINE
Contractor’s Safety Plan and Traffic Control Plan
Upon Issuance of Notice to Proceed
Contractor’s Spill Prevention, Control, and Countermeasures Plan
Upon Issuance of Notice to Proceed
List of Subcontractors and Suppliers*
Upon Issuance of Notice to Proceed
Contractor’s Quality-Control Plan
Upon Issuance of Notice to Proceed
New Hampshire DOT Bond if Applicable
Upon Issuance of Notice to Proceed
List of Emergency contact names, numbers and title of personnel.
2 weeks before mobilization
Manufacturer’s Fabrication Drawings and Design Calculations
21 days prior to production
Proposed Source of Aggregate and Stone
21 days prior to use
Construction Schedule
2 weeks before mobilization
Designation of Contractor’s on-site superintendent
2 weeks before mobilization
Aggregate and stone screen reports
Prior to hauling and placement
Delivery load slips; such as aggregate, borrow, concrete, and asphalt
Upon Delivery

Manufacturing test results and Material Production certifications As required

Quality control in-place test results
As required
Manufacturer’s instructions, Warranty Information, and Supplemental Data
Upon Delivery
As-built Drawings
Upon Completion
Proper Invoices
As required
Progress certifications and quantity measurements
With Invoices
Certificates of Payment
With Invoices
Certified Payroll Reports
Weekly

* "List of Subs & Suppliers" assumes that an Item which meets Specifications as written is supplied. Evaluation of product substitution requires review and approval by the CO/COR and may require longer schedule.

Notification Schedule:

The following events require an advance written notification to the COR. Notifications may be faxed, mailed, emailed, or hand delivered.

EVENT
PRIOR NOTICE REQUIRED
Change in Schedule
As soon as identified
Change in Subcontractors or Suppliers
As soon as identified
Intent to close site or alter public traffic
21 days
Intent to mobilize or to suspend
14 days
Intent to dewater or impact streams
14 days
Intent to start excavation
48 hours
Intent to deliver structural components
14 days
Intent to place structure or backfill against structure
48 hours
Intent to install incidental or ancillary items
As progressing

7.0 Specifications

This project uses the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14), U.S. Customary Units; available by reference and download from https://hlh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf

Please note the attached FS supplemental Specs.

Attachment Plans, location map and FS supplemental Specs.