This statement of work outlines the requirements for moving historic and non-historic cannon barrels at Fort Point National Historic Site in San Francisco, California. The contractor will be responsible for lifting and placing five cannon barrels and one artillery shell onto new or existing mounts between November 14, 2023 and December 31, 2023. This includes moving one 10-inch Rodman gun weighing 15,100 pounds, one San Martin cannon weighing approximately 5,500 pounds, two 10-inch Columbiad cannons each weighing around 10,000 pounds, and one 16-inch artillery shell weighing 1,900 pounds. The contractor must have the necessary rigging and hoisting equipment, and provide protective planking or sheeting. The work will take place on Tuesdays or Wednesdays to minimize impacts to visitors, and the contractor must maintain public safety and access. The National Park Service will provide temporary wooden blocking for storage and remove a window for the interior cannon move.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

FORT POINT NATIONAL HISTORIC SITE

Move Historic and Non-Historic Cannon Barrels

09/08/2023

PART 1: GENERAL

1.01 DESCRIPTION

Project Identification: The project is located at Fort Point National Historic Site within the Golden Gate National Recreation Area, San Francisco, CA. The street address for Fort Point NHS is Long Avenue & Marine Drive, 201 Marine Drive, San Francisco CA 94129. The mailing address for any correspondence is GGNRA, Building 201 Fort Mason, San Francisco CA 94123.

The work specified herein includes the lifting and moving of a practice 16” gun artillery shell, 2 non-historic 10” Columbiad cannons, a historic 10” Rodman gun barrel, and the historic San Martin cannon.

Performance Period: The work of this contract shall be provided November 14, 2023 through December 31,2023.

All work occurs on the ground floor of Fort Point NHS in Powder Magazine 1, the Casemates, and on the Parade Ground (see photos attached).

1.02 BACKGROUND

Fort Point stands at the south side of the Golden Gate Strait, forming a substantial landmark at the entrance to San Francisco Bay. Built at the site of an old Spanish gun battery, Fort Point was one of the first major U.S. Army installations in the Bay Area. It guarded the San Francisco Bay and Harbor from the Gold Rush-era in the 1850s until World War II. Although no shots were ever fired in anger from Fort Point, it is the most tangible legacy of the Civil War in California, and represents California’s little known, yet significant, political and social involvement in the Civil War. Built to hold four tiers of cannons, the fort is also an outstanding example of masonry fort construction and is the only fort of its style on the West Coast of the United States. As a testimonial to the fort’s historic significance, the southern anchorage of the Golden Gate Bridge was designed to gracefully arch over it.

Fort Point became a National Historic Site in 1970 and is today managed as a district park unit within the larger Golden Gate National Recreation Area. The fort’s scenic location under the south end of the Golden Gate Bridge attracts visitors throughout the year, many of whom accidentally happen on the fort and have no idea of its significance. Over 300,000 people visited Fort Point in 2017, with a significant number of those being international and national vacationers, particularly during the summer months.

The Fort Point National Historic Site is listed in National Historic Register and owned by the Department of Interior, National Park Service, herein after called NPS, and is maintained by the Golden Gate National Recreation Area (GOGA).

1.03 GENERAL CONDITIONS AND INFORMATION

A. The quality of workmanship, quality and the type of materials, and the details of the project shall conform to all applicable portions of the highest standards except where requirements of the drawings and specifications are in excess thereto, in which case the drawings and specifications shall take precedence.

B. Any particulars described for the work involved is given for guidance to the Contractor, however, the Contractor is to take his own measurements, dimensions and counts, and is responsible for the same. Field verify all new and existing dimensions affecting the work of this contract before ordering materials.

C. All work described in this specification is for moving cannon barrels from temporary blocking in the casemates and onto permanent stands at various locations in the new exhibits (drawings attached). 3 cannons are to be moved onto new exhibit stands (provided by Others), timing to be arranged to coincide with exhibit installation, while the 4th will be placed on display on wooden blocking in Casemate #19. The 16” artillery shell is in Powder Magazine 1 (next to the new location of the San Martin cannon) and will move to a stand (by Others) in Casemate 3, next to the Rodman cannon.

D. The Contractor shall provide all supervision, labor, tools, parts, material, equipment and transportation to complete the following project work items. The Contractor shall take into account the site conditions in project planning and submittal of the proposal.

E. The Contractor shall provide all rigging and hoisting hardware appropriate to the size and weight of the cannons to be moved.

F. The Contractor shall provide planking or plywood as needed to protect the historic floors of the Casemate area (granite) and the Parade Grounds (concrete). Additional plywood or metal plates will also be needed to reinforce the non-historic wood floor in Powder Magazine 1.

G. New cannon and 16" artillery shell mounts are being supplied and installed under a separate contract. Awardee will be working alongside this contract holder under the direct supervision of the COR.

1.04 SPECIAL REQUIREMENTS

A. Accident Prevention and Safety Plan

Before on-site work begins, the Contractor shall submit for approval an accident prevention and safety plan. The Contracting Officer will review both plans for compliance with OSHA and project requirements. If the plans require any revisions, the Contractor shall resubmit the plans within 10 working days. The plans shall include the following:

1. • Name of responsible on-site supervisor.

2. • First-aid procedures.

3. • OSHA and other required postings regarding safety at the site.

4. • Outline of each phase of the work, and the hazards associated with each major phase.

5. • Methods proposed to ensure property protection and safety of the public, Park Visitors, National Park Service personnel, and the Contractor’s employees.

B. Site Use Conditions

Due to the work being conducted within a National Park, which will be open to the public Thursday, Friday, Saturday, Sunday, and Monday weekly, on-site activities shall be carefully coordinated with the Contracting Officer as follows:

• Contractor shall conduct his operations on Tuesdays or Wednesdays.

• Stop Work Orders. GGNRA reserves the right to stop work at any time for emergencies/safety violations, and NEPA and NHPA violations. Emergency and safety stop work orders may be issued directly by GGNRA Safety Officer and/or GGNRA Public Safety personnel (law enforcement/fire). All other stop work orders will be issued through the project POCs (GGNRA).

C. Site Use Conditions

Due to the work being conducted within a National Park, which will be open to the public Thursday, Friday, Saturday, Sunday, and Monday weekly, on-site activities shall be carefully coordinated with the Contracting Officer as follows:

• Contractor shall conduct his operations on Tuesdays or Wednesdays.

• Stop Work Orders. GGNRA reserves the right to stop work at any time for emergencies/safety violations, and NEPA and NHPA violations. Emergency and safety stop work orders may be issued directly by GGNRA Safety Officer and/or GGNRA Public Safety personnel (law enforcement/fire). All other stop work orders will be issued through the project POCs (GGNRA).

1.05 SCOPE OF WORK

1. Scheduled in conjunction with the exhibit installation process:

Place 1 of the Columbiad cannon barrels onto new custom-made steel mount (mount by Others) in Casemate 1. This cannon is in the 10,000 lbs. weight range, measures 37” side to side (to the outside of the pivot trunnions) and is app. 130” long.

2. Place the Rodman gun onto new custom-made steel mount (mount by Others) in Casemate 3.

The Rodman gun barrel weighs 15,100 lbs., measures 38” in width (to the outside of the pivot trunnions) and is 138” long.

3. Place the San Martin cannon inside Powder Magazine 1 onto its refurbished wood carriage (refurbishment by Others). The San Martin is smaller and lighter at app. 5,500 lbs., 22” wide (to the outside of the pivot trunnions) and 110” long. Access to Powder Magazine 1 is restrictive- the hallway entrance is too narrow and the corners too tight for the San Martin to pass through unless the barrel were to travel tipped up on end. It is projected that it would be easier to hoist the cannon through an existing window from the Parade Ground. The wood planked floor has already been reinforced at the interior location where the cannon is to be placed (reinforcing by Others) but will require additional temporary planking, plywood, or plating to spread the weight load of the cannon while moving from the interior of the window over and on to the permanent gun carriage.

4. Place the 2nd Columbiad onto existing wooden blocking on display in the location in Casemate #19. This cannon is in the 10,000 lbs. weight range, measures 37” side to side (to the outside of the pivot trunnions) and is app. 130” long.

5. Place the 16” gun artillery shell on its new mount (by Others) between Casemates 2 and 3. The shell is currently stored in Powder Magazine 1 next to the new location for the San Martin cannon. The shell is estimated to weigh 1900 lbs.

1.06 GOVERNMENT SUPPLIED MATERIALS

The Government will provide wooden blocking for the temporary storage of the cannons on the Parade Ground.

Due to the length of the cannon in Powder Magazine 1, it cannot be moved through the hallways, and it will need to be moved through a window that Government staff will remove and replace in order for this work to be completed by the awardee.

PART 2: PUBLIC ACCESS AND SAFETY

1. Conduct operations to ensure public safety and ensure the least amount of inconvenience to the public.

2. Maintain access for National Park Service administrative and other official business throughout the work.

3. Leave work area in a condition that is safe for visitors on weekends, holidays, and other times when work is not in progress

1.03 GENERAL CONDITIONS AND INFORMATION
1.05 SCOPE OF WORK
1.06 GOVERNMENT SUPPLIED MATERIALS
PART 2: PUBLIC ACCESS AND SAFETY