This file is a Questions and Answers document for a federal contract opportunity involving furniture and electronic appliances installation at Bunch Hall Dorm B221.
The project encompasses furnishing 68 identical rooms across a three-story building with no elevators. The building will remain unoccupied during installation, and no existing items require disassembly. Installation must occur Monday through Friday between 0730 and 1700 CST, with a 10 duty day completion deadline. Extensions require approval from the MHO Point of Contact. The building is currently under active construction, and the awardee must coordinate with the requiring activity after award notification to determine the project start date. Products will include wall-mounted items into sheet rock walls. A 53-foot trailer has unencumbered access for delivery, and on-site storage is available approximately three-quarters of a mile from the building. If trash disposal is necessary during installation, a dumpster may be placed reasonably close to Building 221. Installers will access the building via stairs only, as elevators are not available. This RFQ is an all-or-none requirement, meaning offerors must quote on all CLINs and all items with no partial bidding allowed. Open-market bidding is permitted for the items required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Atch4 Quote Schedule-Frntrs 15Sep26.xlsx | XLSX spreadsheet | |
| Atch4 Quote Schedule-Frntrs 10Sep26.xlsx | XLSX spreadsheet | |
| Atch4 Quote Schedule-Frntrs 8Sep26.xlsx | XLSX spreadsheet | |
| Atch8 Floor Plans All 3-Frntrs.pdf | ||
| Atch2 Salient Characteristics-Frntrs.pdf | ||
| Combo RFQ FA465926QZ016 - Bunch Hall Dorm B221 Furniture.pdf | ||
| Atch6 Past Performance List of References-Frntrs.pdf | ||
| Atch3 Photo Examples-Frntrs.pdf | ||
| Atch1 Statement of Work-Frntrs.pdf | ||
| Atch5 Provisions and Clauses-Frntrs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&As: Bunch Hall Dorm B221 Furniture & Electronic Appliances
1. How many total rooms and room types? 68 rooms, one room type.
2. How many stories? Three, no elevators.
3. Will the buildings be occupied? No.
a. If they are occupied, is there any way to temporarily place guests in another building on base? N/A.
b. What is the estimated occupancy rate during the requested time of install? Zero.
4. Will there be Removal & Disposal of furniture, can you provide a location within proximity of the base that can be used for disposal? No.
5. If a dumpster is required to be included in our installation services, can I get a clear understanding of placement, to the closest proximity to building(s). If required to get rid of trash and debris during installation, reasonably close to building 221.
6. Does the base have storage on site for installer use? Yes.
a. If so, can I get a clear understanding of proximity to building requiring installation. Approximately ¾ of a mile.
b. If not, can I get a clear understanding of placement, closest to the proximity to building(s). N/A
7. What are the delivery hours? Monday – Friday, 0730 – 1700 CST, excluding Federal holidays.
8. Is there unencumbered access for a 53’ trailer to deliver product? Yes.
a. If not, provide a location where the delivery truck can park during unloaded, at a location closest to building. N/A.
9. What are the allowable hours of installation (example 7AM – 8PM)? Monday – Friday, 0730 – 1700 CST.
10. Are the installers able to have full access to elevators or to stairs only? Stairs only.
11. Are Installers required to disassemble existing items? N/A, No existing items.
12. Is there a required time to start this project? The building is under active construction, and the project will start upon completion or at partial completion. Awardee shall coordinate with the requiring activity after the notification of award.
13. Is there a required time frame to have work completed within? 10 duty days to complete.
Extensions must be approved by MHO POC.
14. Will any product be mounted into the wall? Yes.
a. If so, what material are the walls made of? Sheet rock.
15. Is there anything else we should know about this project that would be helpful? Not at this time.
a. Maybe a challenge to be aware of or something that went wrong in the past that would be wise to discuss? N/A.
16. Can the items be open-market bid? Yes.
17. Is this an all or none RFQ, or can a company partial bid? All, the offerors must quote on all CLINs including all items.