Atch1_SOW_EOC Upgrade.pdf
PDF 97 KB Posted
- Attached to
- EOC Upgrade
- Solicitation number
- FA4626-20-Q-0078
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Atch1_SOW_EOC Upgrade.pdf | ||
| Questions and Answers.pdf | ||
| Atch1_SOW_EOC Upgrade.pdf | ||
| COMBO.pdf | ||
| Atch3_Memorandum for 341st MW Contractors.pdf | ||
| Atch2_Installation Perimeter Access Control.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
24 August 2020 EOC Upgrade
Monitor 3: From GIS computer 25ft. Cable is run along the floor to the TV monitor wall, up the wall, and directly back out along the wall allowing the monitor to utilize the current outlet that the existing projector is plugged into.
Monitor 4: From EOC manager computer 76ft. Follows the same path as monitor 2 except the cable continues to follow the ceiling all the way back to the back wall where it then goes down roughly 4 feet to where the TV is mounted on the wall.
Monitor 5. From EOC Admin computer 72ft. Follows the same path as monitor 1 except that it continues to run along the wall past monitor 1 to the South wall where it then runs back along the wall and down to where the monitor is mounted on the wall.
Monitor 6. From GIS computer 56 ft. Follows the same path as monitor 3 except that it runs all the ceiling to the north wall and back towards the east wall then down to where the monitor is mounted on the wall.
Diagram 1.2
STATEMENT OF WORK
24 August 2020 EOC Upgrade
Diagram 1.3
General Information:
The Government will install all electrical wiring conduit for placement of monitors. Any electrical work will be performed by Malmstrom AFB.
The ceiling in the EOC is an open ceiling see attached photos of EOC ceiling and locations to mount monitors.
System needs to have a minimum of a 2 year warranty included in the quote and must also provide an option quote for an extended service contract to cover items like adjustments.
Include all owner’s manuals/specifications/warranty documents.
Schedule:
Contractor shall provide a detailed schedule showing the timeframe from award to installation of fully operational system. This includes an estimation of delivery and installation time following award of the contract.