This document is the pre-proposal conference minutes and record of a site visit for a federal contract opportunity to repair 29 military family housing (MFH) units at Misawa Air Base, Japan.
The project, with a contract number of QKKA204002, requires the contractor to provide all supervision, management, quality control, labor, tools, equipment, materials, and performance of all work necessary to construct improvements for the renovation of the 29 MFH buildings. The contract type is firm-fixed-price with a performance period of 634 calendar days including 30 days for mobilization. Key solicitation details include requirements for antiterrorism awareness training, liquidated damages, hazardous material handling, and past performance information. Offerors must be registered in the System for Award Management. The award will be made using a subjective tradeoff process where past performance is approximately equal to price in importance. The solicitation closing date is February 26, 2024 at 2:00 PM Japan Standard Time, with questions due no later than February 16, 2024.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mission – Family – Warrior
35th Fighter Wing
Pre-proposal Conference / Site Visit RFP No. FA520524R0001 Project No. QKKA204002, Repair JNCO Homes, MFH 29 units (221, 712, 716, 718, 723, 812, 817, 818), Misawa Air Base, Japan
35 CONS/PKP
35 CES/CENM
9 Feb 24, 0900 hours
Mission – Family – Warrior
Summary
Introduction
Scope & Requirements General Requirement
Solicitation CONS remarks for solicitation / filling instructions
CES Technical Briefing
Site Visit to Bldgs 712, 716, 718, 723, 812, 817, and 818 (Site visit for Bldg. 221 was conducted on 30 Jan 24)
Introduction
35 CONS
MSgt Derek Crader, Contracting Officer
Ms. Miyako Fujimoto, Contracting Officer
Mr. Kazuo Miura, Contract Administrator
Mr. Takafumi Nosaki, Contract Administrator
Mr. Akito Miura, Contract Administrator
35 CES
Introduced by CES Technical Briefing later
Mission – Family – Warrior
Scope & Requirements
Scope & Requirements (cont’d)
Project Description (Sec. B):
The contractor shall provide all supervision, management, quality control, labor, tools, equipment, materials, and performance of all work necessary to construct improvements for the renovation of the housing buildings.
Place: MFH 221, 712, 716, 718, 723, 812, 817, and 818
Contract Type: Firm-Fixed-Price (FFP)
Performance Period: 634 calendar days (incl. 30 CDs mobilization)
Mission – Family – Warrior
Solicitation
Fill-in
Complete block 14 through 20
RFP – Page 2
Solicitation (Cont’d)
Fill-in
RFP – Page 4
Mission – Family – Warrior
Solicitation (Cont’d)
Section I
DFARS 252.204-7004 Antiterrorism Awareness Training for Contractors
Contractor personnel who require routine physical access to military installation shall complete Level 1 antiterrorism awareness training within 30 days of requiring access and annually thereafter
FAR 52.211-12 Liquidated Damages
@¥113,027 (1st day) & @¥69,779 (2nd day ~)
FAR 52.223-3 Hazardous Material
RFP – Page 12
RFP – Page 13
Fill-in
RFP – Page 13
Solicitation (Cont’d)
Section J RFP – Page 33
DatePageDescriptionDocument Type
8 Dec 231,148SpecificationsAttachment 1
8 Dec 23319DrawingsAttachment 2
14 Dec 236Other Contract RequirementsAttachment 3
6 Sep 2347Schedule of Material SubmittalsAttachment 4
26 Oct 233List of Contractor Furnished U.S. MaterialAttachment 5
26 Oct 231List of Gov’t Furnished Contractor Installed ItemsAttachment 6
15 Jun 23431Hazardous Materials Inspection ReportAttachment 7
14 Dec 231Past Performance Questionnaire (PPQ) Cover LetterAttachment 8
14 Dec 235Past/Present Performance QuestionnaireAttachment 9
Mission – Family – Warrior
Solicitation (Cont’d)
Section K
FAR 52.204-8 Annual Reps & Certs
FAR 52.204-24 Reps Certain Telecom & Video Surveillance Svc or Equipment
FAR 52.209-7 Responsibility Matters
DFARS 252.204-7007 Alt. A, Annual Reps & Certs
Fill-in
RFP – Page 34 ~
RFP – Page 37 ~
RFP – Page 38 ~
RFP – Page 39 ~
Other Contract Requirements
Para. 6, Special Contract Requirements:
H002 Required Insurance
Property Damage - ¥2,000,000
H003 Performance Bond
Submit within 30 CD after the award date of contract or prior to issuance of the Notice to Proceed whichever comes first.
Require additional if Mod > $10,000
Atch 3 – Page 3
Mission – Family – Warrior
Other Contract Requirements (Cont’d)
Para. 8, Reps, Certs & Other Statements of Offerors
K001 Tax Exemption under SOFA
Total amount of consumption tax
¥53.80 x Est. Gas Quantity
¥32.10 x Est. Diesel Quantity
Fill-in
Atch 3 – Page 4
Other Contract Requirements (Cont’d)
Para. 8, Reps, Certs & Other Statements of Offerors (cont’d)
K002 Contractor’s Cert
K003 Const. Contractor License
Offeror shall submit “special construction license” under applicable law together with offer, to demonstrate compliance with FAR 52.236-7, as modified, and DFARS 252.225-7042
Joint Venture or Partnership – the special construction license of each member of the JV or each partner of the partnership must be submitted together with the offer
Such offer that fails in representation of the above required license will not be considered for award
Fill-in
Atch 3 – Page 5
Submit
Mission – Family – Warrior
Solicitation (Cont’d)
Section L
L-100 Proposal Preparation Instructions
Offerors are required to meet all sol. requirements, terms & conditions, reps & certs, and tech. requirements
Prepare & Submit:
Part I – Summary and Misc. Data (Submit 1 Orig.+ E-copy)
Part II – Price Proposal (Submit 1 Orig.+ E-copy)
Part III – Past Performance Proposal (Submit 1 Orig. + E-copy)
Submit
RFP – Page 41
Solicitation (Cont’d)
Section L (cont’d)
Part I – Summary & Misc. Data (Submit 1 Orig.+ E-copy)
Concise summary & Master Table of Contents of the Entire Proposal
Signed SF 1442 (Page 1 & 2)
Acknowledgement of the all sol. amendments, if issued
Fill-ins/Cert in Section I thru K and Atch 3
Section I (pages require a fill-in)
Section K (its entirely)
Atch 3 para. 8 (pages require a fill-in)
Affirmation of no exceptions, deviations, or waivers, if none proposed
Submit
Mission – Family – Warrior
Solicitation (Cont’d)
Section L (cont’d)
Part II – Price Proposal (Submit 1 Orig.+ E-copy)
Completed Section B (Page 4)
Submit
Solicitation (Cont’d)
Section L (cont’d)
Part III – Past Performance Proposal (No more than 5 pages per contract / Submit 1 Orig.+ E-copy)
Past Performance Information (see next slide for detail) No more than 5 contracts within 5 years
Quality & Satisfaction Rating of Contracts Any info currently available (letters, metrics, customer surveys, independent surveys, etc.) that demonstrates customer satisfaction with overall job performance and/or quality of completed and/or ongoing contracts
Past/Present Performance Questionnaire (PPQ) Use Atch. 9 of RFP Customer/POC evaluator must directly send PPQ to the CO Do not include in proposal package
Submit
Mission – Family – Warrior
Solicitation (Cont’d)
Past Performance Information Company/Division Name1
Contract/Project Title2
Contracting Agency/Customer3
Contract Number4
Contract Dollar Value (use FY24 budget rate of ¥139.1635 if conversion is necessary)5
Period of Performance6
Verified, up-to-date name, mailing and e-mail addresses, and telephone number of the contracting officer (Point-of-Contact)
Comments regarding compliance with contract terms and conditions8
Comments regarding any known performance deemed unacceptable to the customer, or not in accordance with the contract terms and conditions
Include rationale supporting your assertion of relevance and identify aspects (scope, magnitude of effort, and complexity) of the contracts deemed relevant and how they relate to the proposed effort
Solicitation (Cont’d)
Section L (cont’d)
Past Performance Questionnaire (PPQ) Atch 9
Submit
Request for PPQ
Send a completed PPQ within 10 days after receipt of PPQ request
Offeror Customer/POC
Evaluator 35 CONS/PKP
E-mail:
miyako.fujimoto.jp@us.af.mil kazuo.miura.jp@us.af.mil
FAX: 0176-52-4793
Mail: 35th Contracting Squadron Attn: Mr. Kazuo Miura Bldg. 656, Misawa Air Base, Hirahata, Misawa-shi, Aomori-ken, Japan 033-0012
Mission – Family – Warrior
Solicitation (Cont’d)
Section L (cont’d)
FAR 52.204-7 System for Award Management
Offeror is required to be registered in SAM when submitting an offer
RFP – Page 44
Solicitation (Cont’d)
Section M
M-900 Basis for Contract Award
Subjective Tradeoff (STO) best value source selection
Weight of Importance: Past performance is approximately equal to price
Evaluation Process:
Price – Fairness and reasonableness of the price. The Gov’t reserves the right to perform price realism analysis
Past Performance – Recent and Relevant performance information
RFP – Page 49 ~
Mission – Family – Warrior
Solicitation (Cont’d)
Section M (cont’d)
Past Performance Factor
Recency: Work within the last 5 years prior to the issuance date of the solicitation
Relevancy: Performance effort involved similar scope, magnitude of effort, and complexities to that required by this solicitation
Integrated Assessment
The Gov’t reserves the right to award a contract to other than the lowest price offer
Best value award decision using the Price and the Past Performance Confidence Rating
CES Technical Briefing
CES Technical Briefing
Mission – Family – Warrior
Q&A
All questions asked must be formally submitted to 35 CONS in the form of questionnaire and/or request for clarification later.
Any technical questions deemed to be critical by the government engineers and the Contracting Officer must be submitted in writing to 35
CONS.
Example:
Information provided at this conference shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing (ref. Solicitation Attachment 3, “Other Contract Requirements”, para 9, L001(c))
Q&A / RFP Closing Date
RFP Closing Date / Time:
26 Feb 24 / 02:00 PM (JST)
Questions shall be submitted to 35 CONS/PKP miyako.fujimoto.jp@us.af.mil / kazuo.miura.jp@us.af.mil / takafumi.nosaki.jp@us.af.mil
NLT 16 Feb 24
Let’s move on to Site Visit
Mission – Family – Warrior
Site Visit
Bus transportation will be provided from the main entrance of Torii Bldg. 656