About this file

This is a blank Air Force Form 66 (AF Form 66) template used for tracking material submittals on federal construction projects. The form is organized as a spreadsheet with columns to track various types of submittals including certification of compliance, shop drawings, samples, color selections, manufacturer's recommendations and warranties, catalog data, and operating instructions. The template includes pre-populated line items for construction schedule (due within 1 week of Notice to Proceed), O&M Manuals, design drawings at 35%, 65%, and 95% completion stages, as-built drawings, and HMI Graphics. The form includes fields for tracking submission dates, review dates, approval status, and contractor notifications.

While this is just a blank template, it appears to be associated with a pre-solicitation for installing SCADA automation at Well 3 at Shaw AFB, which requires process equipment, controls systems integration, and remote SCADA access using Allen Bradley and Stratix switches. The work must comply with Shaw AFB Design and Construction Standards, ANSI, AWWA, NEC, and UPC requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Wells 3 SCADA Automation, newest first.
File Type Posted
Atch 3-HMI Screen Reference.pdf PDF
Atch 1-Statement of Work- VLSB 18-0010 Repair Well 3 with SCADA Upgrade.pdf PDF
Atch 4-Site Pictures CLIN 0001.pdf PDF
Atch 5-Pricing Sheet-Well Automation BLANK-NO FORMULA.xlsx XLSX spreadsheet
Atch 2-Shaw AFB Well Utility Controls Schematic.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NCOC-A

PROJECT NUMBER :PROJECT TITLE:SOLICITATION/CONTRACT NO.:
SCHEDULE OF MATERIAL SUBMITTALS
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONSMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSOTHERREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDIS- APPROVED
1Construction SchedulexWithin 1 week of NTP
2
3O&M Manualsx
435% Drawingsx
565% Drawingsx
695% Drawingsx
7As-Built Drawingsx
8HMI Graphicsxx
9
10
11
12
13
14
15
16
17
18
19

Solicitation No. F38604-99-1480 Attachment 6

AF FORM 66

(Computer Generated) PAGE &P of &N

File details come from the government source that posted it. Updated .