Atch 3 Drawing S-100 FINAL.pdf
PDF 4 MB Posted
- Attached to
- Y1DA--Project 596-20-105 - Improve Site Security, Sousley Campus Federal contract opportunity
- Solicitation number
- 36C24924R0009
About this file
This drawing package outlines site security improvements at the Sousley Campus for the Department of Veterans Affairs project number 596-20-105. It specifies the installation of bollards around perimeter fences, buildings, and electrical equipment to delineate secure areas and prevent vehicle access. Directional boring will install underground conduits for gate operator power feeds. The contractor must provide final layouts and hire a private utility locator prior to any digging. Disturbed landscaping must be re-established, and existing trees avoided during conduit routing. Bollards must be spaced no more than five feet apart and at least three and a half feet from protected assets. The solicitation number for this project is 36C24924R0009.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Atch 8 Existing Utilities Bldg 1 Exterior.pdf | ||
| Atch 9 Existing Utilities - Existing Grades.pdf | ||
| Atch 4 Drawing S-101 R1 FINAL.pdf | ||
| 36C24924R0009 0002.docx | DOCX document | |
| Atch 11 Existing Gate Submittal.pdf | ||
| Atch 10 Datasheet H5A Multisensor Camera.pdf | ||
| Atch 12 Pre-Bid Sign In Sheet.pdf | ||
| 36C24924R0009 0001.docx | DOCX document | |
| Atch 5 Project Specification 596-20-105.pdf | ||
| Atch 7 Construction Past Performance Questionnaire.docx | DOCX document | |
| Atch 2 Drawing Concrete Post Barricade.pdf | ||
| Atch 6 Construction Pricing Schedule.xlsx | XLSX spreadsheet | |
| Atch 4 Drawing S-101 FINAL.pdf | ||
| Atch 1 WD Fayette County Construction Building KY20230090 dated 09082023.pdf | ||
| 36C24924R0009_1.docx | DOCX document |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ENTRANCE 2 ENTRANCE 3
Approximate location of electrical feed from bldg 68 for entrance 3 gate operators. Directional bore all pavement crossings.
Contractor to provide final layout.
Approximate location of electrical feed from bldg 75 for entrance 2 gate operators. Directional bore all pavement crossings.
Contractor to provide final layout.
Police services office. 1st floor office location.
Install bollards on all four sides.
Install bollards on all four sides
Install bollards on all four sides
Install bollards on all four sides
GENERAL NOTES
1. Where possible, leave a minimum of 72 inches between bollards and buildings to allow mowers to pass. When a conflict exists, notify VA COR for direction.
2.Plans do not show existing trees. Contractor to verify existing conditions including existing trees and vegetation.
Electrical conduit should be routed around existing trees.
3. Bollards shall be evenly spaced at no more than 5 feet on center. Bollards shall be 3.5 feet minimum distance from transformers and switches they protect.
4. Contractor shall hire private utility locater to locate utilities prior to any digging or trenching.
5.Where grass is disturbed by any construction activity, it shall be re-established under this contract.
6. Areas identified as pavement on drawings are not limited to only the areas identified. The areas identified are believed to be pertinent to where directional boring will be needed.
Install bollards on all four sides.
Plan west side has 3 existing bollards spaced more than 5 feet apart. Add a bollard in between each existing bollard.
Install bollards on plan north, east, and south sides.
Pad mount transformer.
Install bollards on all four sides.
Install bollards on all four sides.
VA IT Closet for network (PACS & CCTV) tie in.
Room 31 on ground level and 147a on first floorPavement
Install bollards on 3 remaining (plan north, east, and south) sides of electrical equipment.
Existing bollards on plan west side to remain.
File details come from the government source that posted it. Updated .