This document is a Request for Qualifications (RFQ) for Architectural and Engineering (A&E) services to produce a Concept Design for repairing the HVAC system in Building 8500 at Vandenberg Space Force Base, California. The expected construction cost is between $1,000,000 and $5,000,000. The 30th Contracting Squadron intends to issue a Request for Proposal to one A&E firm, with the contract to be a negotiated, firm fixed-price contract. Interested A&E firms must submit an SF330, Architect-Engineer Qualifications, by April 29, 2024. Evaluation factors include professional qualifications, specialized experience, capacity to accomplish the work, past performance, and knowledge of the local area. The award will be made as a total small business set-aside. The contract price for the design shall not exceed 6% of the estimated construction cost.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 00 00
VANDEBERG SFB GENERAL REQUIREMENTS
PART 1 - GENERAL
NOTE: Whenever two specifications, or documents, are in disagreement it shall be assumed the more stringent shall apply unless indicated otherwise officially in writing by the Contracting Officer. Whenever a disagreement is located, the 30CES PM and Contracting Officer must be notified within 24 hours in writing for clarification.
1.01 PROJECT DESCRIPTION
1.01.1 The Architect-Engineer (A-E) shall investigate, research, and provide a complete and usable Concept Design (35% Design) with all relevant design contract documents to the Government for a Mass Notification System (MNS) at Air Education and Training Command (AETC) Campus Buildings 7425, 8173, 8175, 8195, 8250, 8290, 9190, 9192, 9334 and 9340 at Vandenberg Space Force Base, California.
1.01.2 The work is briefly described as follows, but is not the entire scope of the project:
The A-E shall produce and provide the Government with a Concept Design for a Mass Notification System (MNS) at Air Education and Training Command (AETC) Campus Buildings 7425, 8173, 8175, 8195, 8250, 8290, 9190, 9192, 9334 and 9340 at Vandenberg Space Force Base, California. The MNS shall connect Buildings 7425, 8173, 8175, 8195, 8250, 8290, 9190, 9192, 9334 and 9340, distributing messages, notifications, and instructions to personnel during emergency events.
1.02 OCCUPANCY:
1.02.1 The project site(s) will be occupied by base personnel during construction operations, unless indicated otherwise in the Statement of Work. The contractor must pre-coordinate all work and shall not disturb normal operations in any manner that is not coordinated clearly through the 30CES PM and the Contracting Officer.
1.03 WORK SCHEDULE
1.03.1 Working hours will normally be between the hours of 7:30 a.m. and 4:30 p.m., excluding Saturdays, Sundays, and federal holidays. If the Contractor desires to work during periods other than above, they shall make their request to the Contracting Officer 3 workdays in advance. If Government inspection forces are not required or such forces are reasonably available, the Contracting Officer may authorize the Contractor to perform work during periods other than normal duty hours/days; however, if Government inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of inspection at overtime rates will be charged to
XUMU 16-1092B
Attachment 3 the Contractor. These adjustments to the Contract price may be made periodically as directed by the Contracting Officer.
1.04 MANDATORY WORK STOPPAGES
1.04.1 A mandatory work stoppage occurs whenever the Contractor is restricted from working a full workday and is unable to reallocate work forces to other locations. All costs associated with five mandatory work stoppages must be included in the bid price. No additional compensation or extension to the Contract performance period will be given as a result of five (5) mandatory work stoppages.
1.04.2 The Contractor may be required to, without advance notice, move work to a different location. The Contractor shall be prepared to increase or decrease his work forces with appropriate trades to perform work in the relocated work areas at no additional cost to the Government.
1.04.3 The Contractor shall notify the Contracting Officer and 30CES Project Manager in writing, by the close of the next business day, when a mandatory work stoppage occurs for recording purposes; otherwise, the work stoppage will not be credited to the Contractor.
1.05 SECURITY
1.05.1 The Contractor shall obtain all passes, badges, decals, or other identification media required for security clearance to areas where work is performed. Obtain vehicle and individual identification media at the Pass and Registration Section, 30 SFS/S5SP, Building 11777, (805) 606-1853. Identification media shall be surrendered to the Pass and Registration Section upon termination of the Contract, or termination of an individual's employment with the Contractor. The Contractor must notify the Contracting Officer when all Identification Media is surrendered before final Payment will be issued.
1.05.2 The work to be performed is in a military restricted or controlled area. The Contractor must comply with the entry control policies for the area. The Contractor and its employees are required to have at least a National Agency Check. In the event the Contractor cannot provide personnel able to comply with entry requirements, they may be terminated in accordance with the terms and conditions of the contract.
It is also the Contractor's responsibility to coordinate with the appropriate security officials/area owner at each construction site at least 5 workdays prior to start of Contract performance. For information on security services, contact Personnel Security Section, SLD30/IP, (805) 605-0766.
1.06 UTILITIES
1.06.1 Utilities directly required to complete the Contract will be provided, if available, to the
Contractor without charge unless indicated otherwise. Any temporary connections or lines that are required shall be installed, maintained, and removed by the Contractor at his own expense and in a manner satisfactory to the 30CES PM and 30CES/CEO. Before any temporary connections are made, the contractor shall obtain approval from the Utility Shop (30CES/CEOIU, [805] 606-5885) for gas, water and sewer connections and Exterior Electric (30CES/CEOIE, [805] 606-2241) for electrical connections. Contractor shall remove temporary utilities before final acceptance.
1.06.2 Schedule all utility outages and secure approval of these outages from the Contracting
Officer at least 5 work days in advance of the outage.
1.06.3 Any project involving contact or connection with any water systems must contact both
American Water as well as 30CES/CEO to coordinate. American Water’s contact number is (805) 734-0043. 30CES/CEO may be reached at (805) 606-0739. All American Water requirements shall be met, and compliance documented through the 30 CES PM and the Contracting Officer.
1.06.4 Any excessive usage or abuse of base provided utilities may result in revocation of this privilege at the Contractor Officer or 30CES PM’s discretion and written notification.
Any further utility costs after the date of revocation will be solely the contractor’s responsibility to obtain and pay for.
1.07 SAFETY
1.07.1 Contractor shall observe all safety and fire regulations as presently enforced at
Vandenberg SFB. The construction shall be in accordance with the US Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, and Occupational Safety and Health Act (OSHA) Public
Law 91-596. Comply with OSHA and Air Force Occupational Safety and Health (AFOSH) safety standards.
1.07.2 All construction sites are subject to fire and safety inspections without notice. Any violation of fire and safety standards may result in a work stoppage at the expense of the Contractor.
1.07.3 Contractor shall hold a safety briefing for all subcontractors and craftsmen prior to construction or demolition. This briefing shall be for the specific purpose of making all personnel aware of asbestos and/or lead-based paint issues that may be encountered during demolition and/or renovation even though the project may not seemingly involve disturbance of those substances.
1.07.4 After award of Contract and prior to commencement of the work, the Contractor shall contact the SLD 30 Occupational Safety Office to schedule be briefed on the Safety Guide for Contractors for Vandenberg SFB to discuss the contractor responsibilities for compliance with Air Force and OSHA safety requirements.
1.08 COORDINATION FOR WORK CLEARANCE REQUEST (AF Form 103)
1.08.1 The Contractor shall obtain and process an AF Form 103, Coordination For Work
Clearance Request, for ALL WORK. The Contractor must bring the approved AF Form 332 to the 30th Civil Engineer Squadron Operations Flight Customer Service desk, 30 CES/CEOEC, Building 11439, (805) 606-0010/3152. The Contractor also must return the complete coordinated Form 103 to the customer service desk for final authorization before any work can begin. Note: Approval of the AF Form 103 can take up to several months when poor level of detail and/or insufficient documentation is provided for coordination.
1.08.2 Government agencies will annotate on the AF Form 103, any special instructions and/or compliance requirements prior to start of any work and/or while work is being accomplished. The Contractor shall implement all requirements indicated on the AF Form 103. The Contractor shall not begin work until the AF Form 103 is fully approved.
The Contractor shall keep a hard copy of the fully approved AF Form 103 with all comments and associated documents on site from the start of work until construction or project completion.
1.08.3 The Contractor shall coordinate any work/digging operations in the vicinity of utilities and communication cables with the 30th Civil Engineer Squadron Infrastructure Maintenance Engineering Utility Shop, 30 CES/CEOIU, and the 30th Space Communications Squadron, 30 SCS. No mechanical digging shall be performed within 4 feet of utilities or communication cables until they are physically exposed by hand digging. If a utility or communication cable is damaged, notify the Contracting Officer immediately. A minimum of a 72-hour advance notice for both 30 CES/CEOIU utility monitors, (805) 606-5885, and 30 CS communication monitors, (805) 606-7534, are required. Work shall not begin until the required 30 CES utility or 30 CS communication monitors are present. Additionally, during the 48-hour period prior to a launch operation, Contractors shall cease excavation work when they are within 15' of known communication lines as identified on the approved AF Form 103.
1.08.4 The Contractor shall coordinate all work with the 30th Civil Engineer Squadron's
Installation Management Flight (Environmental), 30 CES/CEI, Building 11146. The Contractor shall coordinate the AF Form 103 with the Installation Management Flight, a minimum of ten (10) workdays prior to any work/digging operations. Environmental monitors may be required from the 30th Civil Engineer Squadron's Installation Management Flight and a minimum of a 72-hours advance notice for environmental monitors is required. Work shall not begin until all required environmental monitors are present.
1.08.5 Work shall not begin until the 30CES PM and 30CONS CO have both received and accepted electronic copies of the fully coordinated and approved AF Form 103. All attachments and comments must be provided to the 30CES PM and 30CONS CO.
1.09 WELDING / HOT-WORK PERMIT: Any welding or torching on Vandenberg SFB requires a welding / hot-work permit. The Contractor shall obtain a welding permit from the Fire Protection Flight, 30 CES/CEF, Building 10660, (805) 606-4680. A permit will be issued within 2 workdays with instructions for welding fire prevention.
1.10 SUBMITTALS
1.10.1 After notification of Contract award and prior to purchasing any materials, submit to the
Contracting Officer for approval three copies of all items listed on AF Form 66, Schedule of Material Submittals (see Attachment 1), with one AF Form 3000, Material Approval Submittal, for each submittal. For the purpose of this statement, all entries included on a single AF Form 3000 are considered to be one submittal. Materials, shop drawings, manufacturer’s recommendations, etc., shall not be incorporated into the resultant Contract work until approved by the Contracting Officer or his Authorized Representative.
1.10.2 The following definitions set forth the minimum requirements for the type submittal listed on the AF Form 66 (Atch 1) and as further delineated under each section of the specifications:
1.10.2.1 CERTIFICATION OF COMPLIANCE:
1.10.2.1.1 Manufacturer’s Certification. Submit manufacturer’s certification that products meet or exceed specified requirements.
1.10.2.1.2 Testing Laboratory Services. Contract with an independent testing laboratory to perform inspections, tests, and other services, in accordance with specified standards.
Notify the Contracting Officer 24 hours prior to commencement of testing services.
1.10.2.1.3 Letter of Compliance. Submit letter stating that materials meet drawings and specifications. Include applicable referenced standards.
1.10.2.2 SHOP DRAWINGS. Submit both pdf electronic files and dwg electronic files via e-mail. If the files are too large for e-mail, ask the Project Manager to send a “Request a Drop-off” be sent through the safe.apps.mil site. Files must be smaller than 8 GB total.
Contractors shall follow up with Government representatives to ensure files were received. Contractors shall ask for written confirmation files were received and follow up with at least a monthly status check on any questions.
1.10.2.3 SAMPLES. Submit one set of the full range of manufacturer’s standard colors, textures, and patterns, unless otherwise indicated. Include the identification of each sample, giving full information. Samples may be retained until the completion of the Contract.
1.10.2.4 COLOR SELECTION. Provide field samples of finishes completed and finished.
Acceptable samples in-place may be retained in completed work.
1.10.2.5 MANUFACTURER’S RECOMMENDATIONS. Submit manufacturer’s printed instructions for delivery, storage, assembly, installation, adjusting, and finishing.
1.10.2.6 MANUFACTURER’S WARRANTY. Submit all manufacturer’s warranties given to the Contractor for products used in the Contract.
1.10.2.7 CATALOG DATA. Mark each copy to identify applicable products, models, options, and other data; supplement manufacturer’s standard data to provide information unique to the work.
1.10.2.8 CONTRACTOR-PROVIDED TRAINING.
1.10.2.8.1 The Contractor shall be responsible for the instruction and training of operating and maintenance personnel as specified below.
1.10.2.8.2 The Contractor shall provide competent instructors for training of personnel designated by the Contracting Officer to operate systems and equipment, perform the required preventive maintenance to minimize breakdown and to perform necessary repairs when malfunction or breakdown of equipment occurs. Such training shall consist of on the equipment and/or classroom training for the periods specified, which shall be completed prior to project completion. The instructor(s) shall have no other duties during the period of training. Classroom instruction, where applicable, shall not exceed 50 percent of the total training time, with the balance devoted to on-the-equipment demonstration and familiarization. Emphasis will be given to both electrical and mechanical features, in accordance with approved training plans.
1.10.2.8.3 The training shall be for not less than the periods of time specified, 5 days per week and 8 hours per day, subject to approval by the Contracting Officer. Each individual training session shall be presented one time only and shall be scheduled in a manner acceptable to the Contracting Officer. The operating and maintenance manual data shall be used as the base material for training. Training shall be limited to normal business hours, Monday through Friday, federal holidays excluded.
1.10.2.8.4 For each individual training session, the Contractor shall provide to the Contracting
Officer no later than 30 days after completion of the training session three reproducible copies of all reference materials/handouts provided by the Contractor to trainees at the training session. These training reference materials/handouts shall be labeled with title, subject(s), and date(s) of the training session(s) at which they were provided to trainees.
1.11 RECORD DRAWINGS
1.11.1 The contractor will use Autodesk Version 2013+ software for this government contract.
1.11.2 The contractor will be required to obtain Vandenberg 30 CES CAD Standards CD or zip file from the 30 CES Engineering Drawing Vault and can request Vandenberg CAD Standards orientations if necessary to support compliance for government contracted work. The foundation of the standards are based of US Army Corps of Engineers A/E/C CAD Standard.
1.11.3 Percentile deliverables for designs or studies will include 30CES CAD AutoCAD (dwg) submission for Vandenberg 30 CES CAD Standards compliance review. Final or 100% for design and or studies AutoCAD files to be submitted, reviewed and approved prior to contract close out. The AutoCAD (dwg) file is the digital reproducible and will require stamps for disciplines requiring a stamp.
1.11.4 As-Built AutoCAD files are to be submitted at the end of any construction and will be reviewed and approved for Vandenberg 30 CES CAD Standards compliance. The AutoCAD (dwg) file is the digital reproducible and will require stamps for disciplines requiring a stamp.
1.11.5 It is the prime contractor’s responsibility to ensure all AutoCAD (dwg) files utilize a spatial reference consistent with Vandenberg GeoBase Office (see 1.14.E), fully accurate according to the actual conditions, coordinate values for all discovered and installed underground utilities including all relevant survey data used, fully compliant with Vandenberg CAD Standards. Any provided drawings do not relieve the contractor of this responsibility, although they may be used towards this effort. Documents and AutoCAD (dwg) must show all details of the project as constructed, clean of extraneous information and be readable and not cluttered.
1.11.6 Documents and CD/DVDs shall be labeled with a minimum of the Prime Contractor’s name, point of contact, phone number, the project number and title, the facilities involved, date of submission, submission revision number (if applicable), and shall be labeled as Controlled Unclassified Information or “CUI”.
1.11.6.1 Percentile and As-Built deliveries will provide One (1) set of full size (30x42) hard copy drawings on archival quality paper to the 30 CES Engineering Drawing Vault along with the CD/DVD with AutoCAD project files (dwg and supporting files). A PDF copy shall also be included.
1.11.6.2 Once CAD drawings are reviewed/accepted by the 30 CES Engineering Drawing Vault, the 30CES PM and Contracting Officer must receive at least one CD/DVD each containing all record drawings / as-built in AutoCAD and PDF formats.
1.11.7 The final As-Builts shall be submitted within 30 days of the Final Inspection, unless indicated differently in the Contract. The As-Built submissions must be submitted and approved by the 30 CES Engineering Drawing Vault before the end of the Period of Performance of the contract. Up to 7% of the total contract cost, or the contractual line item cost (whichever is greater), may be withheld until these are fully complete and coordinated.
1.11.8 The final As-Builts shall be fully compliant with all VSFB CAD Standards and shall show all details of the project as constructed. Documents must be clean of extraneous information and be readable and not cluttered
1.12 ENERGY EFFICIENCY
1.12.1 Energy-efficient technology and equipment is required for all projects at Vandenberg
SFB as mandated by the Energy Policy Act of 1992. Local utility rebate programs shall be used as the minimum criteria for achieving energy efficient design.
1.12.2 For electrical requirements, contact PG&E Representative, at (805) 595-6304, or (805) 595-6324 for specific information and requirements on the PG&E Rebate Program.
1.12.3 The Contractor shall submit energy efficiency data along with other submittal requirements for the following list of equipment as specified under each section of the specifications:
SECTION 11400 - FOOD SERVICE EQUIPMENT
SECTION 15140 - PUMPS
SECTION 15170 - MOTORS
SECTION 15540 - HVAC PUMPS
SECTION 15658 - RECIPROCATING REFRIGERANT COMPRESSORS
SECTION 15671 - AIR-COOLED CONDENSING UNITS
SECTION 15682 - AIR-COOLED WATER CHILLERS
SECTION 15684 - CENTRIFUGAL WATER CHILLERS
SECTION 15781 - PACKAGED ROOFTOP AIR CONDITIONING UNITS
SECTION 15784 - UNIT AIR CONDITIONERS
SECTION 16170 - MOTORS
SECTION 16510 - INTERIOR LUMINAIRES
1.13 GLOBAL POSITIONING SYSTEM (GPS) REQUIREMENTS
Contract shall follow the below at a minimum, unless directed to follow a more stringent standard by the 30 CES Engineering Drawing Vault, or other contract documents/requirements. If contract dictates official mapping data for the GIO in support of GEObase, the contractor will follow at a minimum the following for all contracted work (see 1.14.A.2), utilizing Earth Science Research Institute (ESRI) software version 10x. Unless noted in other contract documents/requirements.
1.13.1 GPS Receiver
To ensure that the appropriate type of GPS receiver is matched to the mapping application, an understanding of receiver capabilities and limitations is required. There are basically three classes of GPS receivers:
1.13.1.1 Recreational Grade
These devices have an accuracy within five to twenty meters. These GPS receivers usually do not have the ability to "post-process" collected data, but usually have the ability to perform real time correction using Wide Area Augmentation System (WAAS).
GPS receivers can be used to navigate to a specific area and/or compile uncorrected GPS data, using associated third party software to convert the collected data directly into GIS supported data formats. Most modern “smart phones/tablets”, auto GPS devices, and Garmin GPS devices fall into this category.
1.13.1.2 Mapping Grade
These have an accuracy from sub-meter to five meters. These GPS receivers have the ability to log raw GPS data, enabling these GPS-collected data to be post-processed utilizing desktop GPS software and allowing locations to be refined or corrected to a higher level of precision than inherent in the raw data. This category of GPS receiver also has the ability to communicate with a base station, store attributes of features, use a data dictionary and upload data from the GPS device to a PC.
1.13.1.3 Survey or High Accuracy Grade
These include instruments with associated software that can achieve one centimeter relative accuracy. These are used by land surveyors primarily for boundary, topographic, and geodetic surveys, photogrammetry, and other activities requiring high accuracy.
Specialized training is needed to use this equipment.
The GPS receivers used to collect all GPS data for the VEGR will depend upon the project. However, regardless of the project, the GPS receivers must be of Mapping Grade or better. For certain engineering projects (buildings/bridges/surveys), Survey or High Accuracy Grade GPS devices will be required. The GPS devices must:
1.13.1.3.1 Routinely achieve 60 centimeter or better horizontal accuracy, using either real time or post processed differential corrections.
1.13.1.3.2 Operates in a 3D mode where the receiver requires signals from a minimum of four satellites to determine a 3D (latitude, longitude, and elevation) location (a fix).
1.13.1.3.3 Allow the storage of position fixes for features that are being mapped. When mapping point features, the receiver must be able to store position fixes (the minimum number depending on the quality of the receiver) for the feature. The receiver must have enough data storage capacity for a typical day’s worth of data collection.
1.13.1.3.4 Be user configurable for critical settings, including DOP, SNR, elevation mask, and logging rate.
1.13.1.3.5 Produce and store data in a format compatible with the base station data used to perform the differential corrections or have the capability to receive real-time corrections from the base station.
The Vandenberg GeoBase Office currently utilizes Trimble GeoExplorer 6000 series devices with Trimble Pathfinder Pro receivers and Terrasync GPS collection software.
This setup routinely allows GPS technicians to achieve post processed 30 centimeter horizontal accuracy (Real Time accuracy is close to 60 centimeters)
1.13.2 Field Data Collection Parameters
To achieve the target accuracy, all collected GPS data must be differentially corrected, either in real time or in a post process step. The following parameters will help to assure that accuracy standards are met:
Position Mode All position fixes must be determined with 7 or more satellites
Elevation Mask 15 degrees above horizon.
PDOP Mask Max PDOP = 3
Signal to Noise Ratio Mask (SNR) If this parameter setting exists, set it to 39.0
Minimum Positions If this parameter setting exists, set it to the manufacturer for point features recommendation that would, at a minimum, allow the GPS data collected to achieve the accuracy standard. Recommend using a minimum of 60 1-second positions. Solutions based on a single fix are not acceptable.
Logging Intervals Intervals for point features will be 1 second. Line and polygon features should be collected as a set of point features that can connected using GIS software.
Logging of DOP If the receiver allows, this parameter setting will be set to allow the logging of DOP data along with position fixes.
1.13.3 Attributing GPS Features (SDSFIE 3.1.0.1)
During GPS data collection, GPS technicians will collect and attribute GPS features based on the spatial feature in VEGR. For example, if a water line is being installed, attributes like pipe size, pipe composition, and pipe designation (Primary vs Secondary) would be required attribution. The contractor is responsible to work with the Vandenberg GeoBase Office for questions on feature attributions.
1.13.4 Processing of GPS Field Data
All GPS data collected for the Port must undergo some post processing steps using GPS processing software before the data can be used to generate a GIS layer. The exception to this step is if the GPS device is able to achieve real time accuracy that meets the 60 centimeter accuracy standard. To assure accuracy standards are adhered to, the Vandenberg Geobase office routinely checks GPS locations of engineering, utility, and communications projects for accuracy.
The GPS processing software must be able to download GPS data files from the GPS receiver, and perform differential corrections. In addition, it must allow exporting the corrected data to a GIS compatible format (File Geodatabase or Shapefile), in the correct coordinate system. Refer to the section below for specific information on the required coordinate system.
1.13.5 GPS Base Stations for Post Processed Differential Corrections For post processed differential corrections, several resources exist for GPS base station data in California.
The nearest operating base station with the highest integrity rating should be used. The Vandenberg GeoBase office has a base station located on top of building 11439 and runs 24/7. Base station files from this base station can acquired from the Vandenberg GeoBase office.
1.13.6 Output to GIS
As stated previously, the preferred GIS data submittals should be in either ESRI File
Geodatabase or Shapefile formats. The GPS processing software must allow for exporting to one of these formats. CAD export files will not be accepted. Refer to the section below for specific information on the required coordinate system.
1.13.7 Elevation Data
If elevation data is required by the project, it will be referenced to the North American
Vertical Datum of 1988 (NAVD 88) vertical geodetic datum. Elevations must be generated as orthometric heights (relative to mean sea level) determined using the GEOID99 (Continental US) geoid conversion model. Conversions from other geoid conversion models are not acceptable.
1.13.8 Spatial Reference
The all GPS data must be delivered using the VEGR Spatial Reference as noted below.
Vandenberg SFB and surrounding local GSUs Projection: California State Plane Zone: NAD 1983 2011 State Plane California Zone V 0405 Units: US Foot Horizontal Datum: North American Datum (NAD) 1983 Vertical Datum: North American Vertical Datum (NAVD) 1988
Pillar Point AFS Projection: NAD 1983 2011 State Plane California Zone III 0405 Zone: III Units: US Foot
Horizontal Datum: North American Datum (NAD) 1983 Vertical Datum: North American Vertical Datum (NAVD) 1988
1.13.9 Deliverables
If GPS data collection work is being performed by a contractor, final deliverables will include:
1.13.9.1 All GPS field data files, both uncorrected and corrected versions, must be submitted.
If field data was collected in real time differential mode, then there will not be uncorrected files, and only the real time corrected files are necessary. If edits are made to corrected files (i.e., fixes deleted or offset), copies of both edited and unedited are to be submitted.
1.13.9.2 All GPS to GIS export files, using the correct spatial reference detailed in 1.14.H.
GIS files must use ESRI File Geodatabase. Shape File format maybe accepted on a case by case need if requested and approved by the Vandenberg GIO.
1.13.9.3 All GPS processing log files pertaining to post process differential correction and GIS export (if produced).
1.14 SPECIFICATIONS AND REQUIREMENTS
1.14.1 All projects at VSFB shall meet requirements including but limited to the following: all
VAFB and VSFB specific specifications and requirements, UFCs, Whole Building Design Guide/UFGS, Federal/State/Local laws, OSHA, NFPA, etc.
PART 2
2 PRODUCTS (Not Used)
PART 3
3 EXECUTION (Not Used)
END OF SECTION
| PART 1 - GENERAL |
| END OF SECTION |