About this file
This document contains the First Article Requirements for a federal contract opportunity to procure a Linear Actuator and Cylinder Assembly for the UH-1N helicopter. The First Article is required to be 1 unit, with contractor testing and a test report required. Specific technical requirements for the First Article are contained in Drawing 209-062-214. Approved First Articles will be forwarded to supply, while disapproved First Articles will be returned to the contractor. The document provides details on the contract number, NSN, disposition of First Articles, and the cognizant engineering organizations responsible for approving and conducting the testing. This First Article requirement is part of a larger contract opportunity to overhaul UH-1N dynamic components, which are flight-critical safety items used on the USAF's UH-1N helicopter fleet.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0001_Extend_Proposal_Due_August_19_ 2024.pdf | ||
| Atch_6_CAVAF_CFM_Reporting_Requirement.pdf | ||
| Atch_11_First_Article_Cylinder_Assembly_NSN_4775_GA.pdf | ||
| Atch_2_PKGRQMT_REPORT_Amendment_02.pdf | ||
| Atch_8_Government_Furnished_Property_1.pdf | ||
| Atch_1_Exhibit1_CDRLS_07022024.pdf | ||
| Atch_7_DD2875_System_Authorization.pdf | ||
| FA8524-24-R-0602 03 July 2024 F.pdf | ||
| Atch_4_Source_Pre_Qualification_Requirements_SIGNED.pdf | ||
| Atch_3_TRNSPDATA_REPORT_Amendment_02.pdf | ||
| Atch_12_First_Article_Cylinder_Assembly_NSN_4776_GA.pdf | ||
| Atch_5_PWS_Final_10_June_24.pdf | ||
| Atch_9_First_Article_Actuator_NSN_6453_GA.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FIRST ARTICLE REQUIREMENTS 1. DATE
08 FEB 2024(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)
2. PR / MIPR NUMBER 3. CAGE / REFERENCE NUMBER
97499 / 209-062-214-1
4. NSN
1680004008271GA
5. FIRST ARTICLE QUANTITY
THE FIRST ARTICLE IS 1 UNIT(S) OF LOT / ITEM x
AND WILL BE: PART OF PRODUCTION QUANTITY X IN ADDITION TO PRODUCTION QUANTITY
6. ARTICLES
X WILL WILL NOT SERVE AS A MANUFACTURING STANDARD
7. LONG LEAD TIME ITEMS
X REQUIRED NOT REQUIRED
(See FAR 52.209-3 OR -4, alternate II)
8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 OR -4 Alternate I)
X REQUIRED NOT REQUIRED
"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."
9. TEST / INSPECTION REQUIREMENTS
A. X CONTRACTOR TESTING
GOVERNMENT TESTING
Performance or other characteristics which the First Articles must meet are
MATERIAL, DIMENSIONAL AND FINISH (ENVIRONMENTAL) SPECIFICATIONS
B. The detailed technical requirements for First Article approval tests are contained in
Drawing:209-062-214
(Cite Spec and Para number)
C. X TEST PLAN REQUIRED
Number of days for government approval / disapproval 45 days.
D. Contractor's notification to ACO and traci.polk@us.af.mil
(Requesting Activity) of test time and location due 30 days prior to start of testing.
E. X TEST REPORT REQUIRED
(1) Forwarded to
See Remarks in Note 1
(2) Government written notice of approval / disapproval due 30 days after receipt of contractor's report.
F. FIRST ARTICLE DELIVERY
(1) Due within calendar days from date contract.
(2) Notify calendar days prior to shipment.
(3) Delivered to government at
(Set Forth Consignee and Address)
(4) Government written notice of approval / disapproval within 45 days after receipt of first article package.
G. Estimated cost of government testing / inspection evaluation.
$1,730.0000
Page 1 of 3AFMC IMT 260, 20020830, V-3 Version 1Generated by PRPS using Jasper Reports on 22 Feb 2024
08 FEB 2024(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)
10. DISPOSITION OF FIRST ARTICLES
X Approved First Articles will be forwarded to
Supply
(insert quantity) First Articles will be expended in testing. Residual components of disapproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.
First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.
X Disapproved First Articles
X will be returned to the contractor will be retained by pending disposition instructions from the contractor.
On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).
a. Approved First Articles will be returned to the contractor for shipment with production item.
b. Disposition of disapproved First Articles will remain the same as marked above.
Other Disposition:
11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL
a. Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the Government, DoD, Air Force.
b. Offerors currently in production of the same or similar article for a Government, DoD, Air Force contract and who have received First Article approval under the existing contract.
c. Offerors who have previously furnished production quantities of the same or similar articles to the Government, DoD, Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.
d. Provided not more than months have elapsed since completion of the contract.
e. X First Article testing will not be waived.
f. See Remarks in block 12 below.
NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED ARTICLE:
A. PROCURING OFFICE B. CONTRACT NUMBER C. DATE OF CONTRACT D. SPECIFICATION NUMBER AND REVISION
12. REMARKS
Giddens, Coby FNAME: 21 FEB 2024DATE:
Note 1: Ship First Article Test Report to:
Attn: Traci Polk DLA Central Receiving/DDWG-ER Special Handling: FA UNIT-DO NOT POST 455 Byron St, Bldg 376 Robins AFB, GA 31098-1887 Note 2: First article test report should include:
1. Certifications for all purchased hardware/material.
2. Dimensional check worksheet.
3. A copy of the latest calibration certifications for all measuring instruments used to perform the dimensional checks.
4. Certifications for any work not performed by the contractor, if applicable.
5. Job travelers. Job travelers should include process from start to finish, even if the first article is requested without coatings.
6. Results of all testing requirements indicated on drawing.
Note 3: Waiver conditions apply only to production of same, and not similar, article.
Page 2 of 3AFMC IMT 260, 20020830, V-3 Version 1Generated by PRPS using Jasper Reports on 22 Feb 2024
08 FEB 2024(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)
13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR APPROVING TEST
(Name, Organization, Phone)
Giddens, Coby F
AFLCMC / WI U E D
478-926-7255
468-7255
14. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR CONDUCTING
TEST (Name, Organization, Phone)
Page 3 of 3AFMC IMT 260, 20020830, V-3 Version 1Generated by PRPS using Jasper Reports on 22 Feb 2024