This statement of work outlines requirements for a fitness facility flooring project at Building 501 gym at Pope Army Airfield in North Carolina. The contractor will remove existing rubber tile flooring and replace it with two layers of 10mm thick Mondo Sport Impact flooring in black color to cover 4,000 square feet. The contractor must provide all labor, equipment, materials including the flooring and polyurethane adhesive, transportation, insurance, and safety measures. Work must be performed from 0730 to 1630 hours Monday through Friday according to the coordinated schedule without interfering with student training. The contractor will be responsible for clean-up and providing a one-year warranty on all work. The related federal contract opportunity is a solicitation from the Department of the Air Force Air Mobility Command for the fitness facility flooring project at the specified location.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA445223Q0035 - QnR.pdf | ||
| Bldg 502 Layout (Gym area in red block).pdf | ||
| Atch 3 - Product Specs - Advance 10mm R052223.pdf | ||
| Combined Synopsis Solicitation - Fitness Facility Flooring.pdf | ||
| Atch 2 - Quote and Contract CLIN Schedule.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FITNESS FACILITY FLOORING PROJECT
BLDG. 501 GYM
352 SWTS, POPE AAF, NC
1. DESCRIPTION OF SERVICES
1.1 The contractor shall provide all labor, equipment, tools, materials, transportation, supervision, and other items and services necessary to remove existing rubber tile flooring in main gym and replace with Mondo rolled rubber flooring per specifications.
1.2 The completed project shall comply with all DoD Codes & Regulations (UFC, ABA, IBC, Fort Bragg Design Guidelines) as it specifically related to the scope of work.
1.3 SCOPE OF WORK: The following scope of work shall serve as general information only and shall not limit the contractor’s responsibility or obligations to perform all tasks(s) within local, state, and federal laws as well as manufacturer’s recommendations. All quantities in this statement of work are close approximates, the contractor shall be responsible for completing the requirements of this SOW regardless of the actual quantity measurement.
2. PERSONNEL
2.1 The contractor shall provide supervision that is experienced, fully qualified, and well versed in terminology and technical process, procedures, means, and methods related to the work. The supervisor shall maintain direct control and surveillance of all contractor personnel who are performing the work.
2.2 The contractor shall submit Materials Submittal(s) for review and approval.
3. WORKING HOURS AND SCHEDULING
3.1 Work will be performed during normal duty business hours: 0730-1630 M-F.
3.2 Work will be done in such as manner as to not interfere with student training. The contractor will coordinate with the unit representative/ Facility Manager (Mr. Dan Kaster) to ensure schedule does not interfere with student training.
3.3 The contractor will be required to coordinate with the Facility Manager and any Government contracting office representative within 48 hours after contract award to establish a work schedule. Work will be inspected, repaired, and completed within a timely manner within the agreed upon schedule of the contract.
4. SECURITY
4.1 All workers will be legal U.S. Citizens with legal picture ID’s and able to gain a clearance on to the military installation.
4.2 No guns, drugs, or illegal paraphernalia will be allowed on the military installation.
4.3 All vehicles, equipment, and containers will be subject to search at any time while on or seeking access to the military installation.
4.4 The contractor shall provide liability insurance, vehicle insurance, workman’s compensation insurance, etc. as required.
5. GENERAL NARRATION OF WORK: Work will be performed at BLD 502, Contractor will perform all work necessary to remove existing rubber tile flooring in the gym.
Contractor will replace rubber tile flooring with two layered rolled Mondo flooring.
Contractor will ensure seamless floor transitions to include thresholds and base boards.
Replace all base boards with four-inch tan rubber coping to match existing.
5.1 MATERIALS:
5.1.1 MONDO Sport Impact Flooring 10mm – 6’W rolls, to cover 4,000 sf. Color:
Black. See Product Spec sheet for additional information.
5.1.2 PU 105 Polyurethane Adhesive
6. PROTECTION OF GOVERNMENT PROPERTY
6.1 The contractor will protect all government and personal property from damage.
7. SAFETY
7.1 All OSHA standards will be complied with.
7.2 Proper PPE will be worn at all times.
7.3 Best practices of safety in the workplace will be adhered to at all times.
7.4 Any electrical, gas, or chemical conditions affecting the work will be coordinated with Facility Manager, if the unforeseen condition requires a modification to the contract the subsequent work will be done by licensed personnel only.
7.5 All tools and materials will be cleaned up and stored safely at the end of the workday or on extended breaks (i.e., lunch).
8. INSPECTION AND ACCEPTANCE
8.1 When work is complete the Unit Facility Manager will inspect the work for completion and quality prior to the job being accepted.
8.2 A minimum of a 12-month warranty on all work (material and labor) will be required in writing upon job completion and prior to final payment.
9. FINAL CLEAN UP
9.1 Upon completion the contractor will adhere to industry standards for clean-up and remove all work-related debris as required. Final payment will be contingent on Unit Facility Manager’s inspection and approval of clean-up.
End of SOW
| STATEMENT OF WORK |
| FITNESS FACILITY FLOORING PROJECT |
| BLDG. 501 GYM |
| 352 SWTS, POPE AAF, NC |
| 1. DESCRIPTION OF SERVICES |
| 2. PERSONNEL |
| 3. WORKING HOURS AND SCHEDULING |
| 4. SECURITY |
| 5. GENERAL NARRATION OF WORK: Work will be performed at BLD 502, Contractor will perform all work necessary to remove existing rubber tile flooring in the gym. Contractor will replace rubber tile flooring with two layered rolled Mondo flooring. Con... |
| 5.1 MATERIALS: |
| 5.1.1 MONDO Sport Impact Flooring 10mm – 6’W rolls, to cover 4,000 sf. Color: Black. See Product Spec sheet for additional information. |
| 5.1.2 PU 105 Polyurethane Adhesive |
| 6. PROTECTION OF GOVERNMENT PROPERTY |
| 7. SAFETY |
| 8. INSPECTION AND ACCEPTANCE |
| 9. FINAL CLEAN UP |