Atch_1_SOW.pdf
PDF 17 MB Posted
- Attached to
- Hot Springs NP-Paint Exterior Reserve Street Bldgs Federal contract opportunity
- Solicitation number
- 140P6326Q0007
About this file
This is a Statement of Work (SOW) for exterior painting services at Hot Springs National Park in Hot Springs, Arkansas, covering multiple historic and non-historic buildings. The work scope includes painting the exterior of Quarters 70 and 71 (two-story historic buildings built 1930-1933 with detached garages), the Medical Director's Residence (MDR, a historic 1912 colonial revival structure with 37 exterior windows and 9 painted doors), the Bally Building (non-historic, 1994), and the Surplus Building (non-historic, 1992). The contract encompasses approximately 13,764 total square feet of painted surfaces across all structures. Work includes surface preparation (scraping, sanding, low-pressure washing not exceeding 600 psi), substrate repairs including wood siding, soffit, fascia, and caulking replacement, putty re-glazing of windows, and application of paint systems. The contract period is 90 calendar days from the Notice to Proceed, with the contractor responsible for incorporating supply lead times, material deliveries, weather allowances, and project decommissioning within this timeframe.
The SOW specifies strict adherence to historic preservation standards given the National Register listing of several structures, requiring repairs and replacements to match existing materials in kind with similar grade, quality, size, texture, and profile. Paint systems must comply with Master Painters Institute (MPI) standards: Latex over Latex Primer (MPI EXT 6.3L) for dressed wood substrates across all buildings, Alkyd Floor Enamel (MPI EXT 6.5B) for traffic surfaces at the MDR, and Latex System (MPI EXT 9.1J) for stucco substrates at the MDR and its garage. Colors must be approved by the Contracting Officer's Representative (COR), with contractors required to submit three color swatches and provide mockup samples of at least 9 square feet. Contractors must establish a comprehensive Accident Prevention Plan, conduct weekly toolbox safety meetings, provide daily progress reports and updated schedules, maintain OSHA compliance, and document all work through photography. On-site work is limited to 8 a.m. to 4 p.m. Monday through Friday, with requests for extended hours requiring 48-hour advance approval. The contractor is responsible for all temporary services, equipment, waste removal and recycling, equipment cleaning to prevent invasive species introduction, and maintaining existing utility services with minimal disruption. Work must preserve cultural resources and immediately suspend operations if archaeological remains are discovered.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6326Q0007_Amd_0002.pdf | ||
| Sol_140P6326Q0007_Amd_0001.pdf | ||
| Atch_3_DOL_Wage_Determination_AR20260028_1_2_26.pdf | ||
| Sol_140P6326Q0007.pdf | ||
| Atch_2_Experience_Questionnaire.xls | XLS spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Div. 1 V. 2023-11-11 Page | 1
Hot Springs National Park 101 Reserve Street, Hot Springs, AR 71901
Paint the Exterior of Reserve Street Buildings
PMIS 203737, 212020
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
2025-12-30
Page | 2
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 - Division 01 Short Form General Requirements
DIVISION 09 – FINISHES
Section 09 91 13 Exterior Painting
SITE PLANS AND PHOTOGRAPHS – APPENDIX A
Page | 3
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: Reserve Street Buildings: The historic Quarters 70 and 71 were built between 1930 and 1933. Each building is two stories, with a basement. There are two sides to each building (an A and a B side), with each side being a mirror of the other side. Total gross square footage for each building is approximately 4,700 square feet. Each building has a historic, detached garage for a total of two detached garages: the East Garage, Building 72; and the West Garage, Building
73. The gross square footage of each garage is approximately 1,132 square feet. The non-historic Bally Building was built in 1994, and its total gross square footage is approximately 1,517 square feet. The non-historic Surplus Building was built in 1992, and its total gross square footage is approximately 947 square feet.
The historic Medical Directors Residence (MDR) was built in 1912. This building is located on Reserve Street and is located near the Quarters 71 building. The MDR is a two-story wood frame colonial revival, with a basement and a large, developed attic. The total gross square footage of the MDR is approximately 10,170 square feet. The MDR has a historic, detached garage. The gross square footage of the MDR’s garage is approximately 550 square feet. The building includes four exterior porches with tongue and groove wood decks and wood handrails and columns.
1.2 Work Covered by the Contract Documents:
A. Project Location: Quarters 70 and its detached garage, the West Garage; Quarters 71 and its detached garage, the East Garage; the Medical Directors Residence (MDR) and the MDR’s detached garage; the Bally building; and the Surplus building are all located near 527 Reserve Street within the city of Hot Springs located in Garland County, Arkansas.
Work consists of: The Contractor shall field verify all conditions, square footage, measurements, and quantities related to the project. Quantities and square footages listed in the Contract Documents are for general reference only.
The Contractor shall repair any surfaces scheduled for painting, including but not limited to repairing all substrates, patching cracks in masonry and stucco, and repairing all wood and masonry joints. Soft, rotten, damaged, or deteriorated wood, or any other substrate materials, must be repaired or replaced in kind. When replacement is necessary, the Contractor shall use the same type of material, ensuring that the species matches if the material is wood. All replacement materials must also be of similar grade, quality, size, texture, and profile to the original. All stucco and masonry repairs are to match the existing surface and/or structure. All repaired or replaced substrate materials must be installed seamlessly to maintain the historic character and achieve a like-new appearance consistent with the original construction.
Page | 4
Surface preparation, to include low-pressure washing and cleaning of all exterior surfaces. Given that all buildings are historic, painted surfaces must be gently cleaned using water at a relatively low pressure prior to painting. Acceptable water pressure is equivalent to that of a garden hose with an attached spray nozzle, and the maximum allowed pressure shall not exceed 600 psi.
The Contractor shall prepare substrates as required to ensure proper paint adhesion, which may include sanding and scraping surfaces where the existing paint is peeling or deteriorated.
Deteriorated caulking shall be removed and reapplied. All new caulking must match the existing color and be installed to blend seamlessly with the existing construction. All deteriorated caulking must be removed before new caulk is applied (refer to the Master Painters Institute [MPI] for further guidance). The Contractor shall provide color samples for caulking to the Contracting Officer's Representative (COR) for approval.
New paint shall match the existing color for all surfaces. The Contractor shall provide three color swatches for each proposed color to the COR, and the final colors for each building will be determined by the COR.
Contractor shall not paint any windows shut and shall remove storm windows when applicable. Mask all surfaces not to be painted (i.e. aluminum frames for windows and doors). Do not paint on brick or stone sills.
The Contractor shall temporarily disconnect downspouts, downspout brackets, soffit vents, or other fastener attached elements not to be painted in order to uniformly apply paint across entire faces of the buildings. Gutters, electrical conduit, utility boxes, or other permanently affixed items that cannot be efficiently removed and reinstalled are not required to be disconnected.
Painting operations for most of the buildings will likely require the use of either an aerial lift or scaffolding.
Use of an aerial lift for any and every location will require COR approval prior to any work.
Painting and repairs will consist of:
Quarters 70:
-Paint the exterior of the historic Quarters 70, approximately 1,324 square feet plus all exterior painted windows, doors, eaves, soffit, and fascia. Puddy re-glaze all windows. Repair approximately 420 square feet of wood siding, front porch elements, soffit, and fascia.
-Paint the exterior doors of Quarters' 70 detached garage, approximately 230 square feet.
Quarters 71:
-Paint the exterior of the historic Quarters 71, approximately 1,324 square feet plus all exterior painted windows, doors, eaves, soffit, and fascia. Puddy re-glaze all windows. Repair approximately 420 square feet of wood siding, soffit and fascia.
-Paint the exterior doors of Quarters' 71 detached garage, approximately 230 square feet
Bally and Surplus Building:
-Paint the exterior of the Bally Building, approximately 2,100 square feet plus all exterior painted windows, doors, eaves, soffit, and fascia. Repair approximately 100 square feet of siding, soffit, and fascia.
Page | 5
-Paint the exterior of the Surplus Building, approximately 1,500 square feet plus all exterior painted windows, doors, eaves, soffit, and fascia. Repair approximately 100 square feet of wood siding, soffit, and fascia.
Medical Director’s Residence and Garage:
-Paint the exterior of the historic Medical Director's Residence (MDR), approximately 4,700 square feet of stucco plus all exterior painted windows, doors, eaves, soffit, and fascia. There are approximately 37 exterior, wood-framed windows and approximately 9 exterior painted doors. Repair approximately 1800 square feet of wood elements to include porch deck and porch ceiling, soffit and fascia, and wood siding.
-Paint the exterior of the MDR Garage, approximately 690 square feet of painted stucco and wooden eaves, and approximately 100 square feet for the painted garage door, the exterior door, exterior windows, eaves, soffit, and fascia. Repair approximately 60 square feet of wood soffit and fascia.
B. All work will be performed under a single contract.
C. Period of performance: Work shall be completed within 90 calendar days of the start date provided on the Notice to Proceed.
a. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts the project beyond typical average weather patterns, contractor shall provide documentation in a request for additional days.
1.3 Existing Condition Protections:
A. Preservation of Historical and Archeological Fabric:
i. The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological remains or data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts not specifically noted within the contract. The Contractor shall immediately suspend all operations in the vicinity and continue work in other areas outside a 50-foot radius of discovery and notify the Contracting Officer immediately. When safe to do so, follow up in writing with photographs within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
Page | 6
iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
v. The Contractor agrees to include this language within all subcontracts.
B. The structure involved in the work of this Contract is a designated historic structure listed in the National Register of Historic Places. Every precaution shall be taken by the Contractor to prevent damage to existing historical materials, structural components of the building and to the surrounding area. Should any damage be incurred as a result of the Contractor’s operations at the site, it shall be repaired, or the damaged materials replaced in kind by the Contractor to the satisfaction of the Contracting Officer at no additional expense to the Government.
C. There is no excavation required for this project.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative
(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park
Page | 7
Service, and applicable park rules and regulations prescribed by the Park Superintendent.
https://www.nps.gov/hosp/learn/management/superintendents-compendium.htm
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited-service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
8 am to 4 pm., Monday through Friday, except when otherwise indicated. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year’s Day Inauguration Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
• Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.
https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022
Page | 8
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Do Not disturb site outside of noted disturbance area, including earthwork, and clearing of vegetation, to:
1. N/A
Contractor shall provide appropriate matts for equipment on turf areas to reduce soil compaction. Contractor shall remediate soil compaction as directed to do so by the CO/COR.
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract
Sum as required.
2. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.
3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.
4. Sanitary Operations:
a. Toilets: Contractor shall be able to use the existing park restroom facilities, specific location to be discussed during the preconstruction meeting. The restroom facilities shall be kept in immaculate condition. At the discretion of Park personnel and/or COR;
contractor may lose the use of the restroom facilities if they are not kept clean and orderly. Restroom use will be a “One strike and you’re out” policy. If restroom privileges are revoked Contractor will be required to provide a toilet for contracting personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free
Page | 9 of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant protection is not required for this project.
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
5. Temporary Enclosures: Not required.
6. Hot Work Permit: Not Required
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location within staging area shown in appendix A below may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility.
3.5 Preservation of Natural Features: N/A
3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.
3.7 Waste Removal, Recycling, and General Housekeeping:
A. Keep project site in a neat, orderly, and safe condition at all times.
1. Contractor is responsible for providing dumpsters for waste and recycling and for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site.
Coordinate with COR for approved dumpster locations prior to commencing construction.
2. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters.
3. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to the extent possible during this project, recycling material as much as possible within local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
Page | 10
4. For all waste and recycling removals offsite, contractors shall provide estimates and/or tickets to quantify material weights and report back to the park, submit to COR for review and record filing.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated. Contractor will maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR. Contractor will maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
B. New /Existing Buildings Unoccupied:
1. N/A
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
Page | 11
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA
29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
B. Noise Control: Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
C. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.
a) Coordinate with COR prior to execution
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926
Page | 12
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.
5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute
"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
https://www.nps.gov/orgs/1671/do-business-with-us.htm
Page | 13
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain 2 sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate, if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification Sections. Types of submittals are indicated in individual specific sections.
Page | 14
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet, and a list of required submittals is included in each technical specification or attached at the end of this document.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.
Paint samples shall be actual paint finish drawdown for all project colors.
Page | 15
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
E. After approving submittals, Contracting Officer and/or COR will return one copy to the Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the
Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is
Page | 16 issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
Page | 17
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of
Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
A. Contract Line-Item No. CLIN 010 Paint Reserve Street Buildings and Paint Medical Director's Residence (MDR)
1. This item consists of CLIN 010 Paint Reserve Street Buildings and Paint Medical Director's Residence (MDR).
2. Payment will be made per the contract and percentage of completion level.
END OF SECTION
SECTION 099113
EXTERIOR PAINTING
PART 1 - GENERAL
1.1 SCOPE OF WORK
A. Project Location: Hot Springs National Park; 101 Reserve Street, Hot Springs, Arkansas 71901
B. Building(s) Name/Identifier:
1. Quarters 70
2. the West Garage (for Quarters 70)
3. Quarters 71
4. the East Garage (for Quarters 71)
5. the Medical Director’s Residence (MDR)
6. the MDR’s Garage
7. the Bally building
8. the Surplus building
1.2 SUMMARY
A. Section includes surface preparation and the application of paint systems on the following exterior substrates:
1. Wood.
2. Portland cement plaster (stucco).
1.3 DEFINITIONS (Master Painters Institute-MPI)
A. Master Painters Institute (MPI) (http://www.specifypaint.us & http://paintinfo.com/)
B. MPI Gloss Level 1: Not more than five units at 60 degrees and 10 units at 85 degrees, according to ASTM D 523.
C. MPI Gloss Level 3: 10 to 25 units at 60 degrees and 10 to 35 units at 85 degrees, according to
ASTM D 523.
D. MPI Gloss Level 4: 20 to 35 units at 60 degrees and not less than 35 units at 85 degrees, according to ASTM D 523.
E. MPI Gloss Level 5: 35 to 70 units at 60 degrees, according to ASTM D 523.
F. MPI Gloss Level 6: 70 to 85 units at 60 degrees, according to ASTM D 523.
G. MPI Gloss Level 7: More than 85 units at 60 degrees, according to ASTM D 523.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product. Include preparation requirements and application instructions.
1. Include printout of current "MPI Approved Products List" for each product category specified, with the proposed product highlighted.
2. Include Safety Data Sheet (SDS).
http://www.specifypaint.us/ http://paintinfo.com/
B. Samples: For each type of paint system and each color and gloss of topcoat.
1.5 QUALITY ASSURANCE
A. Mockups: Apply mockups of each paint system indicated and each color and finish selected to verify preliminary selections made under Sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution.
1. Contracting Officer’s Representative (COR) will select one surface to represent surfaces and conditions for application of each paint system and color.
a. Vertical and Horizontal Surfaces: Provide samples of at least 9 sq. ft.
b. Other Items: COR will designate items or areas required.
2. Final approval of color selections will be based on mockups.
a. If preliminary color selections are not approved, apply additional mockups of additional colors selected by COR at no added cost to Owner.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. MPI Listing Manufactures as shown on the MPI Approved Products Lists.
B. Products: Subject to compliance with requirements, provide product listed in the Exterior Painting Schedule for the paint category indicated.
2.2 PAINT, GENERAL
A. MPI Standards: Products shall comply with MPI standards indicated and shall be listed in its "MPI Approved Products Lists."
B. Material Compatibility:
1. Materials for use within each paint system shall be compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.
2. For each coat in a paint system, products shall be recommended in writing by topcoat manufacturers for use in paint system and on substrate indicated.
C. Colors: As selected by Contracting Officer’s Representative (COR) from manufacturer's full range.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.
B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows:
1.
2. Wood: 15 percent.
3. Portland Cement Plaster: 12 percent.
C. Verify suitability of substrates, including surface conditions and compatibility with existing finishes and primers.
D. Proceed with coating application only after unsatisfactory conditions have been corrected.
1. Application of coating indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Comply with manufacturer's written instructions and recommendations in "MPI Maintenance Repainting Manual" applicable to substrates and paint systems indicated.
B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.
1. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection.
2. Limit use of power washing on Historic Structures to the extent necessary. Any power washing should be done in a manner to avoid damage to the structure and substrate.
C. Clean substrates of substances that could impair bond of paints, including dust, dirt, oil, grease, and incompatible paints and encapsulants.
1. Remove incompatible primers and reprime substrate with compatible primers or apply tie coat as required to produce paint systems indicated.
2. Note presence of encapsulated lead-based paint. Use all precautions required by law and removal methods appropriate to meet OSHA standards. Provide all protective measures necessary for facility to remain occupied during work and for staff/visitor safety. Dispose of all debris and protective measures as required by law.
D. Concrete Substrates: Remove release agents, curing compounds, efflorescence, and chalk. Do not paint surfaces if moisture content or alkalinity of surfaces to be painted exceeds that permitted in manufacturer's written instructions.
E. Masonry Substrates: Remove efflorescence and chalk. Do not paint surfaces if moisture content or alkalinity of surfaces or mortar joints exceeds that permitted in manufacturer's written instructions.
F. Wood Substrates:
1. Scrape and clean knots. Before applying primer, apply coat of knot sealer recommended in writing by topcoat manufacturer for exterior use in paint system indicated.
2. Sand surfaces that will be exposed to view, and dust off.
3. Prime edges, ends, faces, undersides, and backsides of wood.
4. After priming, fill holes and imperfections in the finish surfaces with putty or plastic wood filler. Sand smooth when dried.
3.3 APPLICATION
A. Apply paints according to manufacturer's written instructions and recommendations in "MPI Maintenance Repainting Manual."
1. Use applicators and techniques suited for paint and substrate indicated.
2. Paint surfaces behind movable items same as similar exposed surfaces. Before final installation, paint surfaces behind permanently fixed items with prime coat only.
3. Paint both sides and edges of exterior doors and entire exposed surface of exterior door frames.
4. Paint entire exposed surface of window frames and sashes.
5. Do not paint over labels of independent testing agencies or equipment name, identification, performance rating, or nomenclature plates.
6. Primers specified in painting schedules may be omitted on items that are factory primed or factory finished if acceptable to topcoat manufacturers.
7.
B. If undercoats or other conditions show through topcoat, apply additional coats until cured film has a uniform paint finish, color, and appearance from corner to corner of wall area.
C. Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks, roller tracking, runs, sags, ropiness, or other surface imperfections. Cut in sharp lines and color breaks.
3.4 CLEANING AND PROTECTION
A. Protect work of other trades against damage from paint application. Correct damage to work of other trades by cleaning, repairing, replacing, and refinishing, as approved by COR, and leave in an undamaged condition.
B. At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces.
3.5 EXTERIOR PAINTING SCHEDULE
A. Wood Substrates: Dressed Wood (trim, Architectural woodwork, Doors, Windows, Wood board siding and wood fences).
1. Latex over Latex Primer System MPI EXT 6.3L:
a. Prime Coat: Primer, latex for exterior wood, MPI #6.
b. Topcoat: Latex, exterior, semi-gloss (MPI Gloss Level 5), MPI #11.
c. This substrate applies to all buildings in project.
B. Wood Substrates: Traffic surfaces, including lumber decking and stairs.
1. Alkyd Floor Enamel System MPI EXT 6.5B:
a. Prime Coat: Floor enamel, alkyd, matching topcoat.
b. Topcoat: Floor enamel, alkyd, gloss (MPI Gloss Level 6), MPI #27.
c. This substrate applies to the following buildings:
d. 1. The Medical Director’s Residence
C. Portland Cement Plaster (Stucco) Substrates:
1. Latex System MPI EXT 9.1J:
a. Prime Coat: Primer, alkali resistant, water based, MPI #3.
b. Topcoat:…
This is the start of the file's text. The full file is on GovTribe.