Atch_1_SOW.pdf
PDF 159 KB Posted
- Attached to
- BADL Biowaste Vault Pumping Service Federal contract opportunity
- Solicitation number
- 140P6325Q0009
About this file
This document is a Statement of Work (SOW) for vault pumping services at Badlands National Park in Interior, South Dakota. The National Park Service requires septic pumping services for 13 vault toilets located throughout the park's north unit, with services to be performed every 3 weeks. The contract covers three ordering periods from April 1, 2025 to March 31, 2028, with each period running one year. The vaults are concrete structures with rear access hatches, approximately 1,000 gallons in capacity, located at various parking lots, trail locations, and campground areas. An NPS employee will follow the septic truck to provide water and chemical treatment after each vault is emptied, and the park will provide access to a lagoon system for wastewater disposal. Services will be conducted during hours of 7:00 AM to 4:30 PM, with an estimated 10 services per location during each ordering period. The contractor must develop and maintain a quality control program to ensure services meet commercial practices and standards.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6325Q0009_Amd_0002.pdf | ||
| Atch_7_Site_Visit_Sign-in_Sheet_0002.pdf | ||
| Sol_140P6325Q0009_Amd_0001.pdf | ||
| Sol_140P6325Q0009.pdf | ||
| Atch_6_DOL_WD_2015-5377.pdf | ||
| Atch_3_Experience_Questionaire.xls | XLS spreadsheet | |
| Atch_5_Questions_and_Answers.pdf | ||
| Atch_2_MAP_locations.pdf | ||
| Atch_4_Price_Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Vault Pumping Services Badlands National Park
Interior, SD 57750
1. Background: The National Park Service, Badlands National Park (BADL) has a requirement for septic pumping of vault toilets located within BADL.
2. Objective: Provide septic pumping service at BADL. This includes a total of 13 vaults, all at various locations throughout the parks north unit.
2.1 A NPS Employee will follow the septic truck with water and chemical treatment to facilitate the treatment after the vault has been emptied.
2.2 Park will provide access to lagoon system for wastewater disposal.
3. Place of Performance: Badlands National Park, 25216 Ben Reifel Road, Interior, South Dakota, 57750. Note that all locations are within Badlands National Park. Maps and additional information are available at http://www.nps.gov/badl
4. Period of performance: The contract includes three (3) ordering periods. The performance period shall begin on the date of award.
Ordering Period 1 - April 1, 2025 to March 31, 2026 Ordering Period 2 - April 1, 2026 to March 31, 2027 Ordering Period 3 - April 1, 2027 to March 31, 2028
5. Funding and specific dates will be identified on each order.
6. Scope: To remove septic wastewater every 3 weeks with some adjustment allowable for holidays, weather, and other environmental concerns. Contractor will be responsible for providing a tentative schedule upon award. The ordering period is estimated to have 10 services per location.
6.1. Definitions: Regular pumping event means a service provided for pumping sewage from a single tank and location identified in this document to occur on a scheduled Monday at the standard contract price.
6.2. Hours of Operations: 7:00 AM – 4:30 PM
6.3. Tank Specifications: all vaults and tanks are approximately 1,000 gallons capacity; waste removal will be measured in gallons for tracking and billing purposes.
6.4. Tank Locations:
Locations:
Number Type
Amphitheater Parking Lot 2 Concrete vaults with rear access hatch Door/Window Trail Parking Lot 2 Concrete vaults with rear access hatch Fossil Exhibit Trail Parking Lot 2 Concrete vaults with rear access hatch Bigfoot Overlook Trail Vault Toilet 1 Concrete vault with rear access hatch Conata Picnic Area Vault Toilet 2 Concrete vault with rear access hatch Pinnacles Overlook Vault Toilet 2 Concrete vaults with rear access hatch North Sage Creek Campground Vault Toilet
1 Concrete vault with rear access hatch http://www.nps.gov/badl
South Sage Creek Campground Vault Toilet
1 Concrete vault with rear access hatch
7. Quality Assurance Requirement: The contractor shall develop and maintain a quality control program to ensure services are performed in accordance with commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. As a minimum the contractor shall develop quality control procedures addressing the critical areas identified in this statement of work. The government will periodically evaluate the contractor’s performance in accordance with the statement of work.