Atch 1_SOW_Building C5 transformer replacement.docx
DOCX document 39 KB Posted
- Attached to
- Replace Transformer, Ames, IA Federal contract opportunity
- Solicitation number
- 12639525Q0141
About this file
This document is a Statement of Work (SOW) for replacing a transformer at the USDA National Centers for Animal Health in Ames, Iowa. The project involves removing an existing 300kVA, 13.8kV - 480Y/277V transformer installed in 2004 and installing a new transformer with similar specifications, including a multi-tap configuration for potential future north campus connection. Key requirements include verifying concrete spill containment basin adequacy, properly disposing of the old transformer, testing and disposing of transformer fluids, performing all electrical reconnections, updating arc flash assessment labels, and ensuring compliance with national electrical codes.
The solicitation (12639525Q0141) is set aside for small businesses, with a NAICS code of 238210 and a small business size standard of $19 million. The estimated project value ranges between $25,000 and $100,000. Contractors must adhere to strict site security protocols, including REAL ID compliance for entry, wearing identification badges, and coordinating work with the Contracting Officer's Representative. Work is to be performed during standard hours (7:00 AM to 3:30 PM, Monday through Friday), with advance approval required for work outside these times. The project involves minimal disruption to USDA facility operations, with careful coordination required to maintain site functionality.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12639525Q0141-0003.pdf | ||
| 12639525Q0141-0002.pdf | ||
| Foreign National Vetting Information Form.pdf | ||
| 12639525Q0141-0002.pdf | ||
| 12639525Q0141-0001.pdf | ||
| Atch 2_Building C5 transformer replacement drawing set_FINAL_2025.pdf | ||
| Atch 3_ Federal Construction Wage Rates_Story County.pdf | ||
| 12639525Q0141.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1, Solicitation 12639525Q0141 Statement of Work Building C5 transformer replacement USDA, Ames, IA 5/21/25
Background The existing 300kVA, 13.8kV - 480Y/277V, 3 phase transformer currently servicing building C5 was manufactured and installed in 2004 and has reached its end-of-life expectancy. There is a concern that if this transformer would experience a failure in one of its internal components, that parts would be difficult to find with very long lead times.
Scope The objective of this project is for the contractor to replace the transformer feeding building 403 located on the USDA campus in Ames, Iowa. This scope of work includes:
· Verification that the existing concrete spill containment basin is of sufficient size to accommodate all the liquid inside the new transformer and 6 inches of rain.
· Removing existing transformer and properly dispose of the transformer and its fluids.
· Testing the fluid in the existing transformer for PCBs and documenting the results and the disposal of the fluids and providing the USDA with a copy of the documentation.
· Cleaning and removing any existing fluid and debris from the area around the existing transformer location before the new transformer is installed.
· That the contractor be responsible for all wiring connections, this includes disconnection of old transformer and re-connection of new one and relocation and reconnecting any grounding wires and ground loop systems around existing transformers.
· Disposing of old transformer by contractor in accordance with Federal, State, and local codes.
· Ensuring that the footprint of the new transformer will fit properly and correctly on the existing spill containment basin.
· That new transformer shall be multi-tap for potential future connection to north campus 13.2kV.
· That the contractor shall be responsible for temporary spill containment on new transformer if it is stored on campus prior to installation on the existing concrete spill containment basin and keep a written inspection record until transformer has been installed on new containment pad. This written record will be provided to the COR after the transformer is placed on the new spill containment basin. Any oil leaks shall be the responsibility of the contractor to clean up and reported to the COR immediately.
· Updating the arc flash assessment label and affixing it to the outside of the transformer. See drawings for existing arc flash label.
· Repairing any cables that have been damaged or have existing damage.
Specification of the existing transformer: 300kVA, primary voltage of 13,800 Delta, secondary 480Y/277V. See drawings for specs of new transformer. New transformer shall have a dead front configuration.
General Requirements Work Restrictions & Conditions Electrical outages will be coordinated with the COR at least 2 weeks in advance to allow USDA staff to connect portable generators to equipment inside building C5 while work is being performed.
Anything mentioned in the Scope of Work and not shown on the drawings or shown on the drawings and not mentioned in the Scope of Work, shall be of like effect as if shown or mentioned in both.
The Contractor shall site verify any and all dimensions and shall carefully examine the entire site and building and shall make all necessary investigations to become thoroughly aware of the existing conditions and all difficulties involved in the completion of the work in accordance with the contract documents prior to the submission of bid.
The completed installation shall comply with all applicable provisions of the NEC, Manufacturers Requirements, and the SOW (Drawings and Specifications), enclosed and/or attached.
All work will be performed by qualified personnel, as applicable according to the manufacturer’s specifications.
Contractor shall verify all equipment is operational and ensure that your quality control inspections and corrections have been accomplished before calling for the final inspection!
Site Security Access Beginning May 7th, 2025, a REAL ID compliant driver’s license will be required for entry onto any federal facility. Anyone without a REAL ID compliant driver’s license will be denied entry into the NCAH facility. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/sub-contractor employees shall sign in and out at the main site entrance gate and wear a contractor/visitor identification badge at all times while on the site. The ID badges will be turned in at the end of the workday. A current government-issued identification with a picture ID is required for entry and advanced notification of project personnel is required in accordance with DR4660-004. Vehicle badges shall be displayed at all times while the contractor is on site.
Access to each individual site shall be arranged by the Contracting Officer's Representative (COR) according to the schedule submitted by the contractor and approved by the COR. The contractor shall coordinate and schedule his/her work under this contract to cause the least interference with the normal flow of visitor and employee traffic.
Construction vehicles will be allowed access adjacent to the work; contractor employee’s personal vehicles shall be parked in the facility parking lots.
The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative.
Work shall be confined to the areas identified on the Drawings. Unless accompanied by an NCAH/USDA employee, the Contractor, sub-contractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.
Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs.
Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/sub-contractor employees from the site and barring further site access to individuals.
Work Hours: Regular work hours for the site are 7:00AM to 3:30PM, Monday through Friday, excluding Government holidays. Requests for exceptions to this schedule shall be made in writing 5 days in advance and approved by the Contracting Officer's Representative.
Work Outside Regular Work Hours: Work scheduled outside regular work hours including late hours, Saturdays, Sundays, and Government holidays requires the Contracting Officer’s Representative’s (COR) approval in advance. Make application to the COR at least 5 calendar days prior to such work to allow arrangements to be made by the Government for access to the work area and inspection & monitoring arrangements. Requests shall include the exact dates, hours, location, and purpose of the exception. If approved, the COR will coordinate access with the site security office.
Construct Work in stages to accommodate Owner’s use of premises during construction period. Coordinate construction schedule and operations with Contracting Officer’s Representative (COR).
Contractor shall coordinate use of premises under direction of the COR. Contractor shall confine construction equipment, storage of materials and equipment and operations of workers to areas permitted by law, ordinances, permits, or requirements of Contract Documents, and shall not unreasonably encumber premises with construction equipment or other material or equipment.
Contractor shall:
· Assume full responsibility for protection and safekeeping of items under this Agreement, stored on site.
· Move any stored items, under Contractor’s control, which interfere with operations of Owner or separate contractor.
· Obtain and pay for use of additional storage or Work areas needed for operations.
· Ensure that any materials that are delivered by FedEx, UPS, etc. are delivered to the jobsite and NOT to the USDA warehouse dock at Building 24 or to the north warehouse, Building 11. The USDA and/or the COR will not be responsible for receiving any materials destined for the project. USDA reserves the right to refuse any unscheduled deliveries that arrive at either warehouse or at the main gate. Special considerations shall be made with the COR in advance of the delivery.
· Notify the COR of any scheduled deliveries. The COR will add the carrier or company to the visitor’s schedule. Contractor will meet the delivery and escort them to the jobsite.
Owner will occupy premises during the entire period of construction for its normal operations. Coordinate with Contracting Officer’s Representative (COR) in all construction operations to minimize conflict, and to facilitate Owner usage. Contractor shall at all times conduct its operations as to ensure the least inconvenience to the Owner.
Security Clearance Requirements Use of Premises Limit of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the work is approved.
Keep driveways, entrances, walkways, and doorways serving premises clear and available to the Government, employees, visitors, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
Limited parking may be available on the site away from each facility.
The contractor shall provide a list of all staff employees that will be working on the project to the Contracting Officer’s Representative (COR) a minimum of three days in advance. The contractors that will be onsite will be required to provide a valid driver’s license and be a valid United States Citizen to be able to access campus.
Once onsite, contractors will be escorted by a USDA employee to the location of the work and will be escorted at all times while onsite.
Adherence to Security Policies and Procedures The Contractor shall adhere to all Site, APHIS and USDA security policies and procedures including Code of Federal Regulations Requirements, Standard Operating Procedures, Security Directives, Security Procedures, General Orders, Post Orders and any applicable Government Policies and Procedures.
Failure to adhere to or violation of any above listed requirements, procedures, directives, orders and/or policies may result in criminal prosecution or contractor representative or contractor employee (violator) removal.
Intent of Contract Drawings Government provided drawings, henceforth referred to as “Contract Drawings”, do not attempt to show complete details of building construction that may affect installation. Government provided diagrams of proposed systems are for reference only and do not necessarily show physical arrangement of all equipment and/or maximum number of devices. Minimum system requirements are shown.
Devices are shown diagrammatically only. System layout does not necessarily show maximum number of system components and should not be used for obtaining quantities for linear runs of conduits and wires. The contractor shall provide all conduits and wire wherever needed to complete installation of specific equipment required and provided by the Contractor.
Locations of existing and Government concept devices are approximate and may be distorted for clarity in representation.
Regulatory Requirements The equipment materials, installation, workmanship, and operation shall conform to the most stringent applicable requirements of the most recent editions of the associated publications, in the below section and in the attached specifications unless otherwise noted:
National Fire Protection Association (NFPA) NFPA 101 – Safety to Life from Fire in Buildings and Structures.
NFPA 1 – Uniform Fire Code NFPA 5000 – Building Construction and Safety Code Underwriters Laboratories, Inc. (U.L.)
Appropriate U.L. Standards State and Local Building Codes as adopted by the Authority Having Jurisdiction (AHJ).
The Uniform Federal Accessibility Standards (UFAS) Occupational Safety and Health Administration (OSHA) Architectural Barriers Act (ABA) Equipment Manufacturer Printed Instructions NFPA 70 -- National Electric Code (NEC)
Coordination The contractor shall coordinate all work with the Contracting Officer's Representative. In general, Owner will need a minimum of two weeks’ notice to make connections to building 403 with portable generator during the transformer and new basin install.
The contractor shall submit an installation schedule for review and approval by the Contracting Officer's Representative within 10 days of task order award.
The contractor shall be solely responsible for coordinating work with all sub-contractors and ensuring that all items of joint use in conjunction with installations are completed.
Special Provisions The Contractor shall confine all operations to within the work limits of the project and exercise special care to maintain natural surroundings undamaged. All surfaces and groundwork that has been altered for the installation of the new transformer and containment basin shall be refinished to match original condition by skilled personnel of the trades involved at no additional expense to the Government. All groundwork shall be repaired to the same or better condition and reseeded.
Finished surfaces of existing facilities that are affected, marred, scratched, or damaged by the contractor shall be refinished to match original condition.
Patching material shall be of the same type, style, and thickness, and shall be finished to match existing adjacent surface construction in color and texture.
Patching material, paint color, paint material and paint application methods shall be approved in advance by the Contracting Officer’s Representative.
No building structural members shall be cut or altered without prior approval of the Contracting Officer's Representative.
Any damage resulting from the contractor’s operation shall be brought to the attention of the Contracting Officer's Representative immediately.
The contractor shall take all necessary and reasonable measures to keep the work site clean of trash and debris. Work areas shall be cleaned immediately as work in that area is completed and before moving to a new work site. Place all trash and debris in OSHA approved containers, remove, and dispose of trash off site daily.
The contractor shall move all materials and equipment, including ladders and scaffolding from the site at the completion of each day's operation unless otherwise approved by the Contracting Officer's Representative.
The contractor shall provide proper safety equipment to workmen and ensure a safe environment for employees and the general public at all times. The contractor shall work to ensure free, unobstructed, and safe access to and about the work area.
Temporary Facilities Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any utility connections.
Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service for the project.
Toilet Facilities: The Contractor will be permitted to use the toilet facilities located inside building 402.
Lock-out/Tag-out Program The Contractor and/or sub-contractor employees who will be working on the job will apply a lockout/tagout (LOTO) process to control dangerous energy sources. The Contractor/sub-contractor shall have a LOTO program established and use Contractor LOTO locks, tags, and procedures.
The Contractor/sub-contractor shall review their LOTO program with NCAH F.E.U. personnel to coordinate LOTO programs before implementing LOTO.
Submittal & Shop Drawings Procedures Submittal Register: At the beginning of the project, the Contractor shall provide a Submittal Register identifying all the items called out in the Specifications for submittal to the COR for approval. The Contractor shall update and maintain the Submittal Register to show the current status of all required submittals.
Submittal Requirements Format: There is no formal submittal transmittal or format for this project other than the documents that shall be submitted as PDF files, scanned, or created in documents that can be easily read when printed on 11x17 sheets. Exceptions for larger sheet sizes will be considered by the COR. Failure of the Contractor to provide legible submittals will be adequate grounds for rejection.
Identification: Submittals shall be labeled and marked for this project. The identification shall include Contractor/sub-contractor’s name, date of submittal, description of item, specification section, and details on product data that are marked clearly for this project.
Submittal Procedures: All submittals will be posted in PDF by the Contractor and sent to the USDA for review. This same submittal process will be used for RFIs, Change Bulletins, etc.
Approved Submittals: The approval/acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist.
Submittal items for this project
· New 300kVA, 13.8kv – 480Y/277V, 3 phase transformer.
· New transformer specifications.
Warranty Documentation Warranty List: Provide a warranty summary sheet in spreadsheet format with all the warranties listed by section, description, supplier, warranty contact, start date, end date. Provide an electronic copy to the COR and place printed copy in the front of the Warranty Binder.
Warranty Copies in Binder: Provide one signed & dated copy of all warranties for the air compressor system installed on the project. The Warranty binder shall be divided by Specification Section and shall be provided to the COR. An electronic (scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-out documentation.
Warranty Items New transformer Containment basin size verification
Operation & Maintenance Manuals: Contractor shall provide a printed copy of all Operation & Maintenance documentation provided with the new transformer installed in the project and place the manuals in an organized binder. The O&M Manuals shall be organized by specification section and shall have an index at the front of the binder. The Contractor shall also provide a PDF version of the Manuals to be submitted with the close-out documentation.
Record Drawings Redline Specifications: During the construction period the Contractor shall keep an updated & marked up or “redline” copy of the project specifications on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes. At the end of the project the Contractor shall electronically scan the redline specifications and provide an electronic copy in PDF to the Owner along with the close-out documentation.
Redline Drawings: During the construction period the Contractor shall keep an updated “redline” or “conformed” copy of the project drawings on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes. At the end of the project the Contractor shall electronically scan the redline drawings at full-size and in color and provide an electronic copy in PDF to the Owner along with the close-out documentation.
END OF SECTION