STATEMENT OF WORK FOR
BOAT HARBOR MAINTENANCE DREDGING PLAN
AND SEDIMENT SAMPLING AND ANALYSIS PLAN
AT VANDENBERG SFB, CA
Background: The United States Air Force proposes to develop a Boat Harbor Maintenance Dredging Plan and Sediment Sampling and Analysis Plan to support renewal of the existing dredge permit and to support boat harbor dredging at Vandenberg Space Force Base (VSFB). The existing dredge permit with the United States Army Corps of Engineers (USACE, Corps) expires in December 2022. The boat harbor has been dredged infrequently since 2001 to support the delivery of rocket components on vessels under the existing Regional General Permit (RGP) 71. RGP 71 authorizes dredging up to 10,000 cubic yards (cy) of sediment annually from an approximately 3.5 acre area in the Vandenberg Harbor to -10 feet mean lower low water (MLLW) plus a maximum two-foot overdepth allowance (for a total depth of -12 feet MLLW). The permit requires sediment sampling every three years based on the approved Sediment Sampling and Analysis Plan (SAP). This project would support continued dredge operations beyond December 2022 with development of a Boat Harbor Maintenance Dredging Plan and SAP.
Project Description: The Contractor will develop a Boat Harbor Maintenance Dredging Plan and Sediment Sampling and Analysis Plan for VSFB to support the dredge permit application process and continued boat harbor dredging operations beyond December 2022. All parameters for dredge area, depth, disposal, and methods will be the same as described in RGP 71. Close coordination with VFSB CEIEA personnel is anticipated. Draft and Final Plans will be submitted and if needed, assistance with comments on the final plans by regulatory reviewing agencies/entities will be provided.
Boat Harbor Maintenance Dredging Plan The dredging plan project description will be based on the existing RGP 71 project description and will include maps, regulatory support summaries and appendices as needed (e.g. abalone surveys, eelgrass surveys). RGP 71 is available at https://www.spl.usace.army.mil/Missions/Regulatory/Regional-General-Permits/ More information from the previous public notice to support the new plan is at Corps website.
Additional supporting information will be provided by VSFB.
Sediment Sampling and Analysis Plan The VSFB SAP will be based upon USACE guidance https://www.spl.usace.army.mil/Portals/17/docs/publicnotices/2021%20SAPR%20Guidlines%20Special%20Public%20Notice.pdf?ver=HMcg4YYtWYYuWGjCN4DTqw%3d%3d Additional supporting information will be provided by VSFB.
Project Period of Performance The period of performance for this project is 12 months.
Anticipated Review and Deliverables Schedule
| Date in 2022 |
| Description |
| VSFB CEIEA Review Period |
| 01 January or upon award |
| Start development of Boat Harbor Maintenance Dredging Plan and Sediment Sampling and Analysis Plan |
| 02 May |
| Contractor submits Draft Dredging Plan for review including all appendices |
| 3 weeks |
| 06 May |
| Contractor submits Draft Sampling and Analysis Plan for review including all appendices |
| 2 weeks |
| 27 May |
| Contractor will submit Final Dredging Plan and SAP |
| USACE Reviews June |
| June |
| Contractor shall assist to address any USACE comments on plans |
| SAP Review Process |
| Regulatory Agency Review |
| June |
| USACE schedules SAP review for July with Dredged Material Management Team (DMMT includes USACE, EPA, CA Coastal Commission, Regional Water Quality Control Board and CA Fish and Wildlife). |
| July |
| DMMT Reviews SAP and approves or provides comments. If any comments are received, Contractor shall assist to address. |
| Boat Harbor Maintenance Dredging Plan Review Process |
| Regulatory Agency Review |
| August |
| USACE issues a 30-day Public Notice for the dredging plan to be reviewed by the public in order to renew/issue dredge permit. |
| Mid-September |
| Any comments from the public review period will need to be addressed if needed by the Contractor. |
Qualifications
Familiarity with dredging plans for USACE permits and especially technical expertise with sediment sampling and analysis plans and/or testing is required. Technical knowledge on plan components are needed to provide expertise for the plans. Familiarity with coastal and marine biological resources is necessary. Familiarity with ArcGIS is required to develop and represent the dredge footprint. Provide projects, qualifications, and resumes with expertise in relevant subject areas. At least 5 years of experience is required.