Atch 1 - SOW - Bldg 296 and 877 Carpet.pdf
PDF 122 KB Posted
- Solicitation number
- FA480125Q0033
About this file
This Statement of Work (SOW) details a carpet replacement project for Buildings 296 and 877, with a 120-day performance period starting August 14, 2025. The project requires removing existing glue-down carpet and vinyl wall base, cleaning and preparing floors (concrete in Bldg 296, plywood in Bldg 877), and installing new roll carpet with cushion backing. Specific requirements include taking furniture photos in Bldg 296 for proper replacement, a phased work approach starting with Bldg 877's three rooms, and installing 4" vinyl wall base and transition strips.
Key contract specifications mandate using broadloom carpet (not carpet tiles) glued to the floor, obtaining CE Project Inspector approval for carpet and wall base submittals, and ordering materials exclusively from vendors in the attached Carpet Ordering Guide. The contractor must move furniture in Bldg 296, park storage trailers on-site, install barricades, perform complete clean-up after each phase, and repair any damage. A two-day delay is required between completing Bldg 877 and starting work on Bldg 296, with careful attention to room occupancy and furniture relocation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IMG_0051.jpg | JPG image | |
| IMG_0047.jpg | JPG image | |
| Carpet Ordering Guide.pdf | ||
| Atch 2 - Questions and Answers Sheet - completed.pdf | ||
| IMG_0049.jpg | JPG image | |
| Bldg 877 Floor Plan 1.pdf | ||
| Solicitation - FA480125Q0033.pdf | ||
| Bldg 296 Floor Plan 1.pdf | ||
| Atch 2 - Questions and Answers Sheet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REPLACE FLOOR CARPET, BLDGS 296 & 877
Aug 14, 2025
1. The Contractor shall replace some floor carpet at Bldgs 296 and 877.
2. The Period of Performance will be 120 days.
3. The Contractor will be responsible for moving the furniture in Bldg 296. All personal items will be removed by others prior to the start of work. Take pictures of each room so the furniture can be installed back in the same place. Pictures of the furniture in each room are attached.
4. No furniture moving will be required in Bldg 877.
5. The Bldg 296 furniture can be stored in trailers that can be parked near the work area. The furniture can also be moved around inside the work area as required.
6. See the attached floor plan drawings. There is one drawing for each building.
7. Bldg 296: The work areas are highlighted in yellow. All of the room measurements are shown on the floor plan.
8. Bldg 877: There are three (3) rooms on a second floor mezzanine that will receive new carpet. The outside dimension of the work area is approximately 80' x 23'. The area of each room is circled in red.
9. Work Phasing Plan: Bldg 877 will be completed first. There are three rooms in this building – 126, 127, and 128. Only Room 128 is occupied. Complete Room 127 first. The occupants in Room 128 will then move into Room 127. Room 126 will be next. Room 128 will be last. After Bldg 877 is complete, there will be a two (2) day delay before work can begin in Bldg 296.
10. Remove and dispose the existing glue-down carpet and vinyl wall base in the work areas.
11. Clean and prepare the floors and walls as required after demolition operations are complete. The floor at Bldg 296 is concrete. The floor at Bldg 877 is plywood.
12. Install new roll (broadloom) carpet in the rooms. Do not use carpet tile. The carpet shall have a cushion backing. The carpet shall be glued to the floor.
13. Install new 4" high vinyl wall base around the entire perimeter of the rooms. If there is any damage to the wall surface during demolition operations, the wall shall be repaired. Another option would be to install 5" wall base to cover up any damage.
14. Install vinyl transition strips beneath all the doors.
15. All installation work shall be in accordance with the manufacturer’s instructions.
16. Install barricades around the work area as required.
17. The Contractor will be allowed to park storage trailers and equipment on site.
18. Perform a complete clean-up of the work area after each phase is complete.
19. Repair any damage that may occur during the course of the work.
20. Provide carpet and wall base submittals for approval before ordering materials. Do not order any materials until approval has been received from the CE Project Inspector.
21. See the attached Carpet Ordering Guide. The carpet must be ordered from one of the vendors listed in the guide. A website link is attached below.
https://usaf.dps.mil/sites/aficc/afcc/aficc/affcc/sitecollectiondocuments/carpet/carpethomepage.aspx
------END------