Asphalt Adjustment Spreadsheet 2020.xlsx

XLSX spreadsheet 25 KB Posted

Attached to
Liquid Asphalt 2020
Solicitation number
RFB 605 2000000413 2
Issued by
Kentucky

About this file

This is an Asphalt Adjustment Spreadsheet for Liquid Asphalt Master Agreements under the Kentucky Transportation Cabinet, effective March 1, 2020. The document serves as a calculation tool for tracking liquid asphalt deliveries and associated price adjustments across a twelve-month period from January through December. The spreadsheet is designed to record delivery order numbers, the month each order was placed, the quantity of gallons (G) of material picked up or delivered, and whether the adjustment threshold was met. The document provides a standardized format for monthly tracking with consistent adjustment percentages of 0.6 applied throughout the year.

The pricing mechanism utilizes the KAPI (Kentucky Asphalt Pavement Association Price Index) to calculate monthly adjustments based on the formula: Asphalt Adjustment Quantity = (G x 0.6)/240 x (PC - PL), where PL represents the KAPI for the month the contract was let and PC represents the KAPI for the month of adjustment. The spreadsheet includes a reference to the Kentucky Transportation Cabinet's Fuel and Asphalt Adjustments webpage for obtaining current KAPI values. The total asphalt adjustment quantity shown is $0.0000, indicating this is a blank template ready for data entry. This adjustment mechanism allows for automatic price modifications based on market fluctuations in asphalt pricing, protecting both the state and contractors from significant price volatility during the contract term.

View the file

Other files

File Type Posted
Final_RFB_605_2000000413_1_SO_FORM.PDF PDF
Liquid Asphalt Bid Sheet 2020 - Delivered.xls XLS spreadsheet
Final_RFB_605_2000000413_2_SO_FORM.PDF PDF
Liquid Asphalt Bid Sheet 2020 - Picked Up.xls XLS spreadsheet
FHWA - 1273.pdf PDF
Buy America Clause.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Liquid Asphalt

For Liquid Asphalt Master Agreements effective March 1, 2020Delivery Order Number
Type Delivery Order Here
Month PlacedItemGallons (G)APL
(Feb 2020)PC (KAPI)Threshold Met
(1=Yes, 0=No)AdjustmentpercentDate
0.6January
0.6February
0.6March
0.6April
0.6May
0.6June
0.6July
0.6August
0.6September
0.6October
0.6November
0.6December
Total Asphalt Adjustment Quantity$0.0000

To get the PC (KAPI), click HERE

Asphalt Adjustment Quantity = (G x 0.6)/240 x (PC - PL)

Where:

G = Gallons of material picked up or delivered
PL = KAPI for the month that the contract is let
PC = KAPI for the month of adjustment

https://transportation.ky.gov/Construction/Pages/Fuel-and-Asphalt-Adjustments.aspx