This is an asphalt price adjustment worksheet for master agreements with the Kentucky Transportation Cabinet, effective March 1, 2026, related to Bridge Maintenance & Repair services for FHWA-eligible districts 1-12. The document provides a template for calculating monthly asphalt adjustments across a 12-month period (January through December) based on tonnage of material used and fluctuations in asphalt prices. The worksheet accommodates delivery order numbers, item quantities measured in tons, asphalt content percentages, and threshold determinations to establish whether price adjustments are warranted.

The adjustment calculation follows a specific formula: Asphalt Adjustment Quantity = (Q x 5.6)/100 x (PC - PL), where Q represents tons of material used, PL represents the KAPI (Kentucky Asphalt Price Index) for the month the contract was bid, and PC represents the KAPI for the month of pickup or delivery. The worksheet uses a baseline asphalt content factor of 5.6 and requires monthly KAPI values to be obtained from the Kentucky Transportation Cabinet's fuel and asphalt adjustments portal. The total asphalt adjustment amount is calculated at $0.00 in the template, with adjustments applied only when threshold requirements are met, enabling contractors to receive compensation for asphalt price fluctuations during contract performance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

In Place

For Master Agreements effective March 1, 2026Delivery Order Number
Type Delivery Order Here
Month PlacedItemTons (Q)Asphalt ContentPL
(Feb 2026)PC (KAPI)Threshold Met
(1=Yes, 0=No)AdjustmentpercentDate
5.6January
5.6February
5.6March
5.6April
5.6May
5.6June
5.6July
5.6August
5.6September
5.6October
5.6November
5.6December
Total Asphalt Adjustment Quantity$0.00

To get the PC (KAPI), click HERE

Contract Formula for Calculating Asphalt Adjustment:

Asphalt Adjustment Quantity = (Q x 5.6)/100 x (PC - PL)

Where:
Q = Tons of material or mixture used
PL = KAPI for the month that the contract is bid
PC = KAPI for the month of pick up or delivery