Asphalt Adjustment 2021 - Liquid Asphalt.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
Liquid Asphalt 2021
Solicitation number
RFB 605 2100000333 2
Issued by
Kentucky

About this file

This is a liquid asphalt pricing adjustment spreadsheet for Kentucky state contracts, specifically documenting asphalt adjustment mechanisms for Master Agreements effective March 1, 2021. The document outlines a monthly tracking system for liquid asphalt deliveries, with adjustment calculations applied across a twelve-month period from January through December. The spreadsheet is designed to accommodate delivery order numbers, monthly placement records, and gallons of material picked up or delivered, with a standard adjustment factor of 0.6 applied uniformly across all months.

Pricing adjustments are calculated using the formula: Asphalt Adjustment Quantity = (G × 0.6)/240 × (PC - PL), where G represents gallons of material, PL represents the KAPI (Kentucky Asphalt Price Index) for the month the contract was let, and PC represents the KAPI for the month of adjustment. The adjustment mechanism includes a threshold requirement that must be met before adjustments are triggered. Contractors can access current PC (KAPI) values through the Kentucky Transportation Cabinet's Fuel and Asphalt Adjustments webpage. The spreadsheet provides a total asphalt adjustment quantity field showing $0.0000, indicating that no adjustment was warranted during this period. This pricing structure allows for monthly fluctuations in asphalt costs to be reflected in contract payments while maintaining price stability through indexed adjustment mechanisms.

View the file

Other files

File Type Posted
Liquid Asphalt Bid Sheet 2021 - Picked Up.xls XLS spreadsheet
FHWA - 1273.pdf PDF
Liquid Asphalt Bid Sheet 2021 - Delivered.xls XLS spreadsheet
Buy America Clause.pdf PDF
Final_RFB_605_2100000333_2_SO_FORM.PDF PDF
Final_RFB_605_2100000333_1_SO_FORM.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Liquid Asphalt

For Liquid Asphalt Master Agreements effective March 1, 2021Delivery Order Number
Type Delivery Order Here
Month PlacedItemGallons (G)APL
(Feb 2021)PC (KAPI)Threshold Met
(1=Yes, 0=No)AdjustmentpercentDate
0.6January
0.6February
0.6March
0.6April
0.6May
0.6June
0.6July
0.6August
0.6September
0.6October
0.6November
0.6December
Total Asphalt Adjustment Quantity$0.0000

To get the PC (KAPI), click HERE

Asphalt Adjustment Quantity = (G x 0.6)/240 x (PC - PL)

Where:

G = Gallons of material picked up or delivered
PL = KAPI for the month that the contract is let
PC = KAPI for the month of adjustment

https://transportation.ky.gov/Construction/Pages/Fuel-and-Asphalt-Adjustments.aspx

File details come from the government source that posted it. Updated .