Asbestos Abatement Project Plan_Bldg-2_20151228.pdf

PDF 1 MB Posted

Attached to
Replace Repair Roof TPO Building 2
Solicitation number
W911SG25BA018
Issued by

About this file

This document is an Asbestos Abatement Project Design for Building 2 at Fort Bliss, Texas, dated December 28, 2015. The project involves removing asbestos-containing materials from the roof, specifically cement fiber corrugated boards (transite wall panels) covering 4,729 square feet and roof penetration black mastic covering 800 square feet. The abatement will be conducted by Border Demolition & Environmental under the supervision of El Paso Environmental Consultants (EPEC), with Rosalba Flores serving as the Asbestos Individual Consultant.

The project design provides comprehensive guidelines for safe asbestos removal, including worker protection protocols, wet removal techniques, disposal procedures, and air monitoring requirements. Key specifications include using wet methods to minimize fiber dispersion, establishing decontamination areas, requiring specific personal protective equipment, implementing strict cleaning and disposal protocols, and conducting air sampling to ensure fiber levels remain below 0.01 fibers per cubic centimeter. The document outlines detailed procedures for each stage of the abatement process, from pre-cleaning to final clearance, with multiple inspection points to ensure compliance with federal and state regulations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ASBESTOS ABATEMENT PROJECT DESIGN

for:

Building 02 (Roof), Fort Bliss, TX

December, 28, 2015

Prepared for:

JAYCO General Contractors 1615 Bernard Kern Dr.

EL PASO, TX 79936

Prepared by:

PH: 915-301-2974 epenviroconsultants@outlook.com

ROSALBA FLORES

Asbestos Individual Consultant

TDSHS License Number 10-5779

Expires 07/16/2016

Building 2 - Roofing.

Fort Bliss. TX.

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

2 ASBESTOS ABATEMENT PROJECT DESIGN

SECTIONS TABLE OF CONTENTS PAGE

1.0

1.1 1.2 1.3 1.4 1.5

Summary of the Work Extent of Work

Location and Approximate Quantities Asbestos Health Risks

Stop Asbestos Removal Codes and Regulations

2.0

2.1 2.2

Abatement Contractor Responsibility Contractor’s Submittals

Contractors Responsibility

3.0

3.1 3.2 3.3 3.4 3.5 3.6 3.7

Worker Protection Training prior to engaging in abatement work

Respiratory Protection Medical Examinations

Protective Clothing Entering and Exiting Procedures

Decontamination Procedures Limitations within work area

4.0

4.1 4.2

Pre-Cleaning and Decontamination Removal of Asbestos-Containing Debris

Wet Cleaning

5.0

5.1 5.2 5.3 5.4

Removal of Asbestos-Containing Material Cement Fiber Corrugated Board (transite wall panels)

11-12

6.0

6.1 6.2

Disposal of Regulated Asbestos-Containing Material

7.0

7.1 7.2 7.3 7.4 7.5 7.7 7.8 7.9 7.10 7.11 7.12

Air Monitoring and Final Clearance Air Monitoring

Baseline Fiber Counts Work Area Isolation

Work Area Airborne Fiber Counts Final Air Clearance

Airborne Fiber Counts Fiber Type Dispute Laboratory Testing

Sample Protocols Schedule of Air Samples with PCM

Interior Clearance Samples Personal Air Monitoring

8.0

Clean- Up Procedures Work Area Clean-Up Method of Clean-up

Clean-up of polyethylene sheeting Post-Clearance Clean-up

9.0

Inspections

10.0 Appendix : A: Project Drawings and Sketches

B:License and Certifications

21-24 25-26

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

3 ASBESTOS ABATEMENT PROJECT DESIGN

1.0 SUMMARY OF WORK

Project: Building 2 - Roofing Location: Fort Bliss, TX.

Client: JAYCO General Contractors Consultant: Rosalba Flores TDSHS # 10-5779 Contractor: Border Demolition & Environmental.

Asbestos Abatement designed for this project will be required as follows:

1.1 Extent of Work.

The project consists of removal and disposal of asbestos-containing materials (ACM) utilizing wet methods within full. These operations shall comply with OSHA Class I and II asbestos work requirements and EPA AHERA requirements. The following asbestos-containing materials (ACM) will be removed:

1.2 Location and approximate Quantities.

The Abatement Contractor shall be responsible for verifying existing site conditions and determining the quantity of ACM delineated for removal prior to abatement described in these specifications and associated drawings. The locations and types of ACMs known to be present at the worksite are set for the Building 2 – Roof – Ft. Bliss, TX. (See attached drawing Figure 1). If any other asbestos-containing material(s) is/are found, the abatement contractor shall notify the owner, the consultant, employers, about the location and quantity of the assumed ACMs within 24 of the discovery.

1.3 Asbestos Health Risk.

The disturbance or dislocation of ACM may cause asbestos fibers to be released into the building’s atmosphere, thereby creating a potential health risk to workers and building occupants. Apprise all workers, supervisory personnel, subcontractors, and consultants who shall be at the jobsite of the seriousness of the risk and of proper work procedures which must be followed. The Abatement Contractor will be responsible for the removal and disposal of the asbestos-containing materials and asbestos-contaminated materials in accordance with Texas Department of State Health Services (TDSHS), OSHA 29 CFR 1926.1101, Asbestos Hazard Emergency Response Act (AHERA) 40 CFR Part 763, and the National Emission Standards for Hazardous Air Pollutants (NESHAP) Regulations 40 CFR Part 61.

1.4 Stop Asbestos Removal.

If the Consultant presents a written Stop Asbestos Removal Order, immediately stop all asbestos removal and initiate fiber reduction activities. Do not resume asbestos removal until authorized in writing by the Consultant. A Stop Asbestos Removal Order will be issued at any time the Consultant determines abatement conditions are not

Material Location ~ Square Feet of Material

Cement Fiber Corrugated Board (transite wall panels)

Exterior wall panels of the Penthouse Rooms (Roof)

4,729 square feet

Roof penetration black mastic

Vents/seams of the roof AHU 800 square feet

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

4 ASBESTOS ABATEMENT PROJECT DESIGN

within specifications requirements. Stoppage will continue until conditions have been corrected. Standby time and cost required for corrective action is at Abatement Contractor’s expense. The occurrence of the following events will be reported in writing by the Consultant and will require the Abatement Contractor to automatically stop asbestos removal and initiate fiber reduction activities:

A. Excessive airborne fiber outside containment area (0.01f/cc or greater).

B. Break in containment barriers.

C. Loss of negative air pressure (at or above 0.01 inches of water).

D. Serious injury within the containment area.

E. Fire and safety emergency.

F. Respiratory system failure.

G. Power failure.

H. Excessive airborne fibers inside containment area (0.1 f/cc or greater when wet methods are employed).

1.5 Codes and Regulations.

General Applicability of Codes, Regulations and Standards: Except to the extent that more explicit or more stringent requirements are written directly into the contract documents, all applicable codes, regulations, and standards have the same force and effect (and are made a part of the contract documents by reference) as if copied directly into the contract documents, or as if published copies are bound herewith.

Federal Regulations: Those which govern asbestos abatement work or hauling and disposal of asbestos waste materials including but not limited to the following:

U.S. Department of Labor, Occupational Safety and Health Administration, (OSHA), including but not limited to:

General Industry Title 29, Part 1910, Section 1001 of the Code of Federal Regulations

Respiratory Protection Title 29, Part 1910, Section 134 of the Code of Federal Regulations

Construction Industry Title 29, Part 1926.1101, and 1926.62 of the Code of Federal Regulations

Access to Employee Exposure & Medical Records Title 29, Part 1910, Section 20 of the Code of Federal Regulations

Hazard Communication Title 29, Part 1910, Section 1200 of the Code of Federal Regulations

Specifications for Accident Prevention Signs and Tags Title 29, Part 1910, Section 145 of the Code of Federal Regulations

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

5 ASBESTOS ABATEMENT PROJECT DESIGN

U.S. Environmental Protection Agency (EPA) including but not limited to:

Worker Protection Rule 40 CFR Part 763, Subpart G

CPTS 62044, FKR 2843-9

Federal Register, Vol. 50, No. 134, 7/12/85 P28530-28540

Regulation for Asbestos Title 40, Part 61, Subpart A of the Code of Federal Regulations

National Emission Standard for Asbestos Title 40, Part 61, Subpart M of the Code of Federal Regulations including Asbestos NESHAP Revision; Final Rule, Federal Register;

Tuesday, November 20, 1990

Asbestos Hazard Emergency Response Act (AHERA) Regulations 40 CFR 763 Subpart E

U.S. Department of Transportation (DOT) including but not limited to:

Hazardous Substances: Final Rule Regulation 49 CFR, Parts 171 and 172

State and Local Regulations: Abide by all state and local regulations which govern asbestos abatement work or hauling and disposal of waste materials, including but not limited to the Texas Department of State Health Services Prior to initiating work, proper written notification shall be submitted to the TDSHS per the requirements.

END OF SECTION 1.0

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

6 ASBESTOS ABATEMENT PROJECT DESIGN

2.0 ABATEMENT CONTRACTOR RESPOSIBLITIES

2.1 Abatement Contractor Submittals.

Prior to initiation of abatement activities, Abatement Contractor shall provide the following to CONSULTANT:

Texas Department of State Health Services (TDSHS) 10 Day Notification

Plan of Action

Contingency Plan Fire Action Plan

Emergency Telephone Listing Permits, License, Certificates

Texas License for Project Supervisor, Workers and Transporter

List of Workers

Medical Exam Results Texas Worker Training Certificates

Project Work Schedule NESHAP Training Certificate

Respiratory Fit Test Certification Written Respirator Program pursuant to 29 CFR 1910.134(b)

Abatement Specifications Project Closeout:

Waste disposal Manifest Copies Contractor’s Daily Log

2.2 Abatement Contractor Responsibility.

2.2.1 Abatement Contractor shall get familiarized with the conditions of the project and is responsible for estimating the quantities and verifying the locations of all work to be performed as outlined in this specification. Failure to do so shall not relieve the Contractor of his obligation to furnish all materials and labor necessary to carry out the provisions of the Contract. The locations and quantities of ACBM must be field verified by the Abatement Contractor prior to bidding. Any discrepancy between specified location and quantity of ACM and CONTRACTOR field estimates must be verified in writing before the CONTRACTOR may submit a change order. No change order will be approved unless additional work is approved by OWNER in writing prior to initiation of work.

2.2.2 Abatement Contractor will assume full responsibility and liability for the compliance with all the applicable federal, state, and local regulations pertaining to work practices, hauling and disposal of ACM, and protection of workers, visitors to the site, and persons occupying areas adjacent to the site.

2.2.3 Abatement Contractor will hold the Owner and Consultants harmless for failure to comply with any applicable work, hauling, disposal, safety, health or other on the part of himself, his employees, or his subcontractors.

2.2.4 Abatement Contractor incurs all costs to comply with OSHA regulations.

2.2.5 Abatement Contractor shall provide all labor, materials, equipment and supplies to conduct asbestos abatement of identified asbestos-containing material (ACM) prior to renovation or demolition activities.

2.2.6 Abatement Contractor shall supply electrical power continuously until all work areas have passed clearance inspection and testing for the project. Contractor shall supply PSI with sufficient electrical outlets for air monitoring pumps. Electrical power has been disconnected from the property.

2.2.7 Abatement Contractor shall conduct all work in accordance with this specifications, owner requirements and applicable Federal, State and Local Regulations. Where these specifications and the applicable regulations may conflict, the more stringent will apply.

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

7 ASBESTOS ABATEMENT PROJECT DESIGN

2.2.8 Abatement Contractor is responsible for using Texas Department of State Health Services (TDSHS) licensed workers to conduct any activity that physically disturbs identified or assumed ACBM.

2.2.9 Abatement Contractor may remove non-ACBM (i.e. wood, carpet, glass, etc) as pre-abatement activity if completed prior to the start of abatement, and ensure that ACBM will not be disturbed during this process.

2.2.10 Abatement Contractor shall monitor for and respond to water leaks, fires and other incidents that may occur while contractor is in the work area.

2.2.11 Abatement Contractor shall limit on-site work to the hours of 7:00am to 4:00pm.

2.2.12 Abatement Contractor shall place asbestos waste dumpster in area(s) designated by OWNER.

2.2.13 Abatement Contractor shall remove all waste from the project site after the final air clearance and visual clearance by CONSULTANT. Waste remaining at the jobsite shall be secured when the jobsite is not supervised by contractor personnel, e.i. outside working hours.

2.2.14 Abatement Contractor is to submit close out documents within 15 days of completion, to include, but not limited to, waste manifest(s), personal testing (PEL/STEL), licenses and project logs.

2.2.15 Abatement Contractor shall coordinate all work times with the Owner’s Asbestos Individual Consultant (AIC) or Project Manager and is directed to submit, adjust and amend the TDSHS Notification for the Owner based on his accessibility.

2.2.16 It Is Abatement Contractor responsibility for errors and omissions is not relieved by CONSULTANT review.

2.2.17 It Is Abatement Contractor responsibility for deviation from requirements of contract documents is not relieved by CONSULTANT review, unless CONSULTANT is notified of deviations in writing at time of submittal, and provides written review of specific deviations.

END OF SECTION 2.0

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

8 ASBESTOS ABATEMENT PROJECT DESIGN

3.0 WORKER PROTECTION

3.1 Training prior to engaging in abatement work.

Train workers in accordance with OSHA 29 CFR 1926.1101 and Texas Asbestos Health Protection Rules. Workers will be trained and be knowledgeable on the following topics: Methods of recognizing ACM; health effects of asbestos exposure; effects of smoking and asbestos exposure; activities that could result in hazardous exposures; protective controls; practices and procedures to minimize exposure including engineering controls, work practices, respirators, housekeeping procedures, hygiene facilities, protective clothing, decontamination procedures, emergency procedures and waste transportation and disposal; review OSHA 29 CFR 1910.134 for respirators; medical surveillance program; review OSHA 29 CFR 1926.1101, and for air monitoring, personnel and area; review this section of the project specifications.

3.2 Respiratory Protection.

CONTRACTOR shall instruct and train each worker involved in asbestos abatement or maintenance and repair of friable ACM in proper respiratory use and require that each worker always wear a respirator, properly fitted on the face in the Work Area from the start of any operation which may cause airborne asbestos fibers particles until the work area is completely decontaminated. CONTRACTOR shall use respiratory protection appropriate for the fiber concentration encountered in the work place or as required for other toxic or oxygen-deficient situations encountered.

The minimum respiratory protection for removal of ACM within the structure shall be half-face air purifying respirators (APR) for flooring materials. No reduction of the minimum specified respiratory protection will be considered by the CONSULTANT. Certification that the workers have been fit tested in accordance with current

OSHA guidelines will be provided as part of the Workers Documentation. CONTRACTOR shall provide at minimum, HEPA type filters labeled as P100, with NIOSH and MSHA Certification for “Radionuclide, Radon Daughters, Mist, Dust, Fumes, including Asbestos-Containing Dusts and Mists” and color coded in accordance with ANSI Z228.2

(1980). In addition, a chemical cartridge section may be added, if required, for solvents, etc., during abatement activities. In this case, provided cartridge that have each section of the combination canister labeled with appropriate color code and NIOSH/MSHA Certification. The CONTRACTOR is ultimately responsible for appropriate respiratory protection for the type of abatement being performed and understands that these requirements are only minimum acceptable work standards.

3.3 Medical Examination.

Provide medical examinations for all workers and other employee entering the work area per OSHA 29 CFR 1926.1101 regardless of exposure levels.

3.4 Protective Clothing.

During abatement activities, CONTRACTOR shall provide workers with full-body coveralls, footwear, disposable head covers, hard hats, full eye protection, and gloves and require they be worn in the work area.

CONTRACTOR remains solely responsible for the OSHA compliance of all his employees.

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

9 ASBESTOS ABATEMENT PROJECT DESIGN

CONTRACTOR shall require abatement workers to decontaminate through a tree-chambered, wet decontamination unit which is constructed as part of the containment.

3.5 Entering and Exiting Procedures.

Provide worker protection per most stringent applicable requirements. Provide as a minimum the following:

Ensure that each time workers enter the work area, they remove all street clothes in the changing room of the personnel decontamination unit and put on new disposable coveralls, new head covers, and clean respirators, then proceed through shower room to equipment room, and put on work boots.

3.6 Decontamination Procedures.

Require all workers to adhere to the following personal decontamination procedure as a minimum requirement whenever leaving the work area:

1. When exiting the area, remove disposable coveralls, disposable head covers, and boots in the Equipment Area of the decontamination unit.

2. Still wearing respirators, proceed to thoroughly HEPA vacuum, then wet wipe body including hair and face in order to remove gross contamination. Care must be taken to follow reasonable procedures in removing the respirator to avoid asbestos fibers while decontaminating. Carefully wash face piece of respirator inside and out.

3. When using PAPR: Shut down in the following sequence:

- First cap inlets to filter cartridges, turn off blower unit (this sequence will help keep debris which has collected on the inlet side of filter from dislodging and contaminating inside of unit). Thoroughly wash blower unit and hoses.

Carefully wash battery pack with wet rag. Be extremely cautious of getting water into the battery pack as this will short out and destroy the battery.

4. Proceed to Clean Area and change into street clothes or into new disposable Work Items.

3.7 Limitations within work area.

Ensure that workers do not eat, drink, smoke chew gum or use tobacco, or in any way break the protection of the respiratory protection system in the Work Area.

END OF SECTION 3.0

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

10 ASBESTOS ABATEMENT PROJECT DESIGN

4.0 PRE-CLEANING AND DECONTAMINATION

4.1 Removal of Asbestos-Containing Debris.

This section addresses The Abatement Contractor cleanup of small quantities of collective debris that may dislodge from building finish, fireproofing, TSI on pipes or insulation or other equipment.

Pre-cleaning shall consist of collecting loose fragments prior to installation of the critical and wall barriers. Wet wiping and HEPA vacuuming shall not be required unless friable, dislodged conditions are encountered.

The Abatement Contractor shall remove ACM debris and decontaminate the area involved utilizing the following sequence:

1. Seal entry to Work Area with barrier tape labeled with “DANGER ASBESTOS”.

2. HEPA vacuum floor surface as personnel enter the work area.

3. Remove small debris, if present, with HEPA vacuum.

4. Collect big pieces and place in bottom of a 6-mil polyethylene disposal bag following the disposal requirements of these specifications.

5. Place pieces in the bag without dropping and avoiding unnecessary disturbance and release of material.

6. Remove remaining visible debris with a HEPA vacuum.

7. HEPA vacuum an area 3-feet beyond the location in which any visible debris was identified.

8. Place a 6-mil polyethylene drop cloth immediately atop of the HEPA vacuumed cleaned area before performing any work onsite.

4.2 Wet Cleaning.

Abatement Contractor shall accomplish wet cleaning with disposal rags or paper towels during decontamination of areas where residual ACM fragments are identified on hard surfaces by immersion of disposable rags in water with surfactant or diluted removal encapsulant, wipe surface once and refold to a fresh cloth face and proceed in this manner until faces of disposal rags or paper towels have been used, and dispose of rags. DO NOT place rags back in bucket to rinse out or for any other purpose.

END OF SECTION 4.0

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

11 ASBESTOS ABATEMENT PROJECT DESIGN

5.0 REMOVAL OF ASBESTOS-CONTAINING MATERIAL

The Abatement Contractor will conduct removal and disposal activities in accordance with current Federal, State, and Local Regulations. Prior to initiation of removal activities, CONTRACTOR shall provide workers with the required proactive equipment and require that appropriate equipment be used at all times.

A Competent Person shall supervise all asbestos work.

The Abatement Contractor shall not generate visible dust emissions during abatement activities. All abatement work will be stopped if visible emissions are observed.

5.1 Removal of Cement Fiber Corrugated Boards (Transite Panels).

Establish a decontamination area that is adjacent to the regulated area for decontamination of employees and their equipment. At a minimum the decontamination shall consist of an area covered by an impermeable drop cloth on the floor or horizontal working surface of sufficient size to accommodate cleaning of equipment and removing personal protective equipment without spreading contamination. Work clothes must be cleaned with a HEPA vacuum before they are removed. All equipment and surfaces of containers filled with ACM must be cleaned prior to removing them from the equipment room or area. Install one layer of six mil polyethylene sheeting on the inside face of the cementitious asbestos (transite) panel using tape and/or glue. Cover the wall, sill, or other structure beneath the panel with one layer of four mil polyethylene sheeting. Cover the ground beneath the panel outward from the wall to a distance of one foot for each foot of material height.

Remove the metal framing, screws, caulking, or other means of attachment from the panel to allow removal of the panel whole. Use wet methods if this process disturbs the material.

Wrap asbestos containing materials with two layers of six mil polyethylene sheeting, or double bag prior to disposal.

Provide a temporary seal for the opening created in the structure by installing plywood or other weather tight material if required by the Base Building Package and/or the General Contractor.

5.2 Wet Removal.

The abatement Contractor shall use amended water or other abatement industry agents to facilitate ACM removal while minimizing the generation of airborne asbestos fibers.

The Abatement Contractor shall thoroughly wet material to the satisfaction of the CONSULTANT prior to stripping and/or tooling to reduce fiber dispersal into the air. Accomplish wetting by a fine spray (mist) of amended water or removal encapsulant applied with airless spray equipment. Saturate material sufficiently to wet to the substrate without causing excessive dripping. Allow water or removal encapsulant to penetrate material thoroughly. Spray material repeatedly during the removal process to maintain a continuously wet condition.

If removal encapsulant is utilized, The Abatement Contractor shall apply only when environmental conditions in the

Work Area are as required by the manufacture’s specifications, and comply with applications procedures in strict accordance with manufacture’s written instructions.

The abatement Contractor shall mist Work Area continuously with amended water whenever necessary to reduce airborne fiber levels. Apply mist with airless spray equipment.

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

12 ASBESTOS ABATEMENT PROJECT DESIGN

The Abatement Contractor shall not use compressed air on the non-airless type equipment to wet ACM.

The Abatement Contractor shall remove saturated ACM in small sections from areas. Do not allow material to dry out.

END OF SECTION 5.0

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

13 ASBESTOS ABATEMENT PROJECT DESIGN

6.0 DISPOSAL OF ACM:

Once the ACM is removed, it will be double-bagged and labeled in accordance with Texas Department of State

Health Services (TDSHS) and OSHA guidelines. Pre-printed Generator labels shall be affixed to each bag or wrapped component prior to being placed in the lined waste disposal dumpster or trailer.

All waste will be labeled in accordance with 29 CFR 1910.1200 (f) of OSHA’s Hazard Communication Standard and it will contain the following information:

DANGER

CONTAINS ASBESTOS FIBERS

AVOID CREATING DUST

CANCER AND LUNG DISEASE HAZARD

AUTHORIZED PERSONNEL ONLY

The enclosed cargo area of the truck or dumpster shall be lined with 6-mil polyethylene sheeting to prevent contamination from leaking containers. Trucks and dumpsters shall have lockable enclosed cargo areas.

The area between the bag out area and prepared waste receptacle shall be regulated with barrier tape during bag out operations. The waste dumpster or trailer shall remain secured during all other periods.

The waste must be disposed of at a permitted landfill facility designed to receive such wastes. The Abatement

Contractor shall not transport bagged waste materials in open trucks.

The Abatement Contractor shall retain receipts from landfill for disposed materials.

The Abatement Contractor shall provide copies of Generator and final disposal manifests to CONSULTANT.

END OF SECTION 6.0

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

14 ASBESTOS ABATEMENT PROJECT DESIGN

7.0 AIR MONITORING AND FINAL CLEARANCE

7.1 Air Monitoring.

This section describes air monitoring services to be carried out by the CONSULTANT to verify that the Work performed is in compliance and that the building areas beyond the Work Area and the outside environment remain uncontaminated. This section also sets forth airborne filter levels both inside and outside the Work Area as actions levels and describes the action required by CONTRACTOR if an action level is met or exceeded.

CONSULTANT may delegate responsibilities and duties to a TDSHS licensed Asbestos Project Manager and Asbestos

Air Monitor Technician. The CONSULTANT shall be conducting air monitoring throughout the course of the Work.

Air monitoring required by OSHA is work of the Abatement Contractor and is not covered in this section.

7.2 Baseline Fiber Counts.

Baseline air sampling will be conducted by CONSULTANT prior to initiation of Work by The Abatement Contractor in order to establish background levels of airborne contamination. These samples may be archived by CONSULTANT without analysis.

7.3 Work Area Isolation.

The purpose of CONSULTANT’S air monitoring will be to detect faults in the Work Area isolation such as:

1. Contamination of the building outside the Work Area with airborne asbestos fibers.

2. Failure of filtration or rupture in the negative pressure system.

Should any of the above occur, the Abatement Contractor will immediately cease asbestos abatement activities until the fault is corrected. Work will not recommence until authorized by the CONSULTANT.

7.4 Work Area Airborne Fiber Counts.

The CONSULTANT will monitor airborne fiber counts in the work area. The purpose of this air monitoring will be to detect airborne fiber counts which may significantly challenge the ability of the work area isolation procedures to protect the balance of the building or outside of the building from contamination by airborne fibers.

After the Work Area is found to be visually clean and encapsulant has dried, CONSULTANT shall collect a minimum of three (3) air samples under aggressive sampling protocols and analyzed by Phase Contrast Microscopy (PCM) in accordance with NIOSH 7400 Method A in area which abatement has occurred. A minimum air volume of 1,250 liters of air shall be sampled for final clearance air sampling. Final clearance criteria shall be <0.010f/cc for all clearance samples collected and analyzed.

If final air clearance criteria is not achieved, The Abatement Contractor shall repeat cleaning and continue decontamination procedures from that point.

If final clearance criteria is met, The Abatement Contractor shall remove plastic sheeting and decontamination unit.

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

15 ASBESTOS ABATEMENT PROJECT DESIGN

7.5 Final Air Clearance.

Final Air testing will be performed by Phase Contrast Microscopy (PCM).

7.6 Airborne Fiber Counts.

Inside Work Area:

Where an enclosure is used, maintain an average airborne count in the work area of less than 1.0 fibers per cubic centimeter. If the fiber count rises above this figure for any sample taken, revise work procedures to lower fiber counts. If the Time Weighted Average (TWA) fiber count for any work shift or 8 hour period exceeds 0.2 fibers per cubic centimeter, stop all work, leave negative air system in operation, continue to periodically mist the atmosphere within the work area with amended water and notify CONSULTANT. Do not recommence work until authorized in writing by CONSULTANT.

If airborne fiber counts exceed 0.2 fibers per cubic centimeter for any period of time cease all work until fiber counts fall below 0.1 fibers per cubic centimeter and notify CONSULTANT. Do not recommence work until authorized in writing by the CONSULTANT.

Outside Work Area:

If any air sample taken outside of the work area exceeds the action level of 0.001 fibers per cubic centimeter, immediately and automatically stop all work. If this air sample was taken inside the building and outside of critical barriers around the work area immediately erect new critical barriers as set forth in Section 4.0, to isolate the affected area from the balance of the building.

Erect Critical Barriers at the next existing structural isolation of the involved space (e.i. ceiling, wall and floor).

Decontaminate the affected area in accordance with accepted industry standards.

Respiratory protection as set forth in Section 3.0 shall be worn in affected area until area is cleared for occupancy.

Leave Critical Barriers in place until completion of work and insure that the operation of the negative pressure system in the work area results in a flow of air from the balance of the building into the affected area.

If the exit from the clean room of the personnel decontamination unit enters the affected area, establish a new decontamination facility.

After certification of visual inspection in the work area remove critical barriers separating the work area from the affected area. Final air samples will be taken within the entries area.

7.7 Fiber Type Dispute.

The following procedure will be used to resolve any disputes regarding fiber types when the Work has been stopped due to excessive airborne fiber counts:

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

16 ASBESTOS ABATEMENT PROJECT DESIGN

Air samples will be secured in the same area by CONSULTANT for analysis by Transmission Electron Microscopy at the option of the CONSULTANT and classified as retest and back charged to the Abatement Contractor in accordance with the procedures in this specification.

7.8 Laboratory Testing.

The CONSULTANT shall arrange for laboratory analysis of perform field analysis of the collected air samples. At the option of CONSULTANT, a field laboratory will be setup at the project site, so that verbal reports on air sample analysis can be obtained immediately after collection. Reports to the owner by the CONSULTANT will include air monitoring data and relevant information on Work being conducted such as work hours, number of workers, procedures utilized, discrepancies and corrective measures, containment methods and construction.

The following methods will be utilized at the discretion of the CONSULTANT in collecting and analyzing air samples.

Mixed Cellulose ester filters will be analyzed using NIOSH 7400 method. A representative of the CONSULTANT who has successfully completed a NIOSH 582 course or equivalent and is licensed Air Monitoring Technician will carry out this analysis at a Texas Licensed laboratory located off the jobsite or onsite. PCM mixed Cellulose ester filters will be used for analysis of samples collected for the duration of the project, including clearance sampling.

7.9 Sample Protocols.

The number and volume of air samples taken by the CONSULTANT will generally be in accordance with the following schedule. Sample quantities, locations, volumes and methodologies may vary depending upon the analytical method, project layout, procedures utilized and at the discretion of the CONSULTANT.

7.10 Schedule of Air Samples with PCM.

Before Start of Work: The CONSULTANT will secure the following Air Samples to establish a base line before start of work.

Location Sampled

Number of Samples

25mm

Analytical Method

Filter Media Detection Limit (fibers/cc)

Minimum Volume

Rate LPM

Outside Abatement

Area

1 PCM Cellulose Ester 0.01 1250 2-15

Abatement Area

3 PCM Cellulose Ester 0.01 1250 2-15

Base Line: Is an action level expressed in fibers per cubic centimeters that is the highest actual result from the background sampling process. The baseline samples may be collected and archived at the discretion of the

CONSULTANT.

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

17 ASBESTOS ABATEMENT PROJECT DESIGN

During Abatement: The owner has retained the services of CONSULTANT to provide inspections and air sampling at the areas being abated throughout the course of the project. The number of air samples may vary according to site plan and on authorization of the CONSULTANT or onsite Project Manager.

Number of Samples 25mm

Analytical Method

Filter Media Detection Limit (fibers/cc)

Minimum Volume

Rate LPM

Inside Work Area

3 PCM Cellulose Ester 0.01 500 2-9.5

Outside Work Area

1 PCM Cellulose Ester 0.01 500 2-9.5

Output Negative Pressure System

1 PCM Cellulose Ester 0.01 500 2-9.5

Clean Room 1 PCM Cellulose Ester 0.01 500 2-9.5

If airborne fiber counts exceed allowed limits, additional samples will be taken as necessary to monitor fiber levels and confirm source(s).

7.11 Interior Clearance Samples.

Upon successful completion of visual inspection of interior abatement areas, as scheduled by the CONTRACTOR followed by encapsulation of the abatement area and a drying period, the CONSULTANT will take the following samples:

Number of Samples 25mm

Analytical Method

Filter Media Detection Limit (fibers/cc)

Minimum Volume

Rate LPM

Each Enclosure 3 PCM Cellulose Ester 0.01 1250 9.5

Note: Retesting of clearance samples will be at the CONTRACTOR’s expense.

7.12 Personal Monitoring.

Perform air monitoring as required to meet OSHA Requirements for maintenance of Time Weighted Averaged

(TWA) fiber counts for types of respiratory protection provided. CONSULTANT will not be performing personal air monitoring to meet these OSHA requirements as part of this contract. Negative Exposure Assessments (NEA’s) will not be accepted.

END OF SECTION 7.0

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

18 ASBESTOS ABATEMENT PROJECT DESIGN

8.0 FINAL CLEANUP PROCEDURES

8.1 WORK AREA CLEAN-UP

The work area and the decontamination area shall be thoroughly cleaned after all work is finished.

8.2 METHOD OF CLEAN-UP

The area shall be cleaned with a HEPA vacuum and/or wet-wiped.

8.3 CLEAN-UP OF POLYETHYLENE SHEETING

After vacuuming and/or wet-wiping, all of plastic sheeting shall be sprayed with an encapsulant and then disposed of as asbestos waste.

8.4 POST-CLEARANCE CLEAN-UP

Contractor shall remove all waste materials and equipment from job site within 24 hours of completion of the project (Final Clearance Notification verbally or written from the Consultant).

END SECTION 8.0

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

19 ASBESTOS ABATEMENT PROJECT DESIGN

9.0 INSPECTIONS

In addition to providing air monitoring services, the CONSULTANT will provide a TDSHS licensed Asbestos Project

Manager full-time to conduct onsite observations of Work activities, Work shall not proceed without notice to the

CONSULTANT and presence of CONSULTANT or designated representative at the Work site.

CONSULTANT requests 48-hours advance notice before commencement of Work.

The CONSULTANT will conduct the following key inspections and no Work Activities by CONTRACTOR will proceed beyond these points until all discrepancies noted during the inspection have been rectified.

The CONSULTANT’S inspections do not relieve the CONTRACTOR of Contract obligations are not designated to locate all Work discrepancies. The CONTRACTOR is responsible for the overall quality of the Work.

9.1 First Key Inspection- Inspection of Work Area and Containments Prior to Start of Removal.

Removal operations shall not proceed until the CONSULTANT has completed inspection of the Work Area preparations and until all discrepancies noted have been rectified.

9.2 Second Key Inspection-Inspection during Removal Activities.

Removal activities may not proceed unless CONSULTANT is onsite. Inspection of the Work Area and Work practices will be conducted daily, and upon identification of a discrepancy, the CONTRACTOR shall immediately stop Work and rectify the discrepancy.

9.3 Third Key Inspection- Inspection of Work or Containment after Completion of removal Work, but prior to encapsulation.

A visual inspection of the Work Area and/or containment areas and removal surfaces will be conducted at this point by CONSULTANT and lockdown encapsulation shall not proceed until ACM removal is visually confirmed.

9.4 Fourth Key Inspection-Inspection of Work Area after encapsulation, but prior to Containment Disassembly.

Visual inspection of the encapsulation shall be performed by the CONSULTANT, but not until encapsulant is fully dry

(minimum 2 hours).

9.5 Fifth Key Inspection-Final Clearance.

After encapsulation and final cleanup of Work Area, but prior to removal of Critical Barriers, CONSULTANT will conduct a visual inspection followed by final air testing. Final air sampling will be conducted in accordance with the

Final Clearance Section of this Specification.

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

20 ASBESTOS ABATEMENT PROJECT DESIGN

9.6 Final Key Inspection-Project Closeout Inspection.

A final inspection will be conducted by CONSULTANT after CONTRACTOR has removed Critical Barriers, equipment, and supplies. A project “Punch List” will be provided listing any items requiring correction or completion. Punch List items shall be completed prior to issuance of final completion notice by the Abatement Contractor.

Discrepancies or needed corrective measures observed by the CONSULTANT will be reported to the CONTRACTOR’s onsite superintendent and shall be addressed immediately.

The above inspections are not necessarily single events. Failed inspections will be re-conducted and time classified as retest and charged back to the Abatement Contractor in accordance with this Specification.

Inspections will require 24 hours advance notice to the CONSULTANT.

END OF SECTION 9.0

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

21 ASBESTOS ABATEMENT PROJECT DESIGN

APPENDIX A:

DRAWINGS AND SKETCHES

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

22 ASBESTOS ABATEMENT PROJECT DESIGN

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

23 ASBESTOS ABATEMENT PROJECT DESIGN

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

24 ASBESTOS ABATEMENT PROJECT DESIGN

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

25 ASBESTOS ABATEMENT PROJECT DESIGN

----------License and

Certifications------------

Dec. 28, 2015 Rosalba Flores, Texas AIC # 105779 Expires 07/16/2016 (initials:R.F.)

26 ASBESTOS ABATEMENT PROJECT DESIGN