AS27 Base Life Support Market Research RFI_20260830_V2.docx
DOCX document 52 KB Posted
- Attached to
- RFI Base Life Support Services and Facility Rehabilitation for Angkor Sentinel 2027 (AS27)
- Solicitation number
- AS27RFIBASELIFESUPPORT001
About this file
This is a Request for Information (RFI) issued by the Department of the Army for Base Life Support services and facility rehabilitation supporting Exercise Angkor Sentinel 2027 (AS27) in Cambodia. The RFI seeks market research and industry capability assessments to establish standardized Cost Breakdown Structure (CBS) and Rough Order of Magnitude (ROM) estimates. Responses are due by 30 September 2026 (Hawaii Time, 5PM) to uchechukwu.mbawuike.mil@army.mil, with questions due by 25 September 2026.
The acquisition comprises four distinct components: Component 1 covers external expeditionary Base Life Support (BLS) for 100 US Army Soldiers during a 24-day continuous operational period (7-day ADVON phase February 8-14, 12-day main exercise February 15-26, and 5-day Reverse ADVON February 27-March 3, 2027) at the Multinational Peacekeeping Force Training Center in Cambodia. This includes 100% self-sufficient billeting tents with climate control, 24/7 prime and backup power generation with fuel delivery, external latrines, handwash stations, shower trailers, potable water storage and distribution (120,000 gallons capacity), blackwater and greywater extraction, solid waste haulage, pest control, and laundry services. Components 2, 3, and 4 present three mutually exclusive facility rehabilitation options: a 3-month rapid execution focused on weatherproofing and life-safety remediation; a 6-month intermediate modernization including mechanical, electrical, and plumbing (MEP) replacement; and a 12-month comprehensive master overhaul transforming the compound into a state-of-the-art permanent training hub. All facility work encompasses rehabilitation of eight barracks compounds, a dining facility with cooking area, classroom facilities, medical aid station, and central restrooms. Cross-cutting mandates require vendors to comply with Cambodia vector and pest control standards, solid waste disposal protocols, closed-loop wastewater extraction and treatment, and potable water quality standards (coliform-negative, 0.2-2.0 ppm free available chlorine). Vendors must submit corporate profiles, supply chain assessments, subcontractor and local labor capabilities in Cambodia, environmental licensing documentation, risk analyses, and overall ROM pricing estimates across all components. The Government has clarified this RFI does not constitute a binding commitment and will not reimburse respondent costs.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exercise Angkor Sentinel — RFI
DEPARTMENT OF THE ARMY
ANGKOR SENTINEL 2027 (AS27)
CAMBODIA
Document Type: Request for Information (RFI)
Subject: Base Life Support Services and Facility Rehabilitation for Angkor Sentinel 2027 (AS27)
RFI Number: AS27-RFI-BASE LIFE SUPPORT-001
Release Date: 14 September 2026
Response Deadline: 30 September 2026 (Hawaii Time 5PM)
DISCLAIMER
This Request for Information (RFI) is issued solely for information and planning purposes. It does not constitute a Request for Proposal (RFP), Invitation for Bid (IFB), or Request for Quotation (RFQ), and is not to be construed as a commitment by the Government to enter into a contract. The Government will not pay for any information or administrative costs incurred in response to this RFI. All costs associated with responding to this RFI will be solely at the interested party’s expense.
Key Parameters Target Population: Approximately 100 Personnel total, consisting of:
100 United States (US) Army Soldiers Location: Field environment in Cambodia (in vincinity of Multinational Peacekeeping Force Training Center (ភូមិផ្គង់, ផ្លូវលេខ ៤៤, គីឡូម៉ែត្រ ៨, Krong Chbar Mon, Cambodia).
Contractor Requirement: The contractor must be 100% self-sufficient, providing all mobile food preparation containers, cold storage/refrigeration, power generation, potable water, and waste management.
Period of Performance: Feb 08 – MAR 03 2027
1. Executive Summary & Acquisition Background (BLUF) This RFI is to establish a standardized Cost Breakdown Structure (CBS), Rough Order of Magnitude (ROM) estimates, and industry capability assessments for Base Life Support (BLS) and permanent facility rehabilitation supporting Exercise Angkor Sentinel.
The acquisition framework isolates External Expeditionary BLS (Component 1)—tailored around strict ADVON, Main Body, and Reverse ADVON exercise execution dates—from Three Mutually Exclusive Facility Upgrade Timelines (Components 2, 3, and 4) designed to achieve a 100% turnkey rehabilitation of all permanent installations under 3-Month, 6-Month, or 12-Month Periods of Performance (PoP).
Cross-cutting services—including vector/pest control, solid waste management, and black/greywater removal—are integrated into each component to maintain force health protection and environmental compliance.
Exercise Timeline Architecture ADVON Phase (Feb 08 – Feb 14)
MAIN BODY EXERCISE
(Feb 15 – Feb 26)
REVERSE ADVON
(Feb 27 – Mar 03)
• Site setup & staging
• Power/water commissioning
• 25 PAX support
• Full 200 PAX sustainment
• Continuous BLS operations
• Force health protection
• Retrograde & teardown
• Waste clearing & handover
• 25 PAX support
2. Operational Parameters & Facility Baseline Supported Population & Operational Schedule Main Exercise Window: February 15, 2027 – February 26, 2027 (12 Operational Days) Advanced Echelon (ADVON): February 08, 2027 – February 14, 2027 (7 Mobilization & Setup Days) Reverse ADVON (Redeployment): February 27, 2027 – March 03, 2027 (5 Teardown & Retrograde Days) Total Expeditionary BLS Operational Period: 24 Continuous Days
3. Component 1: External Base Life Support (Expeditionary BLS) Scope of Work: A 100% self-sufficient expeditionary tent camp located at the Billeting Area, fully isolated from base utilities, operating continuously across the ADVON, Main Exercise, and Reverse ADVON periods (February 08 – March 03). Expeditionary Tent would support 100 Personnel (Includes a dedicated female tent)
| CLIN |
| Item Description |
| Technical Scope & Specifications |
| Period / QTY |
| Unit |
| Unit Price ($) |
| Total Cost ($) |
| 1001 |
| Billeting Tents (Climate-Controlled) |
(40 Sq Ft Per Soldier)
| Heavy-duty, weather-resistant frame tents with raised flooring, integrated HVAC/ECU units (maintaining 68–74°F), interior LED lighting, electrical outlets, cots, mattresses, and individual mosquito nets for 100 PAX. ADVON prep by Feb 10. |
| 24 Days |
| 1 Each Tent |
| Vendor Input |
| Vendor Input |
| 1002 |
| 24/7 Prime & Backup Power Generation |
| Continuous prime power generator system with N+1 automatic failover backup, secondary environmental fuel containment, power distribution panels, cables, and 100% contractor-furnished fuel delivery. |
| 24 Days |
| 1 Lot |
| Vendor Input |
| Vendor Input |
| 1003 |
| External Latrines |
Or Potta Johns
1 per 25 males;
1 per 17 females
| Mobile containerized/trailerized flushing latrines with separate male and female compartments, internal lighting, exhaust fans, and complete stock of daily consumables (toilet paper, hand sanitizer). |
| 24 Days |
| 5 Stalls |
(4 Males; 1 Females)
| Vendor Input |
| Vendor Input |
| 1004 |
| Handwash Stations |
| Dual-basin foot-pump operated handwashing units equipped with liquid soap dispensers and weather-protected paper towel holders, serviced and sanitized 3x daily. |
| 24 Days |
| 5 Units |
| Vendor Input |
| Vendor Input |
| 1005 |
| External Shower Trailers |
| Multi-stall containerized shower units with on-demand continuous hot/cold water heating, non-slip flooring, privacy curtains, and dedicated female-segregated secure units. |
| 24 Days |
| 10 Stalls |
| Vendor Input |
| Vendor Input |
| 1006 |
| Water Storage & Distribution |
| Provision of sanitary water bladders/tanks (15,000 gal capacity) and continuous bulk potable water delivery meeting WHO and DoD Tri-Service environmental health standards. |
| 24 Days |
| 120k Gal |
| Vendor Input |
| Vendor Input |
| 1007 |
| Blackwater & Greywater Extraction |
| Daily scheduled vacuum pumping and transport of wastewater from latrines, showers, and handwash units; licensed off-site biological treatment and disposal. |
| 24 Days |
| 24 Svcs |
| Vendor Input |
| Vendor Input |
| 1008 |
| Solid Waste Haulage & Camp Pest Control |
| Covered 4-yard dumpsters, daily trash pickup/bagging, daily camp perimeter mosquito barrier spraying (fogging), rodent traps, and ADVON/Rev-ADVON site sanitation. |
| 24 Days |
| 1 Lot |
| Vendor Input |
| Vendor Input |
| 1008 |
| Laundry Services |
| Laundry Services |
| 24 Days |
| 1 Bag |
| Vendor Input |
| Vendor Input |
4. Phased Permanent Facility Rehabilitation Options The Government seeks independent cost models for three potential upgrade durations. Each option encompasses the complete rehabilitation of all facilities (excluding Component 1 External BLS), differentiated by execution tempo, resource surging, material lifecycle, and engineering depth.
OPTION A: Phase 1 (3 Months) OPTION B: Phase 2 (6 Months) OPTION C: Phase 3 (12 Months)
• Rapid Surge
• Operational Restoration
• Weatherproofing & safety focus
• Intermediate Modernization
• MEP Overhaul
• Anti-fungal coatings & HVAC
• Complete Long-Term Overhaul
• Structural & Grid Overhaul
• Permanent training hub standard
5. Component 2: Phase 1 Complete Facility Upgrade (3-Month Rapid Execution) Strategy: A rapid 90-day surge rehabilitation focusing on high-speed restoration, structural weatherproofing, critical life-safety remediation, functional utility reconnection, and rapid deep-cleansing to achieve immediate operational capability.
| CLIN |
| Facility Area |
| Scope of 3-Month Rapid Rehabilitation |
| QTY |
| Unit |
| Unit Price ($) |
| Total Cost ($) |
| 2001 |
| 8 Barracks Compounds |
| Emergency roof leak patching; screen/window repair; restoring existing 2 latrines, 2 handwash stations, 2 male showers, and 1 female suites to operational status; basic electrical rewiring and light fixtures. |
| 8 |
| Bldgs |
| Vendor Input |
| Vendor Input |
| 2002 |
| DFAC Dining Hall |
| Deep sanitary scrubdown; roof seam sealant application; high-volume exhaust fan repair; replacement of broken fluorescent fixtures with LED luminaires; entry door fly screens. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 2003 |
| DFAC Cooking Facility |
| Hydro-jetting and clearing of blocked drains; grease trap cleanout and mechanical valve restoration; installation of emergency power drop-lines; commercial sanitation line hookup. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 2004 |
| Classroom Facilities |
| Upgrade Airconditioning System, Broken window pane replacement; security mesh installation; ceiling fan motor repairs; whiteboard wall resurfacing; basic interior repainting. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 2005 |
| Medical Aid Station |
| Upgrade Airconditioning System; antimicrobial washdown and wall sealing; pressurized potable water pump install; high-security pharmacy deadbolts. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 2006 |
| Central Restrooms |
| Upgrade Airconditioning System, Pipe descaling; replacement of broken porcelain toilets, urinals, and sink faucets; gravity feed water tank leak sealing and float valve replacement. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 2007 |
| Minor Area Electrical & Lighting |
| Compound-wide installation of high-lumen commercial LED exterior security floodlights; distribution breaker box replacement and circuit grounding verification. |
| 1 |
| Job |
| Vendor Input |
| Vendor Input |
| 2008 |
| Electrical Transformer Repair/Upgrade |
| Repair and Upgrade Electrical Transformer to provide sufficient electrical support for all Billeting, Dinning, and Classroom areas. |
| 1 |
| Job |
| Vendor Input |
| Vendor Input |
6. Component 3: Phase 2 Complete Facility Upgrade (6-Month Intermediate Execution) Strategy: A balanced 180-day intermediate modernization providing comprehensive mechanical, electrical, and plumbing (MEP) replacement, durable epoxy/ceramic floor resurfacing, complete interior/exterior anti-fungal repainting, and facility HVAC enhancements.
| CLIN |
| Facility Area |
| Scope of 6-Month Intermediate Modernization |
| QTY |
| Unit |
| Unit Price ($) |
| Total Cost ($) |
| 3001 |
| 8 Barracks Compounds |
| Full plaster/masonry repair; anti-fungal epoxy coating; full copper/PVC plumbing line repiping; complete restoration existing 2 latrines, 2 handwash stations, 2 male showers, and 1 female suites to operational status; basic electrical rewiring and light fixtures. |
| 8 |
| Bldgs |
| Vendor Input |
| Vendor Input |
| 3002 |
| DFAC Dining Hall |
| Installation of 4x commercial ceiling fans and 2x 36,000 BTU split A/C units; acoustic ceiling tile replacement; heavy-duty slip-resistant epoxy floor coating; dining fixture refurbishment. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 3003 |
| DFAC Cooking Facility |
| Stainless steel prep table buildout; commercial stainless grease hood installation; commercial trench drainage install; dedicated exterior greywater interceptor tank. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 3004 |
| Classroom Facilities |
| Multi-split A/C installation; dual whiteboard and projection electrical infrastructure; commercial doors with perimeter weatherproofing; acoustic dampening wall panels. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 3005 |
| Medical Aid Station |
| Medical-grade antimicrobial seamless flooring; dedicated emergency backup power sub-panel; secure lockable pharmaceutical cage; reverse-osmosis sterile water filtration station. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 3006 |
| Central Restrooms |
| Full wet-area ceramic tiling; institutional stainless vandal-resistant toilets and water-saving push valves; septic tank pumping, structural repair, and new inspection risers. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 3007 |
| General Civil & Electrical Grid |
| Repair and Upgrade Electrical Transformer to provide sufficient electrical support for all Billeting, Dinning, and Classroom areas. |
Underground conduit runs; secondary power sub-panel replacements; perimeter LED street lighting; civil ditch grading to eliminate monsoon rainwater ponding.
| 1 |
| Job |
| Vendor Input |
| Vendor Input |
7. Component 4: Phase 3 Complete Facility Upgrade (12-Month Full Overhaul) Strategy: A comprehensive 365-day master overhaul and long-term modernization delivering institutional-grade architectural, civil, structural, and electrical resilience, transforming the compound into a state-of-the-art permanent training hub.
| CLIN |
| Facility Area |
| Scope of 6-Month Intermediate Modernization |
| QTY |
| Unit |
| Unit Price ($) |
| Total Cost ($) |
| 4001 |
| 8 Barracks Compounds |
| Full plaster/masonry repair; anti-fungal epoxy coating; full copper/PVC plumbing line repiping; complete restoration existing 2 latrines, 2 handwash stations, 2 male showers, and 1 female suites to operational status; basic electrical rewiring and light fixtures. |
| 8 |
| Bldgs |
| Vendor Input |
| Vendor Input |
| 4002 |
| DFAC Dining Hall |
| Installation of 4x commercial ceiling fans and 2x 36,000 BTU split A/C units; acoustic ceiling tile replacement; heavy-duty slip-resistant epoxy floor coating; dining fixture refurbishment. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 4003 |
| DFAC Cooking Facility |
| Stainless steel prep table buildout; commercial stainless grease hood installation; commercial trench drainage install; dedicated exterior greywater interceptor tank. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 4004 |
| Classroom Facilities |
| Multi-split A/C installation; dual whiteboard and projection electrical infrastructure; commercial doors with perimeter weatherproofing; acoustic dampening wall panels. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 4005 |
| Medical Aid Station |
| Medical-grade antimicrobial seamless flooring; dedicated emergency backup power sub-panel; secure lockable pharmaceutical cage; reverse-osmosis sterile water filtration station. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 4006 |
| Central Restrooms |
| Full wet-area ceramic tiling; institutional stainless vandal-resistant toilets and water-saving push valves; septic tank pumping, structural repair, and new inspection risers. |
| 1 |
| Facility |
| Vendor Input |
| Vendor Input |
| 4007 |
| General Civil & Electrical Grid |
| Repair and Upgrade Electrical Transformer to provide sufficient electrical support for all Billeting, Dinning, and Classroom areas. |
Underground conduit runs; secondary power sub-panel replacements; perimeter LED street lighting; civil ditch grading to eliminate monsoon rainwater ponding.
| 1 |
| Job |
| Vendor Input |
| Vendor Input |
8. Cross-Cutting Environmental & Sustainment Mandates All vendors submitting ROM estimates must factor the following technical performance parameters into their unit pricing across all four components:
| 1. Vector & Pest Control |
| 2. Solid Waste Disposal |
| 3. Blackwater / Greywater |
| 4. Potable Water Compliance |
| Comply with Cambodia Vector and Pest Control Standards |
| Covered dumpsters, daily haulage to licensed landfills. |
| Certified vacuum pumping & off-site biological treatment. |
| FWRA Approved Vendors (coliform/chlorine). |
Integrated Pest & Vector Management (IPM): Strict compliance with the Cambodia Standards. Mandatory mosquito abatement targeting Aedes and Anopheles species (Dengue/Malaria mitigation), subsurface termite barriers, and indoor baiting.
Solid Waste Management: Provision of heavy-duty covered roll-off dumpsters. Mandatory daily collection, sorting, and manifest-tracked disposal at authorized provincial municipal landfills. No open burning or burying permitted.
Wastewater & Blackwater Extraction: Closed-loop vacuum extraction from mobile units and permanent septic tanks. Disposal must occur at verified government-certified wastewater treatment facilities.
Potable Water Quality Standards: All water deliveries and plumbed potable lines must be certified negative for coliform bacteria and heavy metals, maintaining a free available chlorine (FAC) residual between 0.2 and 2.0 ppm at all points of distribution. FWRA Approved sources.
9. Vendor Market Research Questionnaire Interested industry contractors are requested to complete the following capability assessment to assist the Contracting Office in developing the formal acquisition strategy:
Vendor Corporate & Technical Profile
| Company Name: |
| _____________________________________ |
| CAGE Code / SAM.gov UEI: |
| ____________________ |
| Primary Point of Contact: |
| ____________________ |
| Corporate Operating Address: |
| ____________________ |
Supply Chain & Sourcing Capacity:
What is your standard lead-time for mobilizing commercial prime generators (150–300 kVA), containerized latrines/showers, and commercial HVAC units into the training area in Cambodia?
Response: ____________________________________________________________________ Subcontractor & Local Labor Mobilization:
Describe your existing network of certified electricians, master plumbers, and civil labor within the targeted Cambodian province.
Response: ____________________________________________________________________ Environmental Licensing & Disposal Assets:
Identify your licensed disposal partner, distance to the nearest approved municipal landfill, and licensed wastewater processing facility.
Response: ____________________________________________________________________ Risk Analysis & Schedule Drivers:
In your technical opinion, what are the primary cost drivers and schedule risk factors (e.g., monsoon season logistics, regional electrical grid instability, imported material tariffs) across the 3-Month, 6-Month, and 12-Month timelines?
Response: ____________________________________________________________________
10. Rough Order of Magnitude (ROM) Summary Schedule Vendors are requested to submit their overall pricing estimates utilizing the standardized format below:
| Component Category |
| Description |
| Execution Duration |
| Estimated ROM Range ($ USD) |
| Component 1 |
| External Expeditionary BLS (ADVON, Main, Rev-ADVON) |
| 24 Continuous Days |
| $ ________________ |
| Component 2 |
| Option A: Complete Facility Upgrade (Rapid Execution) |
| 3 Months PoP |
| $ ________________ |
| Component 3 |
| Option B: Complete Facility Upgrade (Intermediate Overhaul) |
| 6 Months PoP |
| $ ________________ |
| Component 4 |
| Option C: Complete Facility Upgrade (Long-Term Master Overhaul) |
| 12 Months PoP |
| $ ________________ |
| Total Estimated Price |
| Comprehensive Turnkey Life Support & Upgrade |
| Selected Option + BLS |
| $ ________________ |
11. Submission Guidelines & Contracting Point of Contact Respondents shall not be obligated to provide the services described herein, and it is understood by the United States Government that if any price estimates are provided as a result of this request, they are “best” estimates only.
Interested vendors must submit their responses electronically.
Format: Microsoft Word, PDF, or Excel (for the pricing tables).
Language: Spoken and written responses must be in English.
Submission Address: Send to the 413th Contracting Support Brigade at: uchechukwu.mbawuike.mil@army.mil
Point of Contact: MAJ Jared & SSG Mbawuike Responses must be received no later than the deadline listed at the top of this document. Questions regarding this RFI may be submitted via email no later than 25 September 2026 The Government will not award a contract based upon responses to this announcement. The Government shall not reimburse or pay any costs for preparing or submitting information in response to this notice.