ARPA FUNDING-.docx

DOCX document 15 KB Posted

Attached to
Well Installation and Well Abandonment (WIIN-12_W&WA)
Solicitation number
QQ-122031
Issued by
Patrick County, Virginia

About this file

This document outlines ARPA (American Rescue Plan Act) funding compliance requirements and obligations for subrecipients of Virginia Department of Health (VDH) administered federal funds, specifically applicable to Water, Sewer, and Broadband infrastructure projects, including the Well Installation and Well Abandonment (WIIN-12_W&WA) initiative in Virginia. Subrecipients must adopt conflicts of interest policies preventing competitive bidding involvement in specification development, maintain comprehensive audit and financial management practices with public accessibility of audit reports, and ensure personnel availability for federal auditor interviews. Equipment purchased with federal funds requires insurance coverage equal to equipment value, detailed record maintenance including serial numbers and acquisition costs, and biennial physical inventory reconciliation. Contracting requirements mandate cost reduction incentives and clear processes for payment withholding and appeals procedures, while monitoring and reporting obligations include quarterly submissions within 30 days of quarter-end with specific data elements depending on project type.

Quarterly reporting for Water and Sewer projects must include NPDES permit numbers or Public Water System ID numbers as applicable, while Broadband projects require speeds, pricing tiers, technology specifications, fiber mileage, cost-per-mile and cost-per-passing data, and projected household and institutional access increases. Onsite technical inspections and certified completion percentages are mandatory for construction projects, with subrecipients required to notify VDH of any significant impacts from unforeseen events. Labor documentation requirements apply to projects exceeding $10 million. At project completion, subrecipients must remit unused supplies valued over $5,000 to VDH. All requirements derive from 2 CFR Part 200 (Uniform Guidance) and SLFRF (State and Local Fiscal Recovery Fund) Compliance and Reporting Guidance, ensuring federal accountability and transparent stewardship of recovery funds.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARPA FUNDING

· General Obligations

· Adopt and abide by a conflicts of interest policy, prohibiting subrecipients from competing for awards or grants in which they develop or draft specifications, requirements, or statements of work [See 2 CFR 2 CFR 200.319(b)].

· Audit/Financial Management

· The subrecipient makes audit reports available for public inspection [See 2 CFR 200.507].

· Make subrecipient’s personnel available to speak with federal auditors [See 2 CFR 200.508(d)].

· Document any material deviations from budget or project scope or objective, and request prior approval from VDH [See 2 CFR 200.308(b)]

· Equipment Management

· Procure insurance policies for equipment purchased with federal funds equal to the value of such equipment for the duration of the project [See 2 CFR 200.310]

· Maintaining equipment records that include equipment description, a serial number or other identification number, Federal funding source (if applicable), the acquisition date, acquisition cost, location, and equipment condition [See 2 CFR 200.313(d)]

· At least every two years, take a physical inventory of equipment and reconcile the results with equipment records [See 2 CFR 200.313(d)]

· Contracting

· Incentivize cost reductions and opportunities to reduce operating cost going forward [e.g., see 2 CFR 200.318(g)]

· Describe the process by which VDH may withhold payments, including determining unallowable costs, from a subrecipient and the subrecipient’s options to appeal such a decision [See 2 CFR 200.305(b)(6) and 2 CFR 200.410]

· Monitoring/Reporting

· Relate financial data and accomplishments to performance goals and objectives when preparing periodic reports [See 2 CFR 200.329(b)]

· Conduct onsite technical inspections and gain certified percentage of completion data to monitor for construction project completion [See 2 CFR 200.329(d)]

· Inform VDH if the supported activity is significantly impacted by unforeseen positive or negative events [See 2 CFR 200.329(e)]

· Quarterly reporting for all subrecipient ARPA funded Water, Sewer, and Broadband projects include: (1) Projected/actual construction start date; (2) Projected/actual initiation of operations date; (3) Location (for broadband, geospatial location data); (4) Labor documentation requirements for projects over $10 million [See SLFRF Compliance and Reporting Guidance, pg. 21]

· Quarterly reporting for all subrecipient ARPA funded Broadband projects include:(1) Speeds/pricing tiers to be offered; (2) Technology to be deployed; (3) Miles of fiber; (4) Cost per mile; (5) Cost per passing; (6) Number of households projected to have increased access to broadband (7) Number of institutions and businesses projected to have increased access to broadband [See SLFRF Compliance and Reporting Guidance, pg. 22]

· Quarterly reporting for all subrecipient ARPA funded Water and/or Sewer projects include: (1) National Pollutant Discharge Elimination System (NPDES) Permit Number for projects aligned with the Clean Water State Revolving Fund; (2) Public Water System (PWS) ID number for projects aligned with the Drinking Water State Revolving Fund [See SLFRF Compliance and Reporting Guidance, pg. 22]

· Ensure subrecipients prepare, complete, and submit ARPA SLFRF financial, performance, and compliance reporting within 30 days of each quarter [See SLFRF Compliance and Reporting Guidance, pg. 9]

· Project Wrap-up

· Remit the value of any unused supplies in excess of $5,000 to VDH [See 2 CFR 200.314(a)]