ARES Notional Schedule Update to Industry.pdf

PDF 257 KB Posted

Attached to
ARES Notional Schedule Update
Solicitation number
Not on record
Issued by

About this file

This document is a Notional Schedule Update from Kessel Run Flight Operations (Flight Ops) for the Aerospace Readiness Enterprise System (ARES), outlining a detailed acquisition milestone schedule for a prototype and production Other Transaction (OT) award. The key acquisition dates include releasing the Final Solution Solicitation on 15 December 2025, with industry questions due by 19 December 2025, solution submissions from offerors by 9 January 2026, and initial solution evaluations completed by 16 January 2026. The prototype OT award is scheduled for 25 February 2026, with a Minimum Viable Product (MVP) delivery targeted for 22 May 2026, and the production OT award set for 10 August 2026. The document emphasizes that this schedule is notional and subject to change, with the government seeking to aggressively reduce timelines wherever possible.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Kessel Run Flight Operations (Flight Ops)

Aerospace Readiness Enterprise System (ARES)

Notional Schedule Update to Industry

Updated Notional Acquisition Milestone Schedule

Acquisition Milestone Date

Release Final Solution Solicitation 15 December 2025

Questions from Industry Due 19 December 2025 Receive Solutions from Offerors 9 January 2026 Evaluation of Solutions from Offerors 16 January 2026 Prototype OT Award 25 February 2026

Prototype Delivered-Minimum Viable Product (MVP) 22 May 2026 Production OT Award 10 August 2026

NOTE: This schedule is notional and subject to change. The Government is seeking to aggressively reduce the schedule wherever possible. This update is current as of 2 December 2025.

Instructions Regarding this ARES Update

The Government will not be accepting any questions regarding any material released in this update. Any questions should be held until the Final Solution Solicitation is released to Industry.

At that time, questions must flow through the Agreements Officer as annotated in the SAM.gov posting for the Final Solution Solicitation.