This Appendix I document contains the construction and administration forms for the Chi941410B Nutrient Reduction Wetland Project (Bid No. 26-04) administered by the Iowa Department of Agriculture and Land Stewardship's Division of Soil Conservation and Water Quality in Chickasaw County. The project involves construction of a nutrient reduction wetland with multiple completion milestones: all construction work except seeding is due by June 15, 2027, buffer seeding by June 30, 2027, and structure seeding by September 15, 2027. The forms establish a 14-day post-award period for the successful bidder to obtain a Performance Bond, submit a Construction Progress Schedule, execute the contract, and provide proof of Iowa Department of Inspections, Appeals & Licensing registration and Certificate of Insurance. A mandatory Preconstruction Conference must occur within seven days prior to the established Construction Start Date, and no site work may commence before this conference. The Notice-to-Proceed authorizes the contractor to purchase construction materials tax-free under Iowa Code Section 423.2(80), with reimbursement available for materials stored before the Construction Start Date.

The forms provide templates and procedures for ongoing contract administration, including a Construction Progress Schedule form to establish specific work phases and durations, an Application and Certificate for Payment for contractor reimbursement requests, a Change Order Request form for scope modifications requiring approval by Susan Kozak, Director of the Division of Soil Conservation and Water Quality, and a Construction Contract Amendment form to document revisions to completion dates or contract costs. The Sales Tax Exemption Certificate authorizes the contractor to purchase qualifying building materials exempt from Iowa sales tax and applicable local option taxes, provided the materials are used on the project and the contractor maintains documentation of purchases and usage. Contractors are cautioned that misuse of the exemption certificate for non-qualifying items or materials not used on the project may result in civil or criminal penalties, with any improperly exempted taxes due directly to the Iowa Department of Revenue in the same calendar quarter the project is completed.

View the file

Other files

File Type Posted
Bid Bond revised 6-21-25.pdf PDF
Pre-bid notes, sign-in sheet, plan holders list.pdf PDF
Notice to Bidders revised 6-23.pdf PDF
Specifications.pdf PDF
Doc CC Proposal, Acknowledgement, Affidavit.pdf PDF
Notice to Bidders.pdf PDF
Schedule of Prices.pdf PDF
Plans.pdf PDF
Construction Monitoring Plan.pdf PDF
General Requirements.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX I

CONSTRUCTION & ADMINISTRATION FORMS

Chi941410B Nutrient Reduction Wetland Project DOCUMENT LL Bid No. 26-04 NOTICE-OF-AWARD

LL-1

June 15, 2026

Contractor name and address

Delivery via email: Contractor Email

RE: NOTICE-OF-AWARD – Chi941410B Nutrient Reduction Wetland Project, Contract 26-04

Dear _______________________________, This is to notify you that the Division of Soil Conservation and Water Quality has determined __________________ is the successful bidder for the Chi941410B Nutrient Reduction Wetland Project.

Award is being made for the base bid of $____________.

In accordance with Item #9 of the Instructions to Bidders, Document BB, you have fourteen (14) calendar days from the date of receipt of this notice to obtain the Performance Bond (Document NN), submit your Construction Progress Schedule (Document JJ) for review, and execute the Contract (Document DD). In addition, the Division must be provided with a Certificate of Insurance pursuant to the General Conditions, Insurance and Related Provisions (Document FF, Part 6-01).

Please note that Iowa Code Section 91C.7, requires that all construction contractors awarded a contract to perform work for the state or an agency of the state must be registered with the Iowa Department of Inspections, Appeals & Licensing. The Division of Soil Conservation and Water Quality cannot execute a contract with your firm unless you provide proof of this registration. Be sure to fill in the Department of Inspections, Appeals & Licensing registration number blank on the Contract (Document DD).

Enclosed are the Contract (Document DD), Construction Progress Schedule form (Document JJ), and the Performance Bond (Document NN). Please complete, sign and return scanned electronic copies along with completed Performance Bond. In addition, we must have the Certificate of Insurance pursuant to the General Conditions and/or Special Conditions.

Congratulations on being the successful bidder. We look forward to working with your company on this project. If you have any questions, please contact Tracy Blocker, (515) 344-6279.

Sincerely, Jake Hansen, Chief Water Resources Bureau Division of Soil Conservation and Water Quality

JH/tab Enclosures

CC:

Chi941410B Nutrient Reduction Wetland Project DOCUMENT MM Bid No. 26-04 NOTICE- TO-PROCEED

MM-1

June 15, 2026

Contractor name and address

Delivery via email: Contractor Email

RE: NOTICE-TO-PROCEED – Chi941410B Nutrient Reduction Wetland Project, Contract 26-04

Dear____________________________, The Division of Soil Conservation and Water Quality received the signed construction Contract (Document DD), the completed Performance Bond (Document NN), and the Certificate of Insurance from your company. These documents were found to be in order and the Division executed this contract with __________ dated xx/xx/xxxx. A scanned copy of the executed Contract and Performance Bond are enclosed.

The Division has accepted the Construction Progress Schedule (Document JJ) included here, with a Construction Start Date of xx/xx/xxxx. A Preconstruction Conference, as required in Item 13 of the Instructions to Bidders (Document BB), must be held within seven (7) days prior to the Construction Start Date established in the Construction Progress Schedule, or earlier if mutually agreed. No work may commence on site prior to the Preconstruction Conference. If the Construction Start Date requires adjustment, that needs to be communicated to the Engineer and Division in a timely manner so as to facilitate scheduling of the Preconstruction Conference.

In accordance with the Contract _____________________ must commence work under this contract for the Chi941410B Nutrient Reduction Wetland Project on or before the Construction Start Date scheduled in the Construction Progress Schedule, but not before the Preconstruction Conference. You have until June 15, 2027 to complete all of the work except for seeding, and until 06/30/2027 to complete the buffer seeding and 09/15/2027 to complete structure seeding.

Also attached is a scanned copy of the Iowa Construction Sales Tax Exempt Certificate and Authorization Letter for this project. Pursuant to Iowa Code Section 423.2(80), this allows you to purchase materials tax free for use on this project. Please read the information provided in the authorization letter. You are authorized with this Notice-to-Proceed to purchase necessary materials for this project and request reimbursement for those items that are stored prior to the Construction Start Date.

If you have any questions, please contact Tracy Blocker, (515) 344-6279.

Sincerely, Jake Hansen, Chief Water Resources Bureau Division of Soil Conservation and Water Quality

JH/tab Attachments

CC:

Chi941410B Nutrient Reduction Wetland Project DOCUMENT JJ Bid No. 26-04 CONSTRUCTION PROGRESS SCHEDULE

JJ-1

STATE OF IOWA

DIVISION OF SOIL CONSERVATION AND WATER QUALITY

CONSTRUCTION PROGRESS SCHEDULE

Project ID: Chi941410B Date: _______________________________

Contractor: ___________________________________________________________________________________

Contract End Dates:

All Construction Work Except Seeding: June 15, 2027 Seeding: Buffer 06/30/2027 Seeding: Structure 09/15/2027

Scheduled Dates:

Anticipated Construction Start Date:

Preconstruction Conference Date Range*:

*Preconstruction Conference must be held prior to Construction Start Date, by no more than seven (7) days

Estimated Completion Date of All Work Except Seeding:

Final Walkthrough should be held prior to Contract End Date for all construction work except seeding

Major Construction Work Item(s) Order of Work Estimated Duration of Work

(Items to be established/grouped by Division on an individual project basis)

Dates established in this schedule may be adjusted as described in Document FF, Paragraph 3-21.

Chi941410B Nutrient Reduction Wetland Project DOCUMENT JJ Bid No. 26-04 CONSTRUCTION PROGRESS SCHEDULE

JJ-2

FOR THE CONTRACTOR

(Company Representative)

(Date)

(Name of Company)

(Address of Company)

(City, State, Zip code

FOR THE DIVISION

Mike Bourland, Water Resources Bureau Division of Soil Conservation and Water Quality

Accepted

Adjustment Requested

If adjustment is requested, describe below:

END OF DOCUMENT JJ

Chi941410B Nutrient Reduction Wetland Project DOCUMENT SS Bid No. 26-04 APPLICATION AND CERTIFICATE FOR PAYMENT

SS-1

Chi941410B Nutrient Reduction Wetland Project DOCUMENT SS Bid No. 26-04 APPLICATION AND CERTIFICATE FOR PAYMENT

SS-2

Chi941410B Nutrient Reduction Wetland Project DOCUMENT HH Bid No. 26-04 CHANGE ORDER REQUEST

HH-1

STATE OF IOWA

CHANGE ORDER REQUEST

Change Order Request No.

Project ID: Chi941410B Date:

Name of Project: Chi941410B

Location of Project: Chickasaw County

Name of Contractor:

Architect/Engineer: JEO, Jake Mirovsky P.E.

Contract Plan and Detail Reference:

Change Order Request Drawing No. and Date:

Contract Specification Reference:

Description of Change:

BREAKDOWN OF CHANGE ORDER COST BY BID ITEM:

Item # Description Adjustment Quantity Unit Cost

Total Cost Adjustment

TOTAL $

BREAKDOWN OF CONTRACT COST:

Original Project Contract Amount: $ 0.00 Approved Contract Amendments No. through $ 0.00 Pending Recommended Change Order Requests through $ 0.00 Approved Change Order Requests No. through $ 0.00 This Amendment Request: $ 0.00 Resulting Total Recommended Amount: $ 0.00

Reason for Contract Change:

Chi941410B Nutrient Reduction Wetland Project DOCUMENT HH Bid No. 26-04 CHANGE ORDER REQUEST

HH-2

Change Requested by:

(Signature) (Date)

CONTRACTOR APPROVAL

By:

(Company) (Signature)

(Address) (Date)

IDALS PROJECT REPRESENTATIVE RECOMMENDATIONS

Concur Recommend Rejection (Attach Explanation)

IDALS Project Representative:

(Signature) (Date)

DIVISION OF SOIL CONSERVATION AND WATER QUALITY AUTHORIZATION

Change Order required due to:

Immediate authorization to proceed granted: Yes No

APPROVED: DENIED:

Susan Kozak, Director Susan Kozak, Director Division of Soil Conservation and Water Quality Division of Soil Conservation and Water Quality Iowa Department of Agriculture Iowa Department of Agriculture and Land Stewardship and Land Stewardship

(Date) (Date)

END OF DOCUMENT HH

Chi941410B Nutrient Reduction Wetland Project DOCUMENT II Bid No. 26-04 CONSTRUCTION CONTRACT AMENDMENT

II-1

State of Iowa Iowa Department of Agriculture and Land Stewardship

Chi941410B Nutrient Reduction Wetland Project Construction Contract Amendment

THIS AMENDMENT, made this ______ day of ___________________________, 20____, by and between the State of Iowa, acting through:

Iowa Department of Agriculture and Land Stewardship

Division of Soil Conservation and Water Quality hereinafter called the DIVISION, and

(Name of Company)

(Address)

(City, State, Zip) hereinafter called the CONTRACTOR.

WITNESSETH: That the DIVISION and the CONTRACTOR mutually agree to amend the agreement made the _____day of __________, 20_____, for the Chickasaw County Nutrient Reduction Wetland Project (Chi941410B – Bid No. 26-04) in this Amendment Number _________ as described below:

Description of Amendment:

Contract Plan Sheet(s) and Detail Reference(s):

Amendment No._______ Drawing No. and Date:

Contract Specification Reference(s):

Reason for Revision of Contract Completion Date(s):

Original Contract Completion Date for All Work Except Seeding: June 15, 2027 Current Completion Date for All Work Except Seeding:

Revised Completion Date for All Work Except Seeding, This Amendment:

Original Contract Completion Date for Seeding-Buffer 06/30/2027 Current Completion Date for Seeding-Buffer Revised Completion Date for Seeding-Buffer, Original Contract Completion Date for Seeding-Structure 09/15/2027 Current Completion Date for Seeding-Structure Revised Completion Date for Seeding-Structure, Chi941410B Nutrient Reduction Wetland Project DOCUMENT II Bid No. 26-04 CONSTRUCTION CONTRACT AMENDMENT

II-2

BREAKDOWN OF AMENDMENT CONTRACT COST BY BID ITEM:

Item # Description

Quantity Unit Cost

Total Cost

TOTAL $

BREAKDOWN OF CONTRACT COST:

Original Project Contract Amount: $ 0.00 Approved Contract Amendments No. through $ 0.00 Pending Recommended Change Order Requests through $ 0.00 Approved Change Order Requests No. through $ 0.00 This Amendment Request: $ 0.00 Resulting Total Recommended Amount: $ 0.00

IN WITNESS WHEREOF, the parties hereto have executed this Amendment, in the day and year first above mentioned.

FOR THE DIVISION FOR THE CONTRACTOR

Grant D. Menke, Deputy Secretary Iowa Department of Agriculture and Land Stewardship

(Company Representative)

(Date) (Date)

(Name of Company)

(Address of Company)

(City, State, Zip Code)

CONSENT FROM SURETY

Seal if by a corporation

(Surety Representative)

(Name of Surety)

END OF DOCUMENT II

Chi941410B Nutrient Reduction Wetland Project DOCUMENT QQ Bid No. 26-04 SALES TAX EXEMPTION CERTIFICATE

IOWA

Department of Revenue www.state.ia.us/tax

Designated Exempt Entity Iowa Construction Sales Tax Exemption Certificate

This document may be completed by a designated exempt entity and given to their contractor and/or subcontractor along with an authorization letter. Seller: Keep this certificate in your files. Contractor/Exempt Entity: Keep a copy of this certificate for your records. Do not send this to the Department of Revenue

Designated Exempt Entity Division of Soil Conservation and Water Quality Iowa Department of Agriculture and Land Stewardship Address 1 1305 East Walnut Street Address 2

City Des Moines

State

IA

Zip Code 50319

Construction Project Name Chi941410B Nutrient Reduction Wetland Project Construction Project Number (if used) Job No. 26-04

General Contractor or Subcontractor Name Sample Address 1 123 Construction Ave Address 2 City Dig City

State

IA

Zip Code 55555

Description of contract/subcontract (please print/type clearly)

Construction of Nutrient Reduction Wetland.

The named contractor may purchase building materials used in the contract, exempt from sales tax. This exemption does NOT apply to materials, equipment and supplies consumed by the contractor or subcontractor.

Designated Exempt Entity Authorized Agent ._____________________________________ Date: _____________

Authorization Letter From Division of Soil Conservation and Water Quality - Agriculture and Land Stewardship

Pursuant to Iowa Code Sections: 422.42 (16) & (17), and 422.47 (5), you are authorized to purchase construction materials tax free for the contract specified above.

The exemption certificate (or a copy of the certificate) may be provided to the suppliers of your construction materials and will authorize them to sell you the materials exempt from Iowa sales tax and any applicable local option sales tax and school infrastructure local option sales tax. Complete information on qualifying materials can be found at www.state.ia.us/tax, the Department of Revenue (IDR) website.

It is your responsibility to have records identifying the materials purchased and verifying they were used on this contract. Any materials purchased tax-free and not used on the construction project are subject to sales and applicable local option taxes. Should this occur, the tax must be paid directly by you to IDR in the same calendar quarter the project is completed. E-mail the department at: idrf@idrf.state.ia.us if you have questions on this requirement.

Contractors should be aware that use of the certificate to claim exemption from tax for items not used on this project or that do not qualify for exemption could result in civil or criminal penalties.

31-013 (12/10/02)

END OF DOCUMENT QQ

File details come from the government source that posted it. Updated .