Appendix D - Schedule 2026-12 FC.pdf
PDF 865 KB Posted
- Solicitation number
- 2140553
- Issued by
- New York
About this file
This file is a detailed project schedule for the Franklin Courts Infrastructure Improvements Project in the Village of Tarrytown, New York, prepared under Contract No. 2026-12. The project encompasses infrastructure improvements for the redevelopment of Franklin Courts, including rough grading, excavation, soil management, utility installation (stormwater, sanitary, and water mains), segmental retaining wall installation, site electrical trenching and conduit work, light pole and EV charger installation, asphalt striping, landscape plantings, and topsoil placement. The construction schedule spans 622 days from November 17, 2026, through April 4, 2029, and is divided into two distinct phases: Phase 1 runs for 424 days from November 18, 2026, to July 3, 2028, and includes demolition of Buildings 1, 2, 3, 4, 14, and associated structures, construction of new Buildings 1 and 2, site work, utility infrastructure installation, and final street construction. Phase 2 spans 190 days from June 28, 2028, to March 20, 2029, and includes demolition of Buildings 5 through 14, construction of Buildings 3, 4, and a clubhouse, utility completion, and site finalization. Preconstruction and administration activities are scheduled for 755 days beginning May 12, 2026.
The schedule is resource-allocated between HIF (likely the Housing Improvement Fund or prime contractor) and GC (General Contractor) entities. Phase 1 includes critical milestones such as DigSafe markout and survey, environmental abatement and building demolition, removal of approximately 22 underground storage tanks, installation of new municipal storm sewer lines, water and sewer main installation with associated fire hydrants, gabion and segmented retaining wall construction, and modular building construction for new residential structures. Phase 2 activities include similar site preparation, utility infrastructure completion, and construction of additional residential buildings and community facilities. The project note indicates that the contractor is responsible for coordinating contract work with other contractors on site. No pricing information, set-asides, or funding sources are specified in this schedule document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Resource Names
Duration Start Finish Predecessors
1 Construction Milestone Summary 622 days Tue 11/17/26 Wed 4/4/29
2 Phase 1 Commencement HIF/GC 0 days Tue 11/17/26 Tue 11/17/26
3 Phase 1 Completion HIF/GC 1 day Tue 6/27/28 Tue 6/27/28 45,43,24,25
4 Phase 2 Commencement HIF/GC 0 days Tue 6/27/28 Tue 6/27/28 3
5 Phase 2 Completion HIF/GC 1 day Wed 4/4/29 Wed 4/4/29 31,32
6 Preconstruction / Administration 755 days Tue 5/12/26 Tue 4/3/29
35 Construction 610 days Wed 11/18/26 Tue 3/20/29
36 Phase 1 424 days Wed 11/18/26 Mon 7/3/28
37 Initial Site Work, Existing Conditions Work 70.5 days Wed 11/18/26 Wed 2/24/27
38 DigSafe Markout and Survey Stake Property Lines and Limits of Disturbance GC 5 days Wed 11/18/26 Tue 11/24/26 19
39 Install Silt Fence and Erosion Control GC 5 days Wed 11/25/26 Tue 12/1/26 38
40 Tree Removal GC 3 wks Wed 12/2/26 Tue 12/22/26 39
41 Remove Approximately (22) UST's (Buildings 1, 2, 3, 4, and 14) ? 10 days Wed 11/25/26 Tue 12/8/26 38
42 Abatement in Buildings 1, 2, 3, 4, 14, and CB GC 20 days Wed 12/9/26 Tue 1/5/27 41
43 Demolish Buildings 1, 2, 3, 4, 14, CB, and Playground GC 20 days Wed 1/6/27 Tue 2/2/27 42
44 New DMH1 - 2 GC 1.5 wks Wed 12/23/26 Fri 1/1/27 40
45 Construct Access and Temporary Parking along Western Property Line GC 15 days Fri 1/1/27 Fri 1/22/27 40,44
46 HIF Mobilization / Mark-Out - Surveying HIF 2 wks Tue 12/29/26 Mon 1/11/27
47 Install New Municipal Storm Sewer Line from Riverview to NW Corner DMH 2 - 7 HIF 15 days Wed 1/20/27 Tue 2/9/27 38FS+2 mons,46
48 Install Temporary Diversion Swale and Check Dams HIF 5 days Wed 2/10/27 Tue 2/16/27 47
49 Clearing and Grubbing GC 15 days Fri 1/22/27 Fri 2/12/27 45
50 Remove Pavement and Install Stabilized Entrance HIF 3 days Fri 1/22/27 Wed 1/27/27 49SS
51 Removal of Pavement, Curbing, Sidewalks, and Utilities HIF 20 days Wed 1/27/27 Wed 2/24/27 50
52 Strip Topsoil and Stockpile HIF 5 days Wed 2/10/27 Wed 2/17/27 51SS+10 days
53 Site Work 358.5 days Wed 2/17/27 Mon 7/3/28
54 Earthwork and Rough Grading HIF 10 days Wed 2/17/27 Wed 3/3/27 52
55 Install Gabion Retaining Walls HIF 5 days Wed 3/3/27 Wed 3/10/27 54
56 Rough Grading for Proposed Road HIF 20 days Wed 3/10/27 Wed 4/7/27 55SS+5 days
57 Install Storm Lines Along New Roadway HIF 10 days Wed 4/7/27 Wed 4/21/27 56
58 Install Water Main from Franklin Street to Just South of Building 1 + Fire Hydrants HIF 5 days Wed 4/7/27 Wed 4/14/27 56
59 Install Water Main from Franklin Street to Just South of Building 2 + Fire Hydrants HIF 5 days Wed 4/14/27 Wed 4/21/27 58
60 Install Proposed Sewer Line from SMH 5 to SMH 2, Install Temporary Sewer To Existing Main HIF 10 days Wed 4/7/27 Wed 4/21/27 56
61 Install Water + Sewer Lines between Main and Building 1 HIF 5 days Wed 4/21/27 Wed 4/28/27 59
62 Install Water + Sewer Lines between Main and Building 2 HIF 5 days Wed 4/21/27 Wed 4/28/27 60
63 Install Light Pole Foundations and U/G Electric along Eastern Side of Road HIF 5 days Wed 4/21/27 Wed 4/28/27 59,57,58,60
64 EV Charger Trenching + Conduit HIF 2 wks Wed 4/21/27 Wed 5/5/27 63SS
65 Segmented Retaining Wall Work HIF 60 days Wed 4/7/27 Wed 6/30/27 56
66 Respread Topsoil, Seed, and Mulch Lawn + Landscape Areas within Phase 1 HIF 1 wk Tue 6/27/28 Mon 7/3/28 88
67 New Buildings (1 and 2) 299.5 days Wed 5/5/27 Tue 6/27/28
68 Building 1 Foundation + Concrete Retaining Wall Work HIF 20 days Wed 5/5/27 Wed 6/2/27 65SS+20 days,43
69 Building 1 - SSDS / Vapor Barrier Install HIF 1 wk Wed 6/2/27 Wed 6/9/27 68
70 Building 1 - SOG GC 1 wk Wed 6/9/27 Wed 6/16/27 69
71 Building 1 - Podium Concrete GC 20 days Wed 6/16/27 Wed 7/14/27 68,70
72 Building 1 - Remove Reshores GC 30 days Wed 7/14/27 Wed 8/25/27 71
73 Building 1 Masonry Work HIF 10 days Wed 8/25/27 Wed 9/8/27 72
74 Building 1 Set Modules GC 15 days Wed 9/8/27 Wed 9/29/27 68,9,73
75 Building 1 Construction GC 80 days Wed 9/29/27 Wed 1/19/28 74
76 Building 1 - Fire Protection HIF 2 wks Wed 10/27/27 Wed 11/10/27 75SS+4 wks
77 Building 1 - Split Face Block and WT HIF 2 wks Wed 9/29/27 Wed 10/13/27 74
78 Building 2 - Foundation + Concrete Retaining Wall Work HIF 20 days Wed 6/2/27 Wed 6/30/27 68
79 Building 2 - SSDS / Vapor Barrier Install HIF 1 wk Wed 6/30/27 Wed 7/7/27 78
80 Building 2 - SOG GC 1 wk Wed 7/7/27 Wed 7/14/27 79
81 Building 2 - Podium Concrete GC 20 days Wed 7/14/27 Wed 8/11/27 80
82 Building 2 - Remove Reshores GC 30 days Wed 8/11/27 Wed 9/22/27 81
83 Building 2 Masonry Work HIF 10 days Wed 9/22/27 Wed 10/6/27 82
84 Building 2 Set Modules GC 15 days Tue 2/1/28 Mon 2/21/28 78,83,9
85 Building 2 Construction GC 80 days Tue 2/22/28 Mon 6/12/28 84
86 Building 2 - Fire Protection HIF 2 wks Tue 3/21/28 Mon 4/3/28 85SS+4 wks
87 Building 2 - Split Face Block and WT HIF 2 wks Tue 2/22/28 Mon 3/6/28 84
88 Final Street Construction / Asphalt Placement GC 2 wks Tue 6/13/28 Mon 6/26/28 85
Construction Milestone Summary 11/17 Phase 1 Commencement
6/27 6/27 Phase 1 Completion 6/27 Phase 2 Commencement
4/4 4/4 Phase 2 Completion Preconstruction / Administration
Construction Phase 1
Initial Site Work, Existing Conditions Work 11/18 11/24 DigSafe Markout and Survey Stake Property Lines and Limits of Disturbance 11/25 12/1 Install Silt Fence and Erosion Control
12/2 12/22 Tree Removal 11/25 12/8 Remove Approximately (22) UST's (Buildings 1, 2, 3, 4, and 14)
12/9 1/5 Abatement in Buildings 1, 2, 3, 4, 14, and CB 1/6 2/2 Demolish Buildings 1, 2, 3, 4, 14, CB, and Playground
12/23 1/1 New DMH1 - 2 1/1 1/22 Construct Access and Temporary Parking along Western Property Line
12/29 1/11 HIF Mobilization / Mark-Out - Surveying 1/20 2/9 Install New Municipal Storm Sewer Line from Riverview to NW Corner DMH 2 - 7
2/10 2/16 Install Temporary Diversion Swale and Check Dams 1/22 2/12 Clearing and Grubbing 1/22 1/27 Remove Pavement and Install Stabilized Entrance 1/27 2/24 Removal of Pavement, Curbing, Sidewalks, and Utilities
2/10 2/17 Strip Topsoil and Stockpile Site Work
2/17 3/3 Earthwork and Rough Grading 3/3 3/10 Install Gabion Retaining Walls 3/10 4/7 Rough Grading for Proposed Road
4/7 4/21 Install Storm Lines Along New Roadway 4/7 4/14 Install Water Main from Franklin Street to Just South of Building 1 + Fire Hydrants 4/14 4/21 Install Water Main from Franklin Street to Just South of Building 2 + Fire Hydrants 4/7 4/21 Install Proposed Sewer Line from SMH 5 to SMH 2, Install Temporary Sewer To Existing Main 4/21 4/28 Install Water + Sewer Lines between Main and Building 1 4/21 4/28 Install Water + Sewer Lines between Main and Building 2 4/21 4/28 Install Light Pole Foundations and U/G Electric along Eastern Side of Road 4/21 5/5 EV Charger Trenching + Conduit 4/7 6/30 Segmented Retaining Wall Work
6/27 7/3 Respread Topsoil, Seed, and Mulch Lawn + Landscape Areas within Phase 1 New Buildings (1 and 2)
5/5 6/2 Building 1 Foundation + Concrete Retaining Wall Work 6/2 6/9 Building 1 - SSDS / Vapor Barrier Install 6/9 6/16 Building 1 - SOG 6/16 7/14 Building 1 - Podium Concrete
7/14 8/25 Building 1 - Remove Reshores 8/25 9/8 Building 1 Masonry Work
9/8 9/29 Building 1 Set Modules 9/29 1/19 Building 1 Construction
10/27 11/10 Building 1 - Fire Protection 9/29 10/13 Building 1 - Split Face Block and WT
6/2 6/30 Building 2 - Foundation + Concrete Retaining Wall Work 6/30 7/7 Building 2 - SSDS / Vapor Barrier Install
7/7 7/14 Building 2 - SOG 7/14 8/11 Building 2 - Podium Concrete
8/11 9/22 Building 2 - Remove Reshores 9/22 10/6 Building 2 Masonry Work
2/1 2/21 Building 2 Set Modules 2/22 6/12 Building 2 Construction
3/21 4/3 Building 2 - Fire Protection 2/22 3/6 Building 2 - Split Face Block and WT
6/13 6/26 Final Street Construction / Asphalt Placement
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2026 2027 2028 2029 2030
FRANKLIN COURTS INFRASTRUCTURE IMPROVEMENTS PROJECT SCHEDULE FRANKLIN COURTS
Vilage of Tarrytown, NY
Page 1 Thu 11/5/26
CONTRACT NO. 2026-12
NOTE: CONTRACTOR IS RESPONSIBLE FOR COORDINATING CONTRACT WORK WITH OTHER CONTRACTORS.
Duration Start Finish Predecessors
89 Street Line Striping HIF 1 day Tue 6/27/28 Tue 6/27/28 88
90 Phase 2 190 days Wed 6/28/28 Tue 3/20/29
91 Initial Site Work / Existing Conditions Work 80 days Wed 6/28/28 Tue 10/17/28
92 DigSafe Markout and Survey Stake Property Lines and Limits of Disturbance HIF/GC 5 days Wed 6/28/28 Tue 7/4/28 4
93 Install Silt Fence and Erosion Control GC 5 days Wed 7/5/28 Tue 7/11/28 92
94 Remove Temporary Gravel Access Road and Construct Emergency Road GC 5 days Wed 7/12/28 Tue 7/18/28 93
95 Clearing and Grubbing GC 5 days Wed 7/19/28 Tue 7/25/28 94
96 Removal of Pavement, Curbing, Sidewalks, and Utilities GC 5 days Wed 7/26/28 Tue 8/1/28 95
97 Strip Topsoil and Stockpile GC 5 days Wed 8/2/28 Tue 8/8/28 96
98 Abatement in Buildings 5, 6, 7, 8, and 9 GC 20 days Wed 7/26/28 Tue 8/22/28 95
99 Demolish in Buildings 5, 6, 7, 8, and 9 GC 20 days Wed 8/23/28 Tue 9/19/28 98
100 Abatement in Buildings 10, 11, 12, 13, and 14 GC 20 days Wed 8/23/28 Tue 9/19/28 98
101 Demolish Buildings 10, 11, 12, 13, and 14 GC 20 days Wed 9/20/28 Tue 10/17/28 99,100
102 Site Work 120 days Wed 8/9/28 Tue 1/23/29
103 Construct Bio-Retention Filter and Associated Structures GC 5 days Wed 8/9/28 Tue 8/15/28 97
104 Earthwork and Rough Grading GC 30 days Wed 8/16/28 Tue 9/26/28 103
105 Complete Installation and Testing of the Sewer Mains and Manholes from SMH2 to SMH1 GC 10 days Wed 9/27/28 Tue 10/10/28 104
106 Utility Work HIF 15 days Wed 9/27/28 Tue 10/17/28 104
107 Install Light Pole Foundations and U/G Electric along Eastern Side of Road HIF 5 days Wed 10/18/28 Tue 10/24/28 106
108 Complete Installation and Testing of Water Main Loop GC 10 days Wed 10/18/28 Tue 10/31/28 106
109 Install Water Lines between Main and Building 3 GC 10 days Wed 12/6/28 Tue 12/19/28 120
110 Install Sewer Lines between Main and Building 3 GC 10 days Wed 12/6/28 Tue 12/19/28 120
111 Remove Existing Municipal Storm Line + Restore Grade HIF 2 wks Wed 10/18/28 Tue 10/31/28 101
112 Completion of the Cul-de-Sac HIF/GC 20 days Wed 12/20/28 Tue 1/16/29 106,109,110
113 Install Water Lines between Main and Building 4 GC 10 days Wed 12/27/28 Tue 1/9/29 123
114 Install Sewer Lines between Main and Building 4 GC 10 days Wed 12/27/28 Tue 1/9/29 123
115 Install Water Lines between Main and Clubhouse GC 5 days Wed 1/17/29 Tue 1/23/29 126
116 Install Sewer Lines between Main and Clubhouse GC 5 days Wed 1/17/29 Tue 1/23/29 126
117 Respread Topsoil, Seed, and Mulch Lawn Areas within Phase 2 GC 10 days Wed 1/10/29 Tue 1/23/29 114
118 New Buildings (3 and 4, Clubhouse) 105 days Wed 10/25/28 Tue 3/20/29
119 Building 3 Foundation GC 20 days Wed 10/25/28 Tue 11/21/28 107,99
120 Building 3 Set Modules GC 10 days Wed 11/22/28 Tue 12/5/28 119
121 Building 3 Construction GC 60 days Wed 12/6/28 Tue 2/27/29 120
122 Building 4 Foundation GC 20 days Wed 11/15/28 Tue 12/12/28 119SS+15 days,101
123 Building 4 Set Modules GC 10 days Wed 12/13/28 Tue 12/26/28 122
124 Building 4 Construction GC 60 days Wed 12/27/28 Tue 3/20/29 123
125 Clubhouse Foundation GC 10 days Wed 12/27/28 Tue 1/9/29 65FS-200 days,123
126 Clubhouse Set Modules GC 5 days Wed 1/10/29 Tue 1/16/29 125
127 Clubhouse Construction GC 40 days Wed 1/17/29 Tue 3/13/29 126
6/27 6/27 Street Line Striping Phase 2
Initial Site Work / Existing Conditions Work 6/28 7/4 DigSafe Markout and Survey Stake Property Lines and Limits of Disturbance
7/5 7/11 Install Silt Fence and Erosion Control 7/12 7/18 Remove Temporary Gravel Access Road and Construct Emergency Road 7/19 7/25 Clearing and Grubbing 7/26 8/1 Removal of Pavement, Curbing, Sidewalks, and Utilities
8/2 8/8 Strip Topsoil and Stockpile 7/26 8/22 Abatement in Buildings 5, 6, 7, 8, and 9
8/23 9/19 Demolish in Buildings 5, 6, 7, 8, and 9 8/23 9/19 Abatement in Buildings 10, 11, 12, 13, and 14
9/20 10/17 Demolish Buildings 10, 11, 12, 13, and 14 Site Work
8/9 8/15 Construct Bio-Retention Filter and Associated Structures 8/16 9/26 Earthwork and Rough Grading
9/27 10/10 Complete Installation and Testing of the Sewer Mains and Manholes from SMH2 to SMH1 9/27 10/17 Utility Work 10/18 10/24 Install Light Pole Foundations and U/G Electric along Eastern Side of Road 10/18 10/31 Complete Installation and Testing of Water Main Loop
12/6 12/19 Install Water Lines between Main and Building 3 12/6 12/19 Install Sewer Lines between Main and Building 3
10/18 10/31 Remove Existing Municipal Storm Line + Restore Grade 12/20 1/16 Completion of the Cul-de-Sac 12/27 1/9 Install Water Lines between Main and Building 4 12/27 1/9 Install Sewer Lines between Main and Building 4
1/17 1/23 Install Water Lines between Main and Clubhouse 1/17 1/23 Install Sewer Lines between Main and Clubhouse
1/10 1/23 Respread Topsoil, Seed, and Mulch Lawn Areas within Phase 2 New Buildings (3 and 4, Clubhouse)
10/25 11/21 Building 3 Foundation 11/22 12/5 Building 3 Set Modules
12/6 2/27 Building 3 Construction 11/15 12/12 Building 4 Foundation
12/13 12/26 Building 4 Set Modules 12/27 3/20 Building 4 Construction 12/27 1/9 Clubhouse Foundation
1/10 1/16 Clubhouse Set Modules 1/17 3/13 Clubhouse Construction
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2026 2027 2028 2029 2030
FRANKLIN COURTS INFRASTRUCTURE IMPROVEMENTS PROJECT SCHEDULE FRANKLIN COURTS
Vilage of Tarrytown, NY
Page 2 Thu 11/5/26
Duration Start Finish Predecessors
1 Construction Milestone Summary 622 days Tue 11/17/26 Wed 4/4/29
2 Phase 1 Commencement HIF/GC 0 days Tue 11/17/26 Tue 11/17/26
3 Phase 1 Completion HIF/GC 1 day Tue 6/27/28 Tue 6/27/28 45,43,24,25
4 Phase 2 Commencement HIF/GC 0 days Tue 6/27/28 Tue 6/27/28 3
5 Phase 2 Completion HIF/GC 1 day Wed 4/4/29 Wed 4/4/29 31,32
6 Preconstruction / Administration 755 days Tue 5/12/26 Tue 4/3/29
35 Construction 610 days Wed 11/18/26 Tue 3/20/29
36 Phase 1 424 days Wed 11/18/26 Mon 7/3/28
37 Initial Site Work, Existing Conditions Work 70.5 days Wed 11/18/26 Wed 2/24/27
38 DigSafe Markout and Survey Stake Property Lines and Limits of Disturbance GC 5 days Wed 11/18/26 Tue 11/24/26 19
39 Install Silt Fence and Erosion Control GC 5 days Wed 11/25/26 Tue 12/1/26 38
40 Tree Removal GC 3 wks Wed 12/2/26 Tue 12/22/26 39
41 Remove Approximately (22) UST's (Buildings 1, 2, 3, 4, and 14) ? 10 days Wed 11/25/26 Tue 12/8/26 38
42 Abatement in Buildings 1, 2, 3, 4, 14, and CB GC 20 days Wed 12/9/26 Tue 1/5/27 41
43 Demolish Buildings 1, 2, 3, 4, 14, CB, and Playground GC 20 days Wed 1/6/27 Tue 2/2/27 42
44 New DMH1 - 2 GC 1.5 wks Wed 12/23/26 Fri 1/1/27 40
45 Construct Access and Temporary Parking along Western Property Line GC 15 days Fri 1/1/27 Fri 1/22/27 40,44
46 HIF Mobilization / Mark-Out - Surveying HIF 2 wks Tue 12/29/26 Mon 1/11/27
47 Install New Municipal Storm Sewer Line from Riverview to NW Corner DMH 2 - 7 HIF 15 days Wed 1/20/27 Tue 2/9/27 38FS+2 mons,46
48 Install Temporary Diversion Swale and Check Dams HIF 5 days Wed 2/10/27 Tue 2/16/27 47
49 Clearing and Grubbing GC 15 days Fri 1/22/27 Fri 2/12/27 45
50 Remove Pavement and Install Stabilized Entrance HIF 3 days Fri 1/22/27 Wed 1/27/27 49SS
51 Removal of Pavement, Curbing, Sidewalks, and Utilities HIF 20 days Wed 1/27/27 Wed 2/24/27 50
52 Strip Topsoil and Stockpile HIF 5 days Wed 2/10/27 Wed 2/17/27 51SS+10 days
53 Site Work 358.5 days Wed 2/17/27 Mon 7/3/28
54 Earthwork and Rough Grading HIF 10 days Wed 2/17/27 Wed 3/3/27 52
55 Install Gabion Retaining Walls HIF 5 days Wed 3/3/27 Wed 3/10/27 54
56 Rough Grading for Proposed Road HIF 20 days Wed 3/10/27 Wed 4/7/27 55SS+5 days
57 Install Storm Lines Along New Roadway HIF 10 days Wed 4/7/27 Wed 4/21/27 56
58 Install Water Main from Franklin Street to Just South of Building 1 + Fire Hydrants HIF 5 days Wed 4/7/27 Wed 4/14/27 56
59 Install Water Main from Franklin Street to Just South of Building 2 + Fire Hydrants HIF 5 days Wed 4/14/27 Wed 4/21/27 58
60 Install Proposed Sewer Line from SMH 5 to SMH 2, Install Temporary Sewer To Existing Main HIF 10 days Wed 4/7/27 Wed 4/21/27 56
61 Install Water + Sewer Lines between Main and Building 1 HIF 5 days Wed 4/21/27 Wed 4/28/27 59
62 Install Water + Sewer Lines between Main and Building 2 HIF 5 days Wed 4/21/27 Wed 4/28/27 60
63 Install Light Pole Foundations and U/G Electric along Eastern Side of Road HIF 5 days Wed 4/21/27 Wed 4/28/27 59,57,58,60
64 EV Charger Trenching + Conduit HIF 2 wks Wed 4/21/27 Wed 5/5/27 63SS
65 Segmented Retaining Wall Work HIF 60 days Wed 4/7/27 Wed 6/30/27 56
66 Respread Topsoil, Seed, and Mulch Lawn + Landscape Areas within Phase 1 HIF 1 wk Tue 6/27/28 Mon 7/3/28 88
67 New Buildings (1 and 2) 299.5 days Wed 5/5/27 Tue 6/27/28
68 Building 1 Foundation + Concrete Retaining Wall Work HIF 20 days Wed 5/5/27 Wed 6/2/27 65SS+20 days,43
69 Building 1 - SSDS / Vapor Barrier Install HIF 1 wk Wed 6/2/27 Wed 6/9/27 68
70 Building 1 - SOG GC 1 wk Wed 6/9/27 Wed 6/16/27 69
71 Building 1 - Podium Concrete GC 20 days Wed 6/16/27 Wed 7/14/27 68,70
72 Building 1 - Remove Reshores GC 30 days Wed 7/14/27 Wed 8/25/27 71
73 Building 1 Masonry Work HIF 10 days Wed 8/25/27 Wed 9/8/27 72
74 Building 1 Set Modules GC 15 days Wed 9/8/27 Wed 9/29/27 68,9,73
75 Building 1 Construction GC 80 days Wed 9/29/27 Wed 1/19/28 74
76 Building 1 - Fire Protection HIF 2 wks Wed 10/27/27 Wed 11/10/27 75SS+4 wks
77 Building 1 - Split Face Block and WT HIF 2 wks Wed 9/29/27 Wed 10/13/27 74
78 Building 2 - Foundation + Concrete Retaining Wall Work HIF 20 days Wed 6/2/27 Wed 6/30/27 68
79 Building 2 - SSDS / Vapor Barrier Install HIF 1 wk Wed 6/30/27 Wed 7/7/27 78
80 Building 2 - SOG GC 1 wk Wed 7/7/27 Wed 7/14/27 79
81 Building 2 - Podium Concrete GC 20 days Wed 7/14/27 Wed 8/11/27 80
82 Building 2 - Remove Reshores GC 30 days Wed 8/11/27 Wed 9/22/27 81
83 Building 2 Masonry Work HIF 10 days Wed 9/22/27 Wed 10/6/27 82
84 Building 2 Set Modules GC 15 days Tue 2/1/28 Mon 2/21/28 78,83,9
85 Building 2 Construction GC 80 days Tue 2/22/28 Mon 6/12/28 84
86 Building 2 - Fire Protection HIF 2 wks Tue 3/21/28 Mon 4/3/28 85SS+4 wks
87 Building 2 - Split Face Block and WT HIF 2 wks Tue 2/22/28 Mon 3/6/28 84
88 Final Street Construction / Asphalt Placement GC 2 wks Tue 6/13/28 Mon 6/26/28 85
Construction Milestone Summary 11/17 Phase 1 Commencement
6/27 6/27 Phase 1 Completion 6/27 Phase 2 Commencement
4/4 4/4 Phase 2 Completion Preconstruction / Administration
Construction Phase 1
Initial Site Work, Existing Conditions Work 11/18 11/24 DigSafe Markout and Survey Stake Property Lines and Limits of Disturbance 11/25 12/1 Install Silt Fence and Erosion Control
12/2 12/22 Tree Removal 11/25 12/8 Remove Approximately (22) UST's (Buildings 1, 2, 3, 4, and 14)
12/9 1/5 Abatement in Buildings 1, 2, 3, 4, 14, and CB 1/6 2/2 Demolish Buildings 1, 2, 3, 4, 14, CB, and Playground
12/23 1/1 New DMH1 - 2 1/1 1/22 Construct Access and Temporary Parking along Western Property Line
12/29 1/11 HIF Mobilization / Mark-Out - Surveying 1/20 2/9 Install New Municipal Storm Sewer Line from Riverview to NW Corner DMH 2 - 7
2/10 2/16 Install Temporary Diversion Swale and Check Dams 1/22 2/12 Clearing and Grubbing 1/22 1/27 Remove Pavement and Install Stabilized Entrance 1/27 2/24 Removal of Pavement, Curbing, Sidewalks, and Utilities
2/10 2/17 Strip Topsoil and Stockpile Site Work
2/17 3/3 Earthwork and Rough Grading 3/3 3/10 Install Gabion Retaining Walls 3/10 4/7 Rough Grading for Proposed Road
4/7 4/21 Install Storm Lines Along New Roadway 4/7 4/14 Install Water Main from Franklin Street to Just South of Building 1 + Fire Hydrants 4/14 4/21 Install Water Main from Franklin Street to Just South of Building 2 + Fire Hydrants 4/7 4/21 Install Proposed Sewer Line from SMH 5 to SMH 2, Install Temporary Sewer To Existing Main 4/21 4/28 Install Water + Sewer Lines between Main and Building 1 4/21 4/28 Install Water + Sewer Lines between Main and Building 2 4/21 4/28 Install Light Pole Foundations and U/G Electric along Eastern Side of Road 4/21 5/5 EV Charger Trenching + Conduit 4/7 6/30 Segmented Retaining Wall Work
6/27 7/3 Respread Topsoil, Seed, and Mulch Lawn + Landscape Areas within Phase 1 New Buildings (1 and 2)
5/5 6/2 Building 1 Foundation + Concrete Retaining Wall Work 6/2 6/9 Building 1 - SSDS / Vapor Barrier Install 6/9 6/16 Building 1 - SOG 6/16 7/14 Building 1 - Podium Concrete
7/14 8/25 Building 1 - Remove Reshores 8/25 9/8 Building 1 Masonry Work
9/8 9/29 Building 1 Set Modules 9/29 1/19 Building 1 Construction
10/27 11/10 Building 1 - Fire Protection 9/29 10/13 Building 1 - Split Face Block and WT
6/2 6/30 Building 2 - Foundation + Concrete Retaining Wall Work 6/30 7/7 Building 2 - SSDS / Vapor Barrier Install
7/7 7/14 Building 2 - SOG 7/14 8/11 Building 2 - Podium Concrete
8/11 9/22 Building 2 - Remove Reshores 9/22 10/6 Building 2 Masonry Work
2/1 2/21 Building 2 Set Modules 2/22 6/12 Building 2 Construction
3/21 4/3 Building 2 - Fire Protection 2/22 3/6 Building 2 - Split Face Block and WT
6/13 6/26 Final Street Construction / Asphalt Placement
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2026 2027 2028 2029 2030
FRANKLIN COURTS INFRASTRUCTURE IMPROVEMENTS PROJECT SCHEDULE FRANKLIN COURTS
Vilage of Tarrytown, NY
Page 1 Thu 11/5/26
Duration Start Finish Predecessors
89 Street Line Striping HIF 1 day Tue 6/27/28 Tue 6/27/28 88
90 Phase 2 190 days Wed 6/28/28 Tue 3/20/29
91 Initial Site Work / Existing Conditions Work 80 days Wed 6/28/28 Tue 10/17/28
92 DigSafe Markout and Survey Stake Property Lines and Limits of Disturbance HIF/GC 5 days Wed 6/28/28 Tue 7/4/28 4
93 Install Silt Fence and Erosion Control GC 5 days Wed 7/5/28 Tue 7/11/28 92
94 Remove Temporary Gravel Access Road and Construct Emergency Road GC 5 days Wed 7/12/28 Tue 7/18/28 93
95 Clearing and Grubbing GC 5 days Wed 7/19/28 Tue 7/25/28 94
96 Removal of Pavement, Curbing, Sidewalks, and Utilities GC 5 days Wed 7/26/28 Tue 8/1/28 95
97 Strip Topsoil and Stockpile GC 5 days Wed 8/2/28 Tue 8/8/28 96
98 Abatement in Buildings 5, 6, 7, 8, and 9 GC 20 days Wed 7/26/28 Tue 8/22/28 95
99 Demolish in Buildings 5, 6, 7, 8, and 9 GC 20 days Wed 8/23/28 Tue 9/19/28 98
100 Abatement in Buildings 10, 11, 12, 13, and 14 GC 20 days Wed 8/23/28 Tue 9/19/28 98
101 Demolish Buildings 10, 11, 12, 13, and 14 GC 20 days Wed 9/20/28 Tue 10/17/28 99,100
102 Site Work 120 days Wed 8/9/28 Tue 1/23/29
103 Construct Bio-Retention Filter and Associated Structures GC 5 days Wed 8/9/28 Tue 8/15/28 97
104 Earthwork and Rough Grading GC 30 days Wed 8/16/28 Tue 9/26/28 103
105 Complete Installation and Testing of the Sewer Mains and Manholes from SMH2 to SMH1 GC 10 days Wed 9/27/28 Tue 10/10/28 104
106 Utility Work HIF 15 days Wed 9/27/28 Tue 10/17/28 104
107 Install Light Pole Foundations and U/G Electric along Eastern Side of Road HIF 5 days Wed 10/18/28 Tue 10/24/28 106
108 Complete Installation and Testing of Water Main Loop GC 10 days Wed 10/18/28 Tue 10/31/28 106
109 Install Water Lines between Main and Building 3 GC 10 days Wed 12/6/28 Tue 12/19/28 120
110 Install Sewer Lines between Main and Building 3 GC 10 days Wed 12/6/28 Tue 12/19/28 120
111 Remove Existing Municipal Storm Line + Restore Grade HIF 2 wks Wed 10/18/28 Tue 10/31/28 101
112 Completion of the Cul-de-Sac HIF/GC 20 days Wed 12/20/28 Tue 1/16/29 106,109,110
113 Install Water Lines between Main and Building 4 GC 10 days Wed 12/27/28 Tue 1/9/29 123
114 Install Sewer Lines between Main and Building 4 GC 10 days Wed 12/27/28 Tue 1/9/29 123
115 Install Water Lines between Main and Clubhouse GC 5 days Wed 1/17/29 Tue 1/23/29 126
116 Install Sewer Lines between Main and Clubhouse GC 5 days Wed 1/17/29 Tue 1/23/29 126
117 Respread Topsoil, Seed, and Mulch Lawn Areas within Phase 2 GC 10 days Wed 1/10/29 Tue 1/23/29 114
118 New Buildings (3 and 4, Clubhouse) 105 days Wed 10/25/28 Tue 3/20/29
119 Building 3 Foundation GC 20 days Wed 10/25/28 Tue 11/21/28 107,99
120 Building 3 Set Modules GC 10 days Wed 11/22/28 Tue 12/5/28 119
121 Building 3 Construction GC 60 days Wed 12/6/28 Tue 2/27/29 120
122 Building 4 Foundation GC 20 days Wed 11/15/28 Tue 12/12/28 119SS+15 days,101
123 Building 4 Set Modules GC 10 days Wed 12/13/28 Tue 12/26/28 122
124 Building 4 Construction GC 60 days Wed 12/27/28 Tue 3/20/29 123
125 Clubhouse Foundation GC 10 days Wed 12/27/28 Tue 1/9/29 65FS-200 days,123
126 Clubhouse Set Modules GC 5 days Wed 1/10/29 Tue 1/16/29 125
127 Clubhouse Construction GC 40 days Wed 1/17/29 Tue 3/13/29 126
6/27 6/27 Street Line Striping Phase 2
Initial Site Work / Existing Conditions Work 6/28 7/4 DigSafe Markout and Survey Stake Property Lines and Limits of Disturbance
7/5 7/11 Install Silt Fence and Erosion Control 7/12 7/18 Remove Temporary Gravel Access Road and Construct Emergency Road 7/19 7/25 Clearing and Grubbing 7/26 8/1 Removal of Pavement, Curbing, Sidewalks, and Utilities
8/2 8/8 Strip Topsoil and Stockpile 7/26 8/22 Abatement in Buildings 5, 6, 7, 8, and 9
8/23 9/19 Demolish in Buildings 5, 6, 7, 8, and 9 8/23 9/19 Abatement in Buildings 10, 11, 12, 13, and 14
9/20 10/17 Demolish Buildings 10, 11, 12, 13, and 14 Site Work
8/9 8/15 Construct Bio-Retention Filter and Associated Structures 8/16 9/26 Earthwork and Rough Grading
9/27 10/10 Complete Installation and Testing of the Sewer Mains and Manholes from SMH2 to SMH1 9/27 10/17 Utility Work 10/18 10/24 Install Light Pole Foundations and U/G Electric along Eastern Side of Road 10/18 10/31 Complete Installation and Testing of Water Main Loop
12/6 12/19 Install Water Lines between Main and Building 3 12/6 12/19 Install Sewer Lines between Main and Building 3
10/18 10/31 Remove Existing Municipal Storm Line + Restore Grade 12/20 1/16 Completion of the Cul-de-Sac 12/27 1/9 Install Water Lines between Main and Building 4 12/27 1/9 Install Sewer Lines between Main and Building 4
1/17 1/23 Install Water Lines between Main and Clubhouse 1/17 1/23 Install Sewer Lines between Main and Clubhouse
1/10 1/23 Respread Topsoil, Seed, and Mulch Lawn Areas within Phase 2 New Buildings (3 and 4, Clubhouse)
10/25 11/21 Building 3 Foundation 11/22 12/5 Building 3 Set Modules
12/6 2/27 Building 3 Construction 11/15 12/12 Building 4 Foundation
12/13 12/26 Building 4 Set Modules 12/27 3/20 Building 4 Construction 12/27 1/9 Clubhouse Foundation
1/10 1/16 Clubhouse Set Modules 1/17 3/13 Clubhouse Construction
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2026 2027 2028 2029 2030
FRANKLIN COURTS INFRASTRUCTURE IMPROVEMENTS PROJECT SCHEDULE FRANKLIN COURTS
Vilage of Tarrytown, NY
Page 2 Thu 11/5/26