About this file
This is a Direct Labor Burden Calculation form issued by the State of Colorado Office of the State Architect State Buildings Program for Metropolitan State University of Denver's CAVEA Lighting project (26PR05). The form requires contractors and major subcontractors to submit a labor burden calculation sheet prior to execution of the construction agreement. The document outlines that one calculation sheet must be provided per contractor and for each subcontractor, with major subcontractors defined as electricians, plumbers, mechanical contractors, excavators, millwork, concrete, and block layers. The labor burden percentages established through this form will be incorporated into the contract as part of Exhibit A and utilized in the calculation of any future Change Order Proposals per SC-6.312 Line 2 for contractors and Line 10 for subcontractors.
The labor burden calculation requires contractors to itemize the percentage composition of total labor overhead, including payroll taxes, pension costs, health insurance, dental insurance, life insurance, and other specified benefits paid to employees on the contractor's payroll. The form includes fields for the contractor or subcontractor name and a line for the total labor burden percentage, which must be mutually agreed upon by both the contractor and the Principal Representative. The State reserves the right to require backup confirmation of all information included in the calculation. This form, designated as State Form SBP-6.18, was issued in August 2023.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAM
DIRECT LABOR BURDEN CALCULATION
| Institution/Agency: |
| Metropolitan State University of Denver |
| Project No./Name: |
| 26PR05 / CAVEA Lighting |
This form is required to be submitted for review prior to execution of a construction agreement.
List items below by the percentage of what makes up the total labor overhead; Items include benefits that a contractor pays to employees on their payroll. Examples include taxes, pension cost, health and dental insurance etc. The Labor Burden percentage must be agreed to by both the contractor and Principal Representative and will be included in the contract as part of Exhibit A and will be used in the calculation of any future Change Order Proposals (SC-6.312) Line 2.
Major sub-contractors defined as electricians, plumbers, mechanical contractors, excavators, millwork, concrete, block layers etc. Please provide one (1) Labor Burden Calculation Sheet per contractor and for each sub-contractor. These labor burdens shall be used in the calculation of any future Change Order Proposals (SC-6.312) Line 10.
State reserves the right to require back-up confirmation of all information included in this calculation.
State Form SBP–6.18 Issued 8/2023 image1.jpg image2.emf
Microsoft_Excel_Worksheet.xlsx Sheet1
Contractor/Subcontractor Name:
Percent of Salary Paid
Payroll Taxes
Pension Costs
Health Insurance
Dental Insurance
Life Insurance
Other (Specify) Description: _________________________