Appendix B2_Unit Pricing (SBP-6.133).docx

DOCX document 37 KB Posted

Attached to
AHEC-26920-B - Abatement Central (Proj. A) & West (Proj. B)
Solicitation number
IFB1 GMAA 2026000154 2
Issued by
Denver County, Denver City, Colorado

About this file

This is a Unit Pricing Form from the State of Colorado Office of the State Architect, State Buildings Program, for the Auraria Higher Education Center's HVAC Infrastructure Replacement project (Project No. 2020-55P21). The project involves asbestos abatement work for two locations: the Central Classroom (Project A) and West Classroom (Project B). The form establishes unit pricing for seven specific work items that will be used to determine contract sum adjustments if changes to the work scope become necessary. The unit prices remain valid until the date of contract completion as established on the Notice to Proceed.

The seven unit pricing items cover non-friable asbestos containing window caulking (measured in linear feet), non-friable asbestos containing window glazing (linear feet), non-friable trace asbestos containing drywall systems (square feet), construction of secondary containment structures measuring 5' X 5' each (per unit), and labor costs for asbestos abatement workers, asbestos abatement supervisors, and project managers (all measured in hours). All unit prices are inclusive of the pro-rata share of materials, equipment, and disposal costs required to complete each work item. Overhead, profit, and bond costs will be calculated separately on a Change Order Proposal form (SC-6.312) and are not included in the unit prices. Bidders must complete the form by entering dollar amounts for each unit price and providing company name, signature, and date.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

UNIT PRICING FORM

Institution or Agency: Auraria Higher Education Center Project No./Project Name: 2020-55P21 / AHEC HVAC Infrastructure Replacement (Capital Renewal) – Asbestos Abatement for Central Classroom (Project A) and West Classroom (Project B)

INSTRUCTIONS:

The unit prices below shall be used to determine adjustment to the contract sum when changes in the work involving said items are deemed necessary.

Unit Prices shall apply until the date of contract completion established on the Notice to Proceed.

All unit prices shall include the pro-rata share of all costs of materials, equipment and disposal required to complete the work item. Overhead, profit and bond will be calculated on a Change Order Proposal (SC-6.312).

UNIT PRICING

Number
Description

Unit of Measure

Unit Price

U1
Non-friable asbestos containing window caulking
LF
$
U2
Non-friable asbestos containing window glazing
LF
$
U3
Non-friable trace asbestos containing drywall system

SF

U4
Construct one (1) 5’ X 5’ Secondary Containment
EA
$
U5
Asbestos Abatement Worker
HR
$
U6
Asbestos Abatement Supervisor
HR
$
U7
Project Manager
HR
$

THE BIDDER

BY_________________________________________________________________

Company Name

BY__________________________________________________________________

Signature Date

SBP-6.133

Rev 7/2025 image1.jpeg