Appendix B SC6.21 DBB A_2026_R2.pdf

PDF 367 KB Posted

Attached to
RRCC 27-03-IFB01C Nursing & Health Imaging Bldg GC Pre-qual
Solicitation number
IFB1 GJLA 2027000040 3
Issued by
Jefferson County, Colorado

About this file

This document is the State of Colorado Contractor's Design/Bid/Build (D/B/B) Agreement (Form SC-6.21), a standard contract template issued by the Office of the State Architect's State Buildings Program for use by Colorado state agencies and institutions of higher education. The agreement establishes the contractual framework between the State of Colorado and a contractor for the completion of a construction project, with the contractor responsible for performing all work required for complete execution of the project as described in the contract documents. The agreement requires the contractor to substantially complete the project within a specified number of calendar days from the Notice to Proceed and to achieve final completion from Substantial Completion to Final Acceptance within an additional specified period. The contract is not effective until signed by the State Controller or an authorized delegate, and the initial expiration date is set four years after the capital construction appropriation date, including a one-year warranty period, though this date may be extended by mutual agreement to accommodate the project schedule.

The contract sum is established as a fixed amount subject to additions and deductions as provided in the General Conditions (SC-6.23), with the contractor compensated for performance of all work phases and services. The agreement includes provisions for condition precedent clauses allowing for phased funding, whereby the contractor's obligation to perform remaining services is contingent upon appropriation and availability of sufficient funds prior to execution of a written amendment. Optional provisions address apprenticeship utilization certification requirements for projects with construction values of $1 million or more, Buy Clean Colorado Act compliance for projects valued at $500,000 or more, federal Davis-Bacon Act applicability for federally funded projects, and state prevailing wage requirements for non-federally funded projects exceeding $500,000. Liquidated damages may be assessed for delays in achieving Substantial Completion and for extended closeout periods, with specific daily amounts established in the contract. The contractor must provide a performance bond (Form SC-6.22), labor and material payment bond (Form SC-6.221), insurance certificates, prevailing wage documentation, and apprenticeship utilization certifications as applicable based on project value and funding sources.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SC-6.21

Rev. 09/2026

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

CONTRACTOR'S

DESIGN/BID/BUILD (D/B/B)

AGREEMENT

(STATE FORM SC-6.21)

State Agency Insert Department or IHE’s Full Legal Name Department I.D.

Insert Department identification Contract I.D. Number Insert CMS number or other contract number Project Number Insert OSC Project Number Project Name Insert Project as as provided by the State Controller's Office Contractor Name Insert Contractor's full Legal Name including "Inc.", "LLC" etc.

Principal Representatives For the State:

Name Department Name Address Line 1 Address Line 2 City, State ZIP Email

For Contractor:

Name Company Name Address Line 1 Address Line 2 City, State ZIP Email

ATTACHMENT 1: The General Conditions of the Contractor’s Design/Bid/Build (D/B/B) Agreement (SC-6.23)

Rev. 09/2026 TOC

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

CONTRACTOR'S DESIGN/BID/BUILD AGREEMENT

(STATE FORM SC-6.21)

TABLE OF CONTENTS… ...................................................................................................... Page Table of Contents for the entire Agreement is located in THE GENERAL CONDITIONS OF THE

CONTRACTOR’S DESIGN/BID/BUILD (D/B/B) AGREEMENT (SC-6.23)

SIGNATURE PAGE

RECITALS:

1 ARTICLE 1 PERFORMANCE OF THE WORK

2 ARTICLE 2 PROVISIONS OF THE CONTRACT DOCUMENTS

3 ARTICLE 3 TIME OF COMPLETION

4 ARTICLE 4 ESSENTIAL CONDITION

5 ARTICLE 5 CONTRACT SUM

5.1 CONDITION PRECEDENT

6 ARTICLE 6 CONTRACT DOCUMENTS

6.1 CAPITALIZED TERMS

7 ARTICLE 7 OPTIONAL PROVISIONS AND ELECTIONS

7.1 MODIFICATION OF ARTICLE 2: Execution, Correlation, Intent of Documents, Communication and Cooperation

7.2 MODIFICATION OF ARTICLE 13: Shop Drawings, Product Data and Samples

7.3 MODIFICATION 1 OF ARTICLE 27: Labor and Wages

7.4 MODIFICATION 2 OF ARTICLE 27: Labor and Wages

7.5 MODIFICATION OF ARTICLE 39: Non-Binding Dispute Resolution

7.6 MODIFICATION OF ARTICLE 45: Guarantee Inspections After Completion

7.7 MODIFICATION OF ARTICLE 46: Time of Completion and Liquidated Damages

8 ARTICLE 8 NOTICE IDENTIFICATION

EXHIBIT A: CONTRACTORS BID ...................................................................................... A EXHIBIT B: PERFORMANCE BOND ................................................................................. B EXHIBIT C: LABOR AND MATERIAL PAYMENT BOND ...................................................... C EXHIBIT D: INSURANCE CERTIFICATE(S) ......................................................................... D EXHIBIT E: BUILDING CODE COMPLIANCE POLICY ......................................................... E EXHIBIT F: STATE SALES AND USE TAX FORM ................................................................ F

EXHIBIT G: APPLICABLE PREVAILING WAGE DETERMINATIONS AND APPRENTICESHIP

CONTRIBUTION RATES ..................................................................................................... G EXHIBIT H: APPRENTICESHIP UTILIZATION CERTIFICATIONS ........................................... H

Rev. 09/2026 1

SIGNATURE PAGE

THE PARTIES HERETO HAVE EXECUTED THIS AGREEMENT

Each person signing this Agreement represents and warrants that the signer is duly authorized to execute this Agreement and to bind the Party authorizing such signature.

In accordance with §24-30-202, C.R.S., this Contract is not valid until signed by the State Controller (or an authorized delegate) or the Title of IHE CFO per the Fiscal Rules of the individual Institution of Higher Education.

Project Number/Name: Insert OSC Project Number followed by Project Name Contract ID No.: Insert CMS Number & Encumbrance Number

CONTRACTOR

INSERT: Legal Name of Contractor

By: Name & Title of Person Signing for Contractor

Date: __________________

STATE OF COLORADO

Jared S. Polis, Governor

INSERT: Name of Agency or IHE INSERT: Name & Title of Head of Agency or

IHE

By: Name & Title of Person Signing for Agency or

IHE

Date: __________________

State Buildings Program

By: Name & Title of Person Signing for State Buildings

Date: __________________

LEGAL REVIEW

Philip J. Weiser, Attorney General

By: Assistant Attorney General

Date: __________________

STATE CONTROLLER

Robert Jaros, CPA, MBA, JD

By: Name of Agency or IHE Delegate

Effective Date: __________________

Note to Drafter: The SC6.21 template has been waived from a Risk Assessment and legal review so long as the document is not edited beyond the fillable fields.

Note to Drafters: If this contract is for a University that is outside State Fiscal Rule, insert the name of your organization here

Rev. 09/2026 2

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

CONTRACTOR'S DESIGN/BID/BUILD (D/B/B) AGREEMENT

(STATE FORM SC-6.21)

Department ID: Insert Dept. Code Contract ID #: Insert Contract ID Project #:Insert Project #

PARTIES. THIS AGREEMENT is entered into by and between the STATE OF COLORADO, acting by and through the Insert Department's or IHE's Full Legal Name hereinafter referred to as the State or Principal Representative, and Insert Contractor's full Legal Name including "Inc.", "LLC" etc.

having its offices at Street address, City, State and Zip Code hereinafter referred to as the Contractor.

EFFECTIVE DATE AND NOTICE OF NONLIABILITY. This Agreement shall not be effective or enforceable until it is approved and signed by the State Controller or its designee (hereinafter called the “Effective Date”), but shall be effective and enforceable thereafter in accordance with its provisions. The State shall not be bound by any provision of this Contract before the Effective Date, and shall have no obligation to pay Contractor for any Work performed or expense incurred before the Effective Date.

INITIAL EXPIRATION DATE. This Agreement will expire on Insert Month day, year, (the “Initial Expiration Date”), which is four (4) years after the capital construction appropriate date and includes the one (1) year warranty period. The Initial Expiration Date may be extended by the mutual agreement of the Parties in order to accommodate the Project schedule, as approved by the Architect/Engineer. In no event shall the Initial Expiration Date or the amended expiration date supersede or contradict the dates of Substantial Completion or Final Acceptance or prohibit the completion of any warranty Work identified or in progress at the end of the one (1) year warranty period.

RECITALS:

WHEREAS, the Principal Representative intends to engage the services of a Contractor for the Insert Project Name as provided by the State Controller's Office hereinafter called the Project;

and

WHEREAS, authority exists in the Law and Funds have been budgeted, appropriated, and otherwise made available, and a sufficient unencumbered balance thereof remains available for payment in Fund Number Insert Fund Number Here, Account Number Insert Account Number here; and

Note to Drafter: Do not include scope of work here. This is only the Project Name.

Rev. 09/2026 3

WHEREAS, the State has Appropriated and the Principal Representative has been authorized to expend the total sum of Insert Dollar Value in Written Words Dollars ($ ) for this project including all professional services, construction/improvements, project contingencies, furnishings, movable equipment, reimbursable expenses and miscellaneous expenses; and

(WHEREAS, funds are available for only a portion of the services defined herein, as more fully described in the funding Condition Precedent clause in Article 5.1; and)

WITNESSETH, that the State of Colorado and the Contractor agree as follows:

1 ARTICLE 1 PERFORMANCE OF THE WORK

The Contractor shall perform all of the Work required for the complete and prompt execution of everything described or shown in, or reasonably implied from the Contract Documents for the above referenced Project.

2 ARTICLE 2 PROVISIONS OF THE CONTRACT DOCUMENTS

The Contractor agrees to perform the Work to the highest industry standards and to the satisfaction of the State of Colorado and its contractor in strict accordance with the provisions of the Contract Documents.

3 ARTICLE 3 TIME OF COMPLETION

The Contractor agrees to Substantially Complete the Project within calendar days from the date of the Notice to Proceed, in addition, the Contractor agrees to finally complete the Project from Substantial Completion to Final Acceptance within calendar days for a total time of completion of the entire Project of calendar days.

The Contractor shall perform the Work with due diligence to completion.

4 ARTICLE 4 ESSENTIAL CONDITION

Timely completion of the Project is an essential condition of this Agreement. The Contractor shall be subject to any liquidated damages described in Article 7.6 for failure to satisfactorily complete the Work within the time periods in Article 3 above.

Note to Drafters: If the Condition Precedent clause is to be used REMOVE the parenthesis and the italics.

If not accepting the Condition Precedent strike out the language – DO NOT DELETE

Rev. 09/2026 4

5 ARTICLE 5 CONTRACT SUM

The Contractor shall be paid for the performance of this Agreement, subject to any additions and deductions as provided for in Articles 32, 34 and 35 of The General Conditions of the Construction Contract SC-6.23, the sum of INSERT DOLLAR VALUE IN

WORDS DOLLARS AND NO/100 ($ ).

Name of Document Short Description of Work/Date Dollar Amount Base Bid Amount Base Bid Alt. # Alt. #

Total Contract Sum -$

5.1 CONDITION PRECEDENT

(At the time of the execution of this Agreement, there are sufficient funds budgeted and appropriated to compensate the Contractor only for performance of the services through and including design phases that have been fully funded Therefore, it shall be a Condition Precedent to the Contractor’s performance of the remaining services and the State's liability to pay for such performance, sufficient funding must be appropriated and made available to the Principal Representative for the Project prior to and, as a further Condition Precedent, a written Amendment is entered into in accordance with the State of Colorado Fiscal Rules, stating that additional funds are lawfully available for the project. If either Condition Precedent is not satisfied by , the Contractor’s obligation to perform services for Insert the future scope of work or design phases and the State's obligation to pay for such service is discharged without liability to each other. If funding is eventually made available after , the Contractor has no right to perform services under of this Agreement and the state has no right to require the Architect/Engineer to perform the said services.)

6 ARTICLE 6 CONTRACT DOCUMENTS

The Contract Documents, as enumerated in Article 1.1 of The General Conditions of the Contractor’s Design/Bid/Build (D/B/B) Agreement (SC-6.23), (the “General Conditions”).

The Contract Documents, including the General Conditions, are all essential parts of this Agreement and are fully incorporated herein.

6.1 CAPITALIZED TERMS

Capitalized terms used herein and not defined shall have the meanings ascribed to them in The General Conditions of Design/Bid/Build (D/B/B) Agreement (SC-6.23)

7 ARTICLE 7 OPTIONAL PROVISIONS AND ELECTIONS

The provisions of this Article 7 alter or enlarge upon the following Articles (the General Conditions of the Contractor’s Design/Bid/Build Agreement SC-6.23):

7.1 MODIFICATION OF ARTICLE 2: Execution, Correlation, Intent of Documents, State Buildings Program Note to Drafters: This table is an embedded Excel spreadsheet. Double click on the table to edit in Excel.

Delete the table if there were no alternates accepted.

State Buildings Program Note to Drafter: This is usually PROJECT PHASES not Design Phases

State Buildings Program Note to Drafter: Insert the latest date that the funds will be released and the Contractor is willing to hold their fee.

State Buildings Program Note to Drafter: Insert the last date the Contractor is willing to hold their fee.

State Buildings Program Note to Drafter: Insert the latest date that the funds will be released and the Contractor is willing to hold their fee.

State Buildings Program Note to Drafter: Insert the last date the Contractor is willing to hold their fee.

Note to Drafter: Insert the latest date that the funds will be released and the Contractor is willing to hold their fee.

Note to Drafter: Apprenticeship utilization is required if Construction value is $1 million or more and not federally funded

Rev. 09/2026 5

Communication and Cooperation.

If the box below is marked, certification of apprenticeship utilization is required for all mechanical, sheet metal, fire suppression, sprinkler fitting, electrical and plumbing work on the project.

☐ ______ Principal Representative initial

7.2 MODIFICATION OF ARTICLE 13: Shop Drawings, Product Data and Samples

If the box below is marked, the Buy Clean Colorado Act, §24-92-117, C.R.S., shall be applicable to the Project. The Contractor is responsible for submitting Environmental Product Declaration (EPD) information for all eligible materials to be used on the project.

☐ ______ Principal Representative initial

7.3 MODIFICATION 1 OF ARTICLE 27: Labor and Wages

If the box below is marked, the Federal Davis-Bacon Act shall be applicable to the Project.

The minimum wage rates to be paid on the Project shall be furnished by the Principal Representative and included in the Contract Documents.

☐ ______ Principal Representative initial

7.4 MODIFICATION 2 OF ARTICLE 27: Labor and Wages

If the box below is marked, the State prevailing wage statute shall be applicable to the Project. The minimum wage rates to be paid on the Project shall be furnished by the Principal Representative and included in the Contract Documents.

☐ ______ Principal Representative initial

7.5 MODIFICATION OF ARTICLE 39: Non-Binding Dispute Resolution

If the box below is marked, and initialed by the State as noted, the requirement to participate in facilitated negotiations shall be deleted from this Contract. Article 39, Non- Binding Dispute Resolution, shall be deleted in its entirety and all references to the right to the same where ever they appear in the contract shall be similarly deleted.

The box may be marked only for projects with an estimated value of less than $500,000.

☐ ______ Principal Representative initial

7.6 MODIFICATION OF ARTICLE 45: Guarantee Inspections After Completion

If the box below is marked the six month guarantee inspection is not required.

☐ ______ Principal Representative initial

7.7 MODIFICATION OF ARTICLE 46: Time of Completion and Liquidated Damages

If an amount is indicated immediately below, liquidated damages shall be applicable to this Project as, and to, the extent shown below. Where an amount is indicated below, liquidated damages shall be assessed in accordance with and pursuant to the terms of The General Conditions of the Design/Bid/Build Agreement Article 46, Time of Completion And Liquidated Damages, in the amounts and as here indicated. The election

Note to Drafter: Double-click on the box to bring up Check Box Form Field window and select “Checked”

Note to Drafter: The Buy Clean Colorado Act applies to all projects with a construction value of $500,000 or more

Note to Drafter: Federal Davis-Bacon Act might be applicable if federally funded. Confirm with the funding documentation.

Note to Drafter: Double-click on the box to bring up Check Box Form Field window and select “Checked”

Note to drafter: State prevailing wage is required if the construction value is $500,000 or more and not federally funded.

Note to Drafter: Double-click on the box to bring up Check Box Form Field window and select “Checked”

Note to Drafter: Double-click on the box to bring up Check Box Form Field window and select “Checked”

Note to Drafter: Double-click on the box to bring up Check Box Form Field window and select “Checked”

Rev. 09/2026 6 of liquidated damages shall limit and control the parties right to damages as the State’s sole and exclusive remedy for delay.

7.7.1 Inability To Use The Project

For the inability to use the Project, for each day after the number of calendar days specified in the Contractor’s bid for the Project and the Agreement for achievement of Substantial Completion, until the day that the Project has achieved Substantial Completion and the Notice of Substantial Completion is issued, the Contractor agrees that an amount equal Insert dollar value in words Dollars ($ ). shall be assessed against Contractor from amounts due and payable to the Contractor under the Contract, or the Contractor and the Contractor’s Surety shall pay to the Principal Representative such sum for any deficiency, if amounts on account thereof are deducted from remaining amounts due, but amounts remaining are insufficient to cover the entire assessment.

7.7.2 Damages Related to Extended Closeout

For damages related to or arising from additional administrative, technical, supervisory and professional expenses related to and arising from the extended closeout period, for each day in excess of the number of calendar days specified in the Contractor’s bid for the Project and the Agreement to finally complete the Project as defined by the issuance of the Notice of Final Acceptance (after the issuance of the final Notice of Substantial Completion), the Contractor agrees that an amount equal to Insert dollar value in words Dollars ($ ). shall be assessed against Contractor from amounts due and payable to the Contractor under the Contract, or the Contractor and the Contractor’s Surety shall pay to the Principal Representative such sum for any deficiency, if amounts on account thereof are deducted from remaining amounts due but amounts remaining are insufficient to cover the entire assessment.

8 ARTICLE 8 NOTICE IDENTIFICATION

All Notices pertaining to this Agreement and the General Conditions (SC-5.23) or otherwise required to be given shall be transmitted in writing, to the individuals at the addresses listed below, and shall be deemed duly given when received by the parties at their addresses below or any subsequent persons or addresses provided to the other party in writing.

NOTICE TO PRINCIPAL REPRESENTATIVE:

Insert Name of individual acting on the PR behalf Insert Street Address City, State Zip Code Insert email address

With copies to State Buildings Program (or Delegate) Insert Name of individual acting on OSA/SBP behalf

Note to drafter: If liquidated damages are not applicable Note “Not Applicable” in this field.

Note to drafter: If liquidated damages are not applicable Note “Not Applicable” in this field.

Rev. 09/2026 7

Insert Street Address City, State Zip Code Insert email address

NOTICE TO CONTRACTOR:

Insert Name of individual acting on the contractor behalf Insert Street Address City, State Zip Code Insert email address

STATE OF COLORADO

STATE BUILDINGS PROGRAM

CONTRACTOR'S DESIGN/BID/BUILD AGREEMENT

EXHIBIT A: CONTRACTORS BID

CONTRACTOR’S BID (Form SBP-6.13) Workers’ Compensation Certification (SBP-4.1) Bid Alternates (Form SBP-6.131) Unit Pricing (Form SBP-6.133) Bid Bond (Form SBP-6.14) Labor Burden Calculation (Form SBP-6.18)

Note to drafter: Labor burden is required on ALL construction projects

STATE BUILDINGS PROGRAM

CONTRACTOR'S DESIGN/BID/BUILD AGREEMENT

EXHIBIT B: PERFORMANCE BOND

PERFORMANCE BOND (Form SC-6.22)

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

CONTRACTOR'S DESIGN/BID/BUILD AGREEMENT

EXHIBIT C: LABOR AND MATERIAL PAYMENT BOND

LABOR AND MATERIAL PAYMENT BOND (Form SC-6.221)

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

CONTRACTOR'S DESIGN/BID/BUILD AGREEMENT

EXHIBIT D: INSURANCE CERTIFICATE(S)

INSURANCE CERTIFICATE(S) (attached)

STATE BUILDINGS PROGRAM

CONTRACTOR'S DESIGN/BID/BUILD AGREEMENT

EXHIBIT E: BUILDING CODE COMPLIANCE POLICY

APPROVED STATE BUILDING CODES

BUILDING CODE COMPLIANCE POLICY: COORDINATION OF APPROVED BUILDING CODES, PLAN

REVIEWS, BUILDING INSPECTIONS AND STATE DEVELOPMENT REQUIREMENTS

Refer to the Office of the State Architect’s Building Codes Webpage for the Building Code Compliance Policy (Rev. )

Exhibit A: Approved Building Codes of the Code Compliance Policy dated ________. including the Amendments to the International Building Code and Code Compliance Plan Review Procedures (Rev. )

Exhibit B: Plan Review Procedures of the Code Compliance Policy dated ________.

Exhibit I: State Development Requirements of the Code Compliance Policy dated ________.

The State Buildings Program Building Codes Webpage may be found at:

https://osa.colorado.gov/building-codes https://osa.colorado.gov/state-buildings/building-codes https://osa.colorado.gov/building-codes

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

CONTRACTOR'S DESIGN/BID/BUILD AGREEMENT

EXHIBIT F: STATE SALES AND USE TAX FORM

STATE SALES AND USE TAX FORM

Note to Drafter: The CDOR form should have the bottom half completed by the agency so the contractor may expedite their exemption certificate.

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

CONTRACTOR'S DESIGN/BID/BUILD AGREEMENT

(STATE FORM SC-6.21)

EXHIBIT G: APPLICABLE PREVAILING WAGE DETERMINATIONS AND APPRENTICESHIP

CONTRIBUTION RATES

Applicable Prevailing Wage Determinations Apprenticeship Contribution Rates

(Applicable for projects $500,000 or more that are not supplemented with federal funds)

Note to Drafter: Delete this page if not applicable

STATE BUILDINGS PROGRAM

CONTRACTOR'S DESIGN/BID/BUILD AGREEMENT

EXHIBIT H: APPRENTICESHIP UTILIZATION CERTIFICATIONS

APPRENTICESHIP UTILIZATION CERTIFICATIONS

(Applicable for project costs $1,000,000 or more)

Note to drafter: Delete this page if not applicable

State Agency
Department I.D.
Contract I.D. Number
Project Number
Project Name
Contractor Name
Principal Representatives
CONTRACTOR
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
LEGAL REVIEW
STATE CONTROLLER
1 ARTICLE 1 PERFORMANCE OF THE WORK
2 ARTICLE 2 PROVISIONS OF THE CONTRACT DOCUMENTS
3 ARTICLE 3 TIME OF COMPLETION
4 ARTICLE 4 ESSENTIAL CONDITION
5 ARTICLE 5 CONTRACT SUM
5.1 CONDITION PRECEDENT
6 ARTICLE 6 CONTRACT DOCUMENTS
6.1 CAPITALIZED TERMS
7 ARTICLE 7 OPTIONAL PROVISIONS AND ELECTIONS
7.1 MODIFICATION OF ARTICLE 2: Execution, Correlation, Intent of Documents, Communication and Cooperation.
7.2 MODIFICATION OF ARTICLE 13: Shop Drawings, Product Data and Samples
7.3 MODIFICATION 1 OF ARTICLE 27: Labor and Wages
7.4 MODIFICATION 2 OF ARTICLE 27: Labor and Wages
7.5 MODIFICATION OF ARTICLE 39: Non-Binding Dispute Resolution
7.6 MODIFICATION OF ARTICLE 45: Guarantee Inspections After Completion
7.7 MODIFICATION OF ARTICLE 46: Time of Completion and Liquidated Damages
7.7.1 Inability To Use The Project
7.7.2 Damages Related to Extended Closeout
8 ARTICLE 8 NOTICE IDENTIFICATION
APPROVED STATE BUILDING CODES
Refer to the Office of the State Architect’s Building Codes Webpage for the Building Code Compliance Policy (Rev. )
Exhibit A: Approved Building Codes of the Code Compliance Policy dated ________. including the Amendments to the International Building Code and Code Compliance Plan Review Procedures (Rev. )
Exhibit B: Plan Review Procedures of the Code Compliance Policy dated ________.
Exhibit I: State Development Requirements of the Code Compliance Policy dated ________.

File details come from the government source that posted it. Updated .