Appendix_A_-_Technical_Specifications.pdf
PDF 605 KB Posted
- Solicitation number
- 22/23-51
- Issued by
- Hartford County, Connecticut
About this file
The document is a comprehensive technical specification for the Manchester Sanitary Landfill's MSE (Mechanically Stabilized Earth) Berm Wall Phase 1 Construction project located in Manchester, Connecticut. The project involves constructing an approximately 35-foot tall by 900-foot long MSE berm with geosynthetic reinforcement, encompassing multiple critical tasks including clearing and grubbing approximately 8 acres, relocating 15,360 cubic yards of existing waste to an active working face, installing stormwater improvements, implementing perimeter and diversion swales, and constructing an access road. The work will be performed under a single Prime General Construction Contract (Bid No. 22/23-49) with normal working hours defined as 7:00 a.m. to 4:00 p.m. on weekdays, and requires obtaining necessary state and local permits, including those from the Connecticut Department of Energy and Environmental Protection.
The project involves significant environmental and engineering considerations, with detailed specifications for materials, installation techniques, and quality control. Key technical requirements include using specific geosynthetic materials like HDPE geogrids, geotextiles, and liners, with precise installation standards and rigorous testing protocols. The contractor will be responsible for managing waste relocation, erosion control, dust suppression, and maintaining strict safety and environmental compliance. Geotechnical monitoring will be implemented using vibrating wire piezometers and inclinometers to track potential soil movement and pore water pressures during construction. The project's total estimated soil volume involves approximately 65,725 cubic yards of reinforced fill, with comprehensive requirements for material selection, placement, and testing to ensure structural integrity and long-term stability of the MSE berm.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Appendix A
Technical Specifications
2.23 TABLE OF CONTENTS
3185.090.001 TOC-1
TABLE OF CONTENTS
MATERIALS AND PERFORMANCE (TECHNICAL) SPECIFICATIONS
DIVISION 01 GENERAL REQUIREMENTS
01 10 00 SUMMARY OF WORK
01 33 00 SUBMITTAL PROCEDURES
01 43 00 QUALITY CONTROL AND ASSURANCE
01 50 01 HEALTH AND SAFETY PROVISIONS
01 57 13 TEMPORARY EROSION AND SEDIMENT CONTROL
01 57 20 DUST CONTROL
01 71 23 CONSTRUCTION STAKING
01 77 00 CONTRACT CLOSEOUT
DIVISION 31 EARTHWORK
31 05 12 COMMON FILL
31 05 16 AGGREGATES FOR EARTHWORK
31 05 17 SELECT FILL MATERIALS
31 05 19.19 GEOGRIDS FOR EARTHWORK
31 05 19.24 GEOTEXTILES
31 05 19.30 HDPE GEOMEMBRANE LINER
31 09 13 GEOTECHNICAL INSTRUMENTATION AND MONITORING
31 11 00 CLEARING AND GRUBBING
31 23 17 EXCAVATION – BLASTING NOT ALLOWED
31 25 14.16 ROLLED EROSION CONTROL MATS AND BLANKETS
31 37 00 RIPRAP
DIVISION 32 EXTERIOR IMPROVEMENTS
32 31 13 FENCE, CHAIN LINK
32 91 19.13 TOPSOIL PLACEMENT AND GRADING
32 92 19 SEEDING
DIVISION 33 UTILITIES
33 05 33.33 CORRUGATED PERFORATED HDPE DRAINAGE PIPE
33 05 63 CONCRETE VAULTS AND CHAMBERS
33 42 13 PIPE CULVERTS
DIVISION 44 POLLUTION CONTROL EQUIPMENT
44 01 55 WASTE RELOCATION
END OF SECTION
2.23 SUMMARY OF WORK
3185.090.001 01 10 00-1
SECTION 01 10 00
SUMMARY OF WORK
PART 1 - GENERAL
1.01 SUMMARY
A. The following summary of Work is a general summary of the salient features of the Work to be performed by the General and Trades construction contractors. It does not supersede the requirements of the detailed technical specifications.
B. The proposed MSE Berm project is to be constructed at the Manchester Sanitary Landfill which is located at 311 Olcott Street, in Manchester, Connecticut.
C. The work described herein and shown on the Contract Drawings includes furnishing, installing, and incorporating all materials and equipment into the project as well as performing or providing all labor, supervision, equipment, and services unless otherwise specifically noted in the Contract Documents.
D. Work under this contract includes, but is not limited to:
1. Clear and grub approximately 8 acres of mixed vegetation within work area;
2. Preparation of berm subgrade to including relocation of 15,360 CY existing waste to active working face;
3. Construction of an approx. 35’ tall by 900’ long (excluding transition ramps) mechanically stabilized earth (MSE) berm with applicable geosynthetics reinforcement (~65,725 CY soil);
4. Storm water improvements to include perimeter swale relocations, termination swales, diversion berms, and supply and install of a storm water down chute structure;
5. Geotechnical monitoring devices to include vibrating wire piezometers and Inclinometers;
6. Access road construction and miscellaneous site work and related items.
1.02 CONTRACTS
A. Work will be performed under a single Prime General Construction Contract.
The Contract is identified in the following and on the Drawings as Bid No. 22/23
– 49 – Manchester Landfill MSE Berm Wall Phase 1 Construction.
B. Refer to Sections 10 – Form of General Bid and 11 – Measurement and Payment of the Invitation to Bid for detailed Pay Item descriptions.
SUMMARY OF WORK 2.23
01 10 00-2 3185.090.001
1.03 CONTRACTOR’S USE OF SITE AND PREMISES
A. The Project Site is located within the limits of an active Construction and Demolition Debris (C&D) Landfill and Municipal Solid Waste (MSW) Transfer Station.
B. The Contractor shall not in any way interfere with the facility traffic and operation of existing facility (landfill, transfer station, etc.). All traffic flow patterns, staging areas, and haul roads required for construction of project shall be coordinated with the Owner/Engineer.
C. The contractor may use existing haul roads approved by the owner. Any other haul roads required by the General Contractor for the completion of work in this contract shall be constructed and maintained by the contractor at his own expense.
Additional haul road locations must be approved by the engineer. The existing haul roads may be different than shown on this plan. All temporary haul roads installed by the contractor shall be removed and restored to pre-construction conditions unless otherwise approved by the owner/engineer.
D. Normal working hours for this project are defined as 7:00 a.m. to 4:00 p.m. on Mondays through Fridays. No work shall take place outside these hours or on a Town holiday (see Attachment for Town Holiday Calendar) without prior approval of the Engineer. Any activities which require support from Town staff, including but not limited to waste relocation activities, shall only occur when the Town’s scale is open to Commercial customers (currently 7:15 AM to 2:30 PM).
1.04 WORK SEQUENCE
A. General
1. Sequence work in accordance with the requirements of the Contract
Documents and the Progress Schedule.
2. Sequence work to minimize impacts to existing facilities.
3. Work shall be substantially complete as indicated in the Invitation to Bid
Proposal.
B. Suggested Sequence of Construction: The following is a suggested chronological sequence of construction:
1. Coordinate and complete a pre- construction meeting with Town and
Owner. Responsible parties to be identified and emergency phone numbers provided.
2. Install erosion control measures at locations indicated on plans.
3. Clear and grub site.
4. Install pore pressure monitoring system.
5. Install proposed diversion swales and TRM lined swales, seed, establish vegetation, and install check dams.
6. Install diversion swale outlet culverts.
7. Install reinforced fill, MSE wall and structural backfill.
2.23 SUMMARY OF WORK
3185.090.001 01 10 00-3
8. Construct gravel perimeter access road.
9. Install liner system and infiltration trench.
10. Construct storm drainage and install riprap.
11. Install fences, guide rails. Perform final grading, mulch and apply permanent seeding.
12. Remove sediment barriers when permanent vegetative cover is established.
C. Permits
1. The work described herein and depicted in the Contract Drawings includes obtaining all required state and local permits, including, but not limited to, Connecticut Department of Energy and Environmental Protection, Town of Manchester Health Department Permit, Town of Manchester Sanitation Division Permit, and all associated fees, bonds, insurances, all associated inspections and acceptance coordination.
2. The work described above includes performing all work in accordance with the following secured project permits:
a. Connecticut Department of Energy and Environmental Protection
(DEEP) Authorization to Disrupt a Solid Waste Facility No.
201705245, dated August 31, 2017.
b. DEEP - Bureau of Air Management New Source Review Permit to Construct and Operate a Stationary Source (Town No. 097, Premises No. 0225, Permit No. 0114, Stack No. 02).
c. DEEP – Bureau of Air Management Title V Permit, No. 097-0127-
TV.
d. DEEP – Solid Waste Permit to Construct and Operate (1090904-
PCO)
e. DEEP General Permit for the Discharge of Stormwater Associated with Industrial Activities, Permit No. GSI000502.
PART 2 - PRODUCTS
(NOT USED)
PART 3 - EXECUTION
(NOT USED)
2.23 SUBMITTAL PROCEDURES
3185.090.001 01 33 00-1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.01 SUMMARY
A. Section includes requirements for the Schedule of Submittals and administrative and procedural requirements for submitting Shop Drawings Samples, and other submittals.
1.02 DEFINITIONS
A. Action Submittals:
1. Written and graphic information and physical samples that require
Engineer’s responsive action.
2. Action submittals are those submittals indicated in individual
Specification Sections as “action submittals.”
B. Informational Submittals:
1. Written and graphic information and physical Samples that do not require
Engineer’s responsive action.
2. Submittals may be rejected for not complying with requirements.
3. Informational submittals are those submittals indicated in individual
Specification Sections as “informational submittals”.
C. Portable Document Format (PDF): An open file format standard licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
1.03 FORMAT
A. Contractor shall be responsible for submittal all information necessary for submittal approvals. Make submittals to the office of the Engineer: Barton & Loguidice, D.P.C. Contact information for Engineer representative will be provided at the Pre-Construction conference.
B. A letter of transmittal shall accompany each submittal. If data for more than one section of the Specifications is submitted, a separate transmittal letter shall accompany the data submitted for each section.
C. If a Shop Drawing deviates from the requirements of the Contract Documents, Contractor shall specifically note each deviation in its letter of transmittal.
D. When Samples are required, the quantities are identified in the individual Specification sections.
SUBMITTAL PROCEDURES 2.23
01 33 00-2 3185.090.001
E. Contractor’s approval:
1. All submittals shall bear the stamp of approval and signature of Contractor as evidence that the submittal has been reviewed by Contractor.
2. Submittals without this stamp of approval will not be reviewed and will be returned to Contractor.
3. Contractor’s stamp shall contain the following minimum information:
a. Project: Manchester Landfill MSE Berm Wall – Phase 1 Construction
b. Bid No: 22/23-49
c. Contractor:
d. Date:
e. Specification section:
f. Drawing number(s):
g. Submittal No.: BBBB-SS SS SS-sss-rrr, where:
1) BBBB: Bid No.
2) SS SS SS: Specification section number.
3) sss: sequential submittal number.
4) rrr: submittal revision number. All initial submittals shall be revision number “000”.
F. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification section.
2. Submit electronically in PDF format (or DWF format as applicable) via email unless Contractor utilizes Construction management site.
3. Paper Submittals: No paper submittals will be accepted as part of this
Project unless specifically required as part of the Contract Documents or requested by Engineer or Engineer’s consultants.
G. Resubmittals:
1. Make resubmittals in same form and number of copies as initial submittal.
2. Resubmittals shall be as a standalone submittal, including all applicable information from the previous submittals.
3. Resubmittals that only include information on revised items will be returned without review.
4. Note date and content of previous submittal.
5. Note date and content of revision in label or title block and clearly indicate extent of revision.
6. Contractor must clearly draw attention to additional revisions made that were not requested in previous submittal review comments.
7. Resubmit submittals until they are marked with approval notation from
Engineer’s action stamp.
3185.090.001 01 33 00-3
1.04 SCHEDULE OF SUBMITTALS
A. Submit preliminary Schedule of Submittals for review by Engineer.
B. Revise and resubmit until acceptable to Engineer.
1.05 OR-EQUALS AND SUBSTITUTIONS
A. Requests for substitutions or consideration of “or equal” items shall be handled as specified in the General Conditions.
B. Substitutions or “or equal” items shown or implied on the submittal are prohibited and will be rejected.
1.06 DELEGATED DESIGN SERVICES
A. Performance and design criteria:
1. Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.
2. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Engineer.
B. Delegated-design services certification:
1. In addition to Shop Drawings, and other submittals, submit digitally signed PDF electronic file copies of certificate, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.
2. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.
PART 2 - PRODUCTS
[NOT USED]
PART 3 - EXECUTION
3.01 CONTRACTOR’S RESPONSIBILITIES
A. General:
1. Contractor shall forward submittals well in advance of the need for the material or equipment for construction and with required allowance for time required to make delivery of material or equipment after data covering such is approved.
01 33 00-4 3185.090.001
2. Contractor assumes the risk for all material or equipment that is ordered, fabricated, or shipped prior to the approval of submittals.
3. No material or equipment will be permitted to be incorporated into the Work nor will such be included in Applications for Payment until approval thereof has been obtained in the manner specified herein.
B. Coordination:
1. It is Contractor’s responsibility to review submittals of its Suppliers and
Subcontractors before transmitting them to Engineer to assure proper coordination of the Work, to determine that each submittal is in accordance with the Contract Documents, and that there is sufficient information about material and equipment for Engineer to determine compliance with the Contract Documents.
2. Incomplete or inadequate submittals will be returned for revision without review, as specified herein.
3. Approval of submittals shall not relieve Contractor from the obligation of furnishing material and equipment of proper dimension, size, quality, quantity, and all performance characteristics to perform the requirements and intent of the Contract Documents
4. Engineer’s approval shall not relieve Contractor from responsibility for errors of any sort on the submittals.
5. Approval is intended only to assure conformance with the design concept of the Project and compliance with the information given in the Contract Documents.
6. Contractor is responsible for dimensions which shall be confirmed and correlated at the Site.
7. Contractor is responsible for information that pertains solely to the fabrication processes or to the technique of construction and for the coordination of the Work of all trades.
C. Engineer’s Approval:
1. Submittals not bearing the Engineer’s “approved” or “approved as noted” notation shall not be used, issued to Subcontractors, nor utilized for construction purposes.
2. No work shall be performed or equipment installed without an approved Shop Drawing or submittal.
3. Contractor assumes the risk for all work performed or equipment installed without an approved Shop Drawing or submittal.
4. In the event Contractor obtains Engineer’s approval for the use of equipment other than that which is shown or specified, Contractor shall, at its own expense and using methods approved by Engineer, make all changes to the Work, including structures, piping, electrical, equipment and controls, that may be necessary to accommodate this equipment.
3185.090.001 01 33 00-5
3.02 ENGINEER’S ACTION
A. Engineer will review and process all submittals promptly, but a reasonable time shall be allowed for submittal transmittals, reviews, and revisions.
B. Contractor shall allow fifteen (15) days for each submittal review and response in the preparation of Progress Schedule unless otherwise specified in the Contract Documents.
C. In preparing its Construction Progress Schedule, Contractor shall allow for two
(2) submittal review cycles for each submittal.
D. Owner may back-charge Contractor for costs associated with reviewing the third and successive submittal(s).
E. Engineer will document and notify Owner in writing of all such back charges to be deducted Applications for Payment.
3.03 SUBMITTAL STATUS AND PROCEDURE
A. After Engineer completes its review, the submittal will be marked with one of the following dispositions:
1. Approved.
2. Approved as noted.
3. No action required.
4. Revise as noted - Resubmit.
5. Rejected – Resubmit as specified.
B. Submittals marked “Approved”:
1. Submittals that conform to the Contract Documents without comment will be issued a disposition of “Approved”.
2. Contractor may order, fabricate, or ship the materials included in the submittal.
C. Submittals marked “Approved as noted”:
1. Submittals that conform to the Contract Documents with correction of minor clarifications or omissions will be issued a disposition of “Approved as noted”.
2. Contractor may order, fabricate, or ship the materials included in the submittal that incorporates Engineer’s comments.
D. Submittals marked “No action required”: Informational submittals will be issued a disposition of “No action required”, acknowledging to Contractor Engineer’s receipt of the submittal.
01 33 00-6 3185.090.001
E. Submittals marked “Revise as noted - Resubmit”:
1. Submittals that include a named manufacturer or supplier, but contain insufficient information to determine conformance to the Contract Documents will be issued a disposition of “Revise and Resubmit”.
2. Contractor shall make corrections to satisfy the deficiencies indicated and repeat the submittal procedure.
3. The resubmittal shall conform to the submittal numbering procedure specified herein.
F. Submittals marked “Rejected – Resubmit as specified”:
1. Submittals that do not conform to the Contract Documents will be issued a disposition of “Rejected – Resubmit as specified”.
G. Contractor shall revise the submittal to incorporate equipment or products that comply with the requirements of the Contract Documents.
2.23 QUALITY CONTROL AND ASSURANCE
3185.090.001 01 43 00-1
SECTION 01 43 00
QUALITY CONTROL AND ASSURANCE
PART 1 - GENERAL
1.01 DESCRIPTION
A. Work includes:
1. Quality assurance and control of installation
2. References
3. Field samples
4. Manufacturers' field services and reports
1.02 RELATED WORK
A. All individual Technical Specifications.
1.03 QUALITY CONTROL/ASSURANCE
A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality. The Contractor shall be responsible for all Quality Control / Assurance and field testing specified in the individual technical specifications. All samples locations shall be directed by the Engineer.
B. Comply fully with manufacturers' instructions, including each step in sequence.
C. Should manufacturers’ instructions conflict with Contract Documents, request clarification from Engineer before proceeding.
D. Comply with specified standards as a minimum quality of the Work except when more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
E. Perform work by persons qualified to produce workmanship of specified quality.
F. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion or disfigurement.
G. Conform to reference standard by date current on date specified in product sections.
H. Obtain copies of standards when required by Contract Documents.
I. Should specified reference standards conflict with Contract Documents, request clarification from Engineer before proceeding.
QUALITY CONTROL AND ASSURANCE 2.23
01 43 00-2 3185.090.001
J. The contractual relationship of the parties to the Contract shall not be altered from the Contract Documents by mention or inference otherwise in any reference documents.
K. When specified in individual specification sections, the contractor shall require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, and test, adjust and balance equipment as applicable, and to initiate instructions when necessary.
1.04 SUBMITTALS
A. None.
PART 2 - PRODUCTS
[NOT USED]
PART 3 - EXECUTION
[NOT USED]
2.23 HEALTH AND SAFETY PROVISIONS
3185.090.001 01 50 01-1
SECTION 01 50 01
HEALTH AND SAFETY PROVISIONS
PART 1 - GENERAL
1.01 REQUIREMENTS
A. The Contractor's attention is directed to the fact that the work site is adjacent to an existing refuse landfill and that unsafe conditions may occur. The Contractor is advised that leachate, methane, hydrogen sulfide and other toxic gases may be encountered in excavations for this project.
B. The Contractor shall be responsible to monitor working conditions at all times during construction and, as necessary, to provide appropriate protective clothing, equipment and facilities for his personnel, and to establish workplace procedures to ensure their safety, and to enforce the use of these procedures, equipment and facilities in accordance with the following guidelines:
1. Safety and Health Regulations Promulgated by the U.S. Department of
Labor
2. OSHA:
a. 29 CFR 1910 – Occupational Safety and Health Standards
b. 29 CFR 1920 – Safety and Health Regulations for Construction
c. 30 CFR 1 to 199 – Mine Safety and Health Administration
3. U.S. Environmental Protection Agency Interim Standard Operating Safety Guides – Office of Emergency and Remedial Response – Hazardous Response Support Division, Rev. September 1982.
4. U.S. Environmental Protection Agency Medical Monitoring Program Guidelines.
C. The Contractor shall implement a Health and Safety protection program. The program shall include provisions for stations allowing workers to wash and to put on and remove protective clothing, and stations for vehicles to be cleaned, if necessary, before leaving the site.
D. The Contractor shall engage a qualified Health and Safety expert having experience in similar landfill conditions, to monitor site conditions and recommend all necessary Health and Safety protection for the Contractor’s personnel and the personnel of the Owner and Engineer, as may be affected.
E. The Contractor shall comply with all Federal, State and local safety requirements related to the presence of combustible and nausea-inducing gases.
F. The Contractor shall comply with all health and safety provisions included in the Owner’s service agreement.
HEALTH AND SAFETY PROVISIONS 2.23
01 50 01-2 3185.090.001
G. In addition to the above requirements, the Contractor shall comply with the following requirements:
1. All construction equipment on the site shall be equipped with vertical exhaust pipes or a sparkproof exhaust.
2. Smoking shall not be permitted in any area where gases can accumulate.
3. When working in the presence of a detectable concentration of methane, the soils shall be wetted to the satisfaction of the Engineer.
4. Welding or open flames shall not be permitted in enclosed areas. In other areas in which a detectable concentration of methane is found, ground mats shall be used.
5. Toxic gas indicators, combustible gas indicators, and fire extinguishers shall be available at all times during operations. Continuous monitoring shall be employed with the Contractor furnishing daily to the Engineer, three (3) copies of a certified statement of their findings.
H. If, at any time, the Owner or the Engineer is apprised of a safety hazard which demands immediate attention because of its high potential for harm to public travel, persons on or about the work, or public or private property, the Owner or the Engineer shall have the right to order such safeguards to be erected and such precautions to be taken as necessary and the Contractor shall comply with such orders. If, under such circumstances, the Contractor does not or cannot immediately put the work into proper and approved condition, or if the Contractor or his representative is not upon the site so that he can be notified immediately of the insufficiency of safety precautions, then the Owner may put the work into such a condition that it shall be, in his opinion, in all respects safe, and the Contractor shall pay all expenses of such labor and materials as may have been used for this purpose by him or by the Owner. The fact that the Owner or the Engineer does not observe a safety hazard or does not order the Contractor to take remedial measures shall in no way relieve the Contractor of the entire responsibility for any costs or claims for loss, damage, or injury by or against any party sustained on account of the insufficiency of the safety precautions taken by him or by the Owner acting under authority of this Section.
I. The Contractor is alerted to the fact that conditions of high hazard are present or can be present at the site during the performance of the work. It is the responsibility of the Contractor to take appropriate safety precautions to meet whatever conditions of hazard may be present during the performance of the work, whether reasonably foreseeable or not. The safety conditions enumerated in the Technical Specifications are the minimum permissible and neither the Owner nor the Engineer make any representation that the safety standards provided herein will be adequate to meet all eventualities. The Contractor is therefore alerted to the fact that it shall be its responsibility to anticipate and provide such additional safety precautions, facilities, personnel and equipment as shall be necessary to protect life and property from whatsoever conditions of hazard are present or may be present.
2.23 HEALTH AND SAFETY PROVISIONS
3185.090.001 01 50 01-3
J. The Contractor shall, at a minimum, supply and erect highly visible safety fencing a minimum of three (3) feet in height around all construction areas that pose a threat to safety. The Contractor shall erect safety fencing at this own discretion and as directed by the Engineer and shall maintain such fencing until such a time that the potential safety hazard has been rectified. Upon final completion of construction all safety fencing shall be removed offsite by the Contractor, unless otherwise requested by Owner. Safety fencing requirements of OSHA shall be enforced by the Contractor for all subcontractors on-site.
PART 2 - PRODUCTS
[NOT USED]
PART 3 - EXECUTION
2.23 TEMPORARY EROSION AND SEDIMENT CONTROL
3185.090.001 01 57 13-1
SECTION 01 57 13
TEMPORARY EROSION AND SEDIMENT CONTROL
PART 1 - GENERAL
1.01 WORK INCLUDED
A. The work of this Section shall include, but not necessarily be limited to, the following:
1. The furnishing and installation of sedimentation control system, crushed stone dikes, grading to control runoff, baled hay/straw, mulch, outfall protection, temporary seeding and other erosion control devices.
2. Continual maintenance of installed erosion control devices.
3. Removal and cleanup.
1.02 RELATED WORK
A. All of the Contract Documents apply to the work of this Section.
B. Section 01 57 20, Dust Control
C. Section 31 23 17, Excavation – Blasting Not Allowed
1.03 QUALITY ASSURANCE
A. Where Form 818 is referred to, it means "State of Connecticut Department of Transportation Standard Specifications for Roads, Bridges and Incidental Construction, Form 818, 2020" and including all Supplemental Specifications through date of bid advertisement.
B. References to "Connecticut Guidelines for Soil Erosion and-Sedimentation Control" (2002).
1.04 SUBMITTALS
A. Submit haybale, sediment control system, geotextile, inlet sediment control device, and seed mixture technical data to the Engineer for approval.
B. Submit certified test results from a testing laboratory for riprap and crushed stone to the Engineer for approval. Test results must indicate characteristics of materials including gradations. The cost of all testing shall be borne by the Contractor.
TEMPORARY EROSION AND SEDIMENT CONTROL 2.23
01 57 13-2 3185.090.001
PART 2 - PRODUCTS
2.01 MATERIALS
A. Haybales for Check Dams shall comply with the Form 818, Article 2.19.03.
B. Sedimentation Control System shall comply with Form 818, Article M.08.01-19.
C. Riprap for temporary sediment traps and outfall protection shall comply with Form 818, Article M.12.02.
D. Geotextile for temporary sediment traps shall conform to the requirements of Form 818, Article M.08.01-19.
E. Crushed stone shall conform to the requirements of Form 818, Article M1.01.01, No. 3.
F. Temporary Seeding: seed for topsoil stockpiles and exposed areas of disturbance that may remain for extended periods and subject to erosion, shall meet the requirements of Form 818, Article M13.04 (b).
G. Inlet Sediment Control shall be “Siltsack” high flow manufactured by ACF Environmental or approved equal.
PART 3 - EXECUTION
3.01 GENERAL EROSION CONTROL REQUIREMENTS
A. The Contractor shall appoint an individual, acceptable to the Owner and/or Engineer, to coordinate and supervise the maintenance and control of sedimentation and erosion control systems and devices. Compliance with these provisions shall also be included in all subcontract agreements.
1. All sedimentation and erosion control devices shall be inspected weekly by the Contractor to verify their operation and to determine the cleaning and repair necessary for the duration of this Contract. In addition, special attention shall be given to the adequacy of the control systems prior to severe storm weather forecasts. Suspend operations (earthwork) for major storm events and implement additional sedimentation and erosion controls as necessary. Inspect control systems during and after storms to determine necessary repairs.
2. Repairs to sedimentation control systems directed by the Owner/Engineer shall be accomplished within 24 hours of the directive or as soon as possible prior to storm forecasts.
3. Contractor shall maintain on-site, at all times, replacement materials for the devices utilized, readily available for necessary repairs.
2.23 TEMPORARY EROSION AND SEDIMENT CONTROL
3185.090.001 01 57 13-3
4. The Contractor shall comply with the Best Management Practices as shown in Form 818, Article 1.10.03 and "Connecticut Guidelines for Soil Erosion and-Sedimentation Control" (2002).
B. The Owner/Engineer has the authority to control the surface area of each material exposed by construction operations and to direct the Contractor to immediately provide permanent or temporary pollution control measures to prevent contamination of adjacent wetlands, watercourses or other areas of water impoundment. Every effort shall be made by the Contractor to prevent erosion on the site and abutting property.
C. The Owner/Engineer shall limit the surface area of earth material exposed if the Contractor fails to sufficiently protect the slopes to prevent pollution.
D. The erosion control features installed by the Contractor shall be maintained by the Contractor to ensure their efficient operation, and he shall remove/replace such installations if ordered by the Owner/Engineer.
E. The Contractor shall operate all equipment and perform all construction operations so as to minimize pollution. The Contractor shall cease any of his operations, which will increase pollution during rainstorms.
3.02 HAYBALE/STRAW BALE INSTALLATION
A. Bales shall be placed around catch basins, along diversion fences, in swales, or as directed by the Engineer. They shall be held in place by two wooden stakes in each bale driven a minimum of eighteen (18) inches into the ground. Bales shall be maintained or replaced until they are no longer necessary for the purpose intended or are ordered removed by the Owner/Engineer.
3.03 SEDIMENTATION CONTROL SYSTEM
A. Sedimentation Control System shall be mounted on wood-stakes or posts with or without fence backing as recommended by the fabric manufacturer. The bottom six (6") inches of the fabric shall be buried by trenching, laying the six (6") inch section horizontally on the ground and burying by ramping the soil up to the control fence.
B. Maintain sedimentation control system throughout the contract period and remove all such temporary features when directed. Any damaged during construction shall be replaced at no additional cost to the Owner.
C. Sediment buildup shall be removed from behind fences before it exceeds six (6") inches in depth. Sedimentation control system shall be inspected weekly and repaired/replaced as necessary. Additional inspections may be required prior to or immediately following any manor rainstorms. Sedimentation control systems shall be removed at the completion of the project.
TEMPORARY EROSION AND SEDIMENT CONTROL 2.23
01 57 13-4 3185.090.001
3.04 CRUSHED STONE DIKES
A. Install crushed stone dikes in permanent ditches where called for on plan or where as directed by the Owner/Engineer.
3.05 TEMPORARY SEEDING
A. Temporary seed shall be spread using broadcast or mechanical means.
3.06 TEMPORARY SEDIMENT TRAP
A. Temporary sediment traps shall be constructed where shown on the plans or as directed by the Owner/Engineer. Traps shall be constructed as shown on the Contract Drawings and as required by the "Connecticut Guidelines for Soil Erosion and-Sedimentation Control" (2002).
3.07 INLET SEDIMENTATION CONTROL DEVICE
A. Inlet sedimentation control devices shall be installed at each catch basin grate inlet. Appropriate models shall be selected depending on the type and size catch basin to be protected. Install and maintain in accordance with manufacturer’s recommendations and requirements.
3.08 REMOVAL AND CLEANUP
A. All temporary erosion control facilities when ordered by the Engineer shall be removed in a neat and workmanlike manner, and shall also include removal and disposal of accumulated silt.
B. Sediment deposits are to be removed when they reach approximately one-half the height of the device, i.e. sedimentation control fence, haybales, etc.
Accumulations of one-half of the wet storage volume in any temporary sediment trap will be used as criteria for commencement of cleaning operation. Disposal of materials removed during cleaning operations shall be the responsibility of the Contractor. Dispose material off-site or as directed by the Owner and/or Engineer.
2.23 DUST CONTROL
3185.090.001 01 57 20-1
SECTION 01 57 20
DUST CONTROL
PART 1 - GENERAL
1.01 DESCRIPTION
A. Furnish and spread materials to control dust throughout the project area as directed by the Owner and/or Engineer.
B. The furnishing of a pickup sweeper and utilizing it to remove earth and/or dust producing materials from pavement for the purpose of allaying dust conditions.
1.02 RELATED WORK
A. Section 31 23 17, Excavation – Blasting Not Allowed
1.03 QUALITY ASSURANCE
A. Where Form 818 is referred to, it means "State of Connecticut Department of Transportation Standard Specifications for Roads, Bridges and Incidental Construction, Form 818, 2020" and including all Supplemental Specifications through date of bid advertisement.
PART 2 - PRODUCTS
2.01 CALCIUM CHLORIDE
A. Calcium chloride will not be allowed on this project.
2.02 WATER FOR DUST CONTROL
A. Water for dust control shall be potable.
DUST CONTROL 2.23
01 57 20-2 3185.090.001
PART 3 - EXECUTION
3.01 CONSTRUCTION METHODS
A. All of the Contractor's work which may contribute to dusty conditions plus any of the Contractor's work which involves vehicular movement over unpaved surfaces shall be monitored and remedied under the requirements of this Section.
B. Construction methods for this work are as described in Form 818, Article 9.43.03 for "Water for Dust Control".
C. Sweeping shall be in conformance with Form 818, Article 9.39.03. In areas where the pickup sweeper cannot be used efficiently, sweeping shall be done by hand or other acceptable means. Water trucks shall be capable of applying a uniform spread of water over the surface.
2.23 CONSTRUCTION STAKING
3185.090.001 01 71 23-1
SECTION 01 71 23
CONSTRUCTION STAKING
PART 1 - GENERAL
1.01 DESCRIPTION
A. The work under this item shall consist of all construction layout and reference staking necessary for the proper control and satisfactory completion of all work on the project.
1.02 RELATED WORK
A. Section 01 43 00, Quality Control and Assurance
B. Section 31 23 17, Excavation – Blasting Not Allowed
C. Section 31 05 12, Common Fill
1.03 QUALITY ASSURANCE
A. Where Form 818 is referred to, it means "State of Connecticut Department of Transportation Standard Specifications for Roads, Bridges and Incidental Construction, Form 818, 2020" and including all Supplemental Specifications through date of bid advertisement.
1.04 SUBMITTAL
A. No submittals are required.
PART 2 - PRODUCTS
2.01 GENERAL
A. Stakes shall be of the quality specified in Form 818, Article 9.80.02.
CONSTRUCTION STAKING 2.23
01 71 23-2 3185.090.001
PART 3 - EXECUTION
3.01 GENERAL
A. The work shall conform to Form 818, Article 9.80.03 except as amended below:
1. Paragraph 1 of Article 9.80.03 is deleted.
2. The Contractor will be provided information pertaining to all available control points and bench marks prior to the start of work.
3. The Contractor shall be responsible for correcting all errors which could have been eliminated by verifying existing grades prior to beginning work.
2.23 CONTRACT CLOSEOUT
3185.090.001 01 77 00-1
SECTION 01 77 00
CONTRACT CLOSEOUT
PART 1 - GENERAL
1.01 DESCRIPTION
A. Closeout Procedures
B. Final Cleaning
C. Adjusting
D. Project Record Documents
E. Warranties
1.02 CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's inspection.
B. Provide submittals to Engineer and Owner that are required by governing or other authorities.
C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.
1.03 FINAL CLEANING
A. Execute final cleaning prior to final completion.
B. Clean equipment and fixtures to a sanitary condition.
C. Clean debris from leachate collection and drainage systems.
D. Clean site; sweep paved areas, rake clean landscaped surfaces.
E. Remove waste and surplus materials, rubbish, and construction facilities from the site.
1.04 ADJUSTING
A. Adjust operating Products and equipment to ensure smooth and unhindered operation.
CONTRACT CLOSEOUT 2.23
01 77 00-2 3185.090.001
1.05 PROJECT RECORD DOCUMENTS
A. Maintain on site, one clean set of the following record documents; record actual revisions to the Work:
1. Contract Drawings
2. Technical Specifications
3. Addenda
4. Modifications to the Agreement
5. Reviewed shop drawings, product data, and samples
6. Up to date as-built drawings.
B. Store Record Documents separate from documents used for construction.
C. Record information concurrent with construction progress.
D. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and Modifications.
E. Shop Drawings: Legibly mark each item to record actual construction including:
1. Field changes of dimension and detail.
2. Details not on original Contract Drawings.
F. Record Drawings: Record drawings shall be prepared at a scale of 1" = 50' with a 1-foot contour interval, unless otherwise directed by the Engineer. All record drawings shall be signed and sealed by a Surveyor licensed in the State of Connecticut. The Contractor is to submit two (2) prints for each record drawing required as well as an electric format in Auto CAD 2011 or later and a signed and stamped digital scan in an Adobe “.pdf” format. Prior to completion the Contractor shall coordinate with the Engineer on layer names and format. The Record Drawings must include:
1. Measured depths of excavation, subgrade layer grades, pipe inverts and locations, leachate clean-out inverts locations, locations of liner penetrations and other key design features.
2. Field changes of dimension and detail.
3. Details not on original Contract Drawings.
G. Delete Design Engineer title block and seal from all documents.
H. Submit documents to Engineer to achieve final completion.
1.06 OPERATION AND MAINTENANCE DATA
A. Submit three sets prior to final completion, bound in 8-1/2 x 11 inch text pages, three D side ring binders with durable plastic covers.
2.23 CONTRACT CLOSEOUT
3185.090.001 01 77 00-3
B. Prepare binder covers with printed title "OPERATION AND MAINTENANCE INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required.
C. Internally subdivide the binder contents with permanent page dividers, logically organized as described below; with tab titling clearly printed under reinforced laminated plastic tabs.
D. Contents — Prepare a Table of Contents for each volume, with each Product or system description identified, type on 24-pound white paper.
E. Part 1 — Directory, listing names, addresses, and telephone numbers of Engineer, Contractor, Subcontractors, and major equipment suppliers.
F. Part 2 — Operation and maintenance instructions, arranged by system and subdivided by specification section. For each category, identify names, addresses, and telephone numbers of Subcontractors and suppliers. Identify the following:
1. Significant design criteria.
2. List of equipment.
3. Parts list for each component.
4. Operating instructions.
a. Maintenance instructions for equipment and systems.
b. Maintenance instructions for special finishes, including recommended cleaning methods and materials and special precautions identifying detrimental agents.
G. Part 3 — Project documents and certificates, including the following:
1. Shop drawings and product data.
2. Certificates.
3. Photocopies of warranties and bonds.
H. Submit one copy of completed volumes in final form 15 days prior to final inspection. This copy will be returned after final inspection, with Engineer comments. Revise content of documents as required prior to final completion.
I. Submit final volumes revised, within ten days after final inspection.
CONTRACT CLOSEOUT 2.23
01 77 00-4 3185.090.001
1.07 WARRANTIES
A. Provide duplicate notarized copies.
B. Execute and assemble documents from Subcontractors, suppliers, and manufacturers.
C. Provide Table of Contents and assemble in three D side ring binder with durable plastic cover.
D. Submit prior to final completion.
1.08 SPARE PARTS AND MAINTENANCE MATERIALS
A. Provide products, spare parts, maintenance and extra materials in quantities specified in individual specification Sections.
B. Deliver to Project site; obtain receipt prior to final completion.
PART 2 - PRODUCTS
[NOT USED]
PART 3 - EXECUTION
2.23 COMMON FILL
3185.090.001 31 05 12-1
SECTION 31 05 12
COMMON FILL
PART 1 - GENERAL
1.01 DESCRIPTION
A. Under this Section, the Contractor shall furnish all labor, materials and equipment for Common Fill and Select Common Fill Materials, as shown on the Plans, as specified, and/or directed.
B. Work under this Section shall include, but not necessarily be limited to excavating, transporting, dumping, spreading, compacting, and testing common fill materials in the locations and to the depths and grades shown on the Contract Drawings or as directed by the Engineer.
C. Common Fill will be used for the MSE berm retained backfill area, to construct the diversion swale berms, perimeter swale containment, and other miscellaneous locations indicated in the Contract Drawing or as directed by the Engineer.
D. Select Common Fill will be used to construct the MSE berm reinforced fill area or as directed by the Engineer.
1.02 REFERENCE STANDARDS
A. The following is a list of standards that may be referenced in this Section:
1. American Association of State Highway Transportation Officials
(AASHTO):
a. M147, Standard Specification for Materials for Aggregate and
Soil-Aggregate Subbase, Base and Surface Courses.
b. T104, Standard Method of Test for Soundness of Aggregate by use of Sodium Sulfate or Magnesium Sulfate
c. T180, Standard Specification for Moisture-Density Relations of
Soils Using a 10-lb Rammer and a 18-in. Drop.
2. ASTM International (ASTM):
a. C88, Standard Test Method for Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate.
b. C136, Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates.
c. D422, Standard Test Method for Particle-Size Analysis of Soils
d. D698, Standard Test Method for Laboratory Compaction
Characteristics of Soil Using Standard Effort (12,400 ft-lbf/ft3).
e. D1557, Standard Test Methods for Laboratory Compaction
Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3).
f. D2487, Standard Classification of Soils for Engineering Purposes
(Unified Soil Classification System).
COMMON FILL 2.23
31 05 12-2 3185.090.001
g. D2922, Standard Test Method for Density of Soil and Soil- Aggregate by Nuclear Methods (Shallow Depth)
h. D4318, Standard Test Method for Liquid Limit, Plastic Limit, and Plasticity Index of Soils.
i. D4767, Standard Test Method for Consolidated Undrained Triaxial Compression Test for Cohesive Soils.
j. D6938, Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
1.03 SUBMITTALS
A. Materials Source: Name of imported materials suppliers and source.
B. The Contractor shall submit to the Engineer for approval all prequalification testing for proposed Common and Select Common fill materials for each source in accordance with testing requirements and methods outlined in Article 3.02 A.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Common Fill Material:
1. Common Fill Material shall be natural soil, free from excessive moisture, frost, stumps, trees, roots, sod, muck, marl, vegetable matter or other unsuitable materials.
2. Common Fill shall be excavated on-site material and/or imported by the Contractor and hauled to Owner/Engineer designated stockpile locations.
Acceptable material shall be well graded from fine to coarse. Stones, if any, shall not exceed six (6) inches in greatest dimension. All materials shall be suitable for compaction in layers not exceeding twelve (12) inches in loose thickness and shall remain stable when wet.
3. Common Fill shall conform to the following soil parameters:
a. Grading (percent passing sieve size):
1) 6-inch: 100 percent passing.
2) No. 200 Sieve: 0-15 percent passing
b. The portion of the reinforced backfill passing the No. 40 sieve shall have a liquid limit of less than 40 and a plasticity index less than 20.
c. USCS classification shall be low or non-plastic soils.
d. Common Fill shall have a minimum internal friction angle (i.e.
phi) of 33 degrees or greater (effective stress basis as demonstrated by direct shear or triaxial shear strength [CIU] under loading conditions of 2 ksf, 4 ksf, and 8 ksf at 90-percent of the maximum Modified Proctor dry density with a moisture content within 3-
3185.090.001 31 05 12-3 percent of optimum. Materials not meeting the required internal friction angle may be considered if results of shear strength testing noted above result in the following peak shear strengths at required loading:
a) Peak Shear Strength Required
i) 2 ksf: 1,298 psf
4 ksf: 2,598 psf 8 ksf: 5,195 psf
e. Common fill shall be substantially free of shale or other soft poor durability particles. The material shall have a magnesium sulfate soundness loss of less than 30 percent after four cycles or a sodium sulfate value loss less than 15 percent after five cycles in accordance with AASHTO T104.
B. Select Common Fill Material:
1. Select Common Fill Material shall be natural soil, free from excessive moisture, frost, stumps, trees, roots, sod, muck, marl, vegetable matter or other unsuitable materials.
2. Select Common Fill shall be imported by the Contractor and hauled to Owner/Engineer designated stockpile locations. Acceptable material shall be well graded from fine to coarse. Stones, if any, shall not exceed four
(4) inches in greatest dimension. All materials shall be suitable for compaction in layers not exceeding nine (9) inches in compacted thickness and shall remain stable when wet.
3. Select Common Fill shall conform to the following soil parameters:
a. Grading (percent passing sieve size):
Sieve Size Percent Passing 4” 100 3” 100-90 2” 100-70
1” 100-50 No. 40 0-60 No. 200 0-15
b. The portion of the reinforced backfill passing the No. 40 sieve shall have a liquid limit of less than 40 and a plasticity index less than 6.
c. USCS classification shall be low or non-plastic soils.
d. Effective friction angle shall have a minimum internal friction angle (i.e. phi) of 33 degrees or greater at or below 5 percent strain (effective stress basis as demonstrated by direct shear or triaxial shear strength [CIU] under normal loading of 2 ksf, 4 ksf, and 8 ksf at 90-percent of the maximum Modified Proctor dry density with a moisture content within 3-percent of optimum.
e. Select Common fill shall be substantially free of shale or other soft poor durability particles. The material shall have a magnesium sulfate soundness loss of less than 30 percent after four cycles or a
31 05 12-4 3185.090.001 sodium sulfate value loss less than 15 percent after five cycles in accordance with AASHTO T104.
PART 3 - EXECUTION
3.01 PLACEMENT
A. The entire surface to be covered with select common fill and/or common fill shall be stripped of all grass, vegetation, top soil, rubbish, or other unsuitable materials before backfilling.
B. In general, select common fill and common fill shall be placed in horizontal layers not exceeding nine (9) and twelve (12) inches respectively, in loose thickness and shall be compacted according to the criteria and tolerances of Article 3.03.
1. For zones where compaction is accomplished with hand operated equipment, fill shall be placed in horizontal layers not exceeding ten (10) inches in loose thickness.
C. Subgrade for common fill and select common fill placement shall be leveled and proof rolled by the Contractor utilizing a loaded truck with 18 kip axle loads and approved by the Engineer prior to the placement of the overlying select common fill or common fill.
1. Where unsuitable subgrade material is identified by the Engineer, the unsuitable material shall be over excavated until suitable material is identified and replaced with free draining aggregate material installed to the criteria contained within the this Section.
D. Subgrade for the retained backfill system shall be approved by the Engineer prior to the placement of overlying layers.
This is the start of the file's text. The full file is on GovTribe.