This file is an appendix containing detailed feature work lists for the Walsen Project mine closure contract in Colorado. The document outlines specifications for Item 4.0 (Install Mine Closures) encompassing eight distinct mine features (W01 through W08) and Item 5.0 (Install Maintenance Mine Closures) covering three maintenance features. The closure work involves a combination of excavation, backfilling, and erosion control measures tailored to each feature's characteristics. Feature W01 is a 30-by-27-foot sinkhole requiring 754 cubic yards of imported backfill material and 110 linear feet of wattles; W02 is a 61-by-55-foot subsidence feature requiring 261 cubic yards of imported material and 150 linear feet of wattles; W03 is a 41-by-63-foot subsidence feature requiring 251 cubic yards of imported material and 80 linear feet of wattles; W04 is a small 3.5-by-5-foot sinkhole requiring 1 cubic yard of onsite material with no wattles; W05 is a large 201-by-170-foot sinkhole requiring 3,318 cubic yards of imported material and 200 linear feet of wattles; W06 is a 4-by-5-foot sinkhole requiring 2 cubic yards of imported material and 25 linear feet of wattles; W07 is a 21-by-19-foot subsidence feature requiring 23 cubic yards of imported material and 60 linear feet of wattles; and W08 is a 6-by-6-foot sinkhole utilizing a monolithic concrete plug (8 cubic yards of concrete and 10 cubic yards of rockfill) with 190 linear feet of wattles. The maintenance work includes grading approximately 0.35 acres encompassing nine subsidence features with 300 linear feet of wattles, backfilling a 2-by-3.5-foot shaft with 0.3 cubic yards of material, and managing a 35-by-35-foot air shaft requiring removal of 60 cubic yards of debris and backfilling with onsite waste material and 50 linear feet of wattles.

The document specifies detailed closure methods, including machine backfill with imported or onsite material meeting specific grading requirements with medium diameters of approximately 12 inches and sufficient finer particles to minimize voids. Most features are addressed under Section 2.0 specifications, with W08 utilizing Section 7.0 specifications for monolithic plug installation. All backfill volumes are calculated using geometric assumptions such as half-ellipsoid or oval configurations based on feature dimensions and depth. Special considerations include proximity to high-voltage overhead powerlines at features W01 and W02, requirements to preserve existing trees during grading operations, and provisions allowing contractors to reuse existing onsite wattles if they meet bid specifications. The contractor is responsible for obtaining landfill invoices for debris disposal at the air shaft feature and ensuring all concrete samples are provided to the Project Manager for testing purposes.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item 4.0: Install Mine Closures Walsen Table 1.0 – Feature Work List

Feature ID Type Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

W01 Sink Hole

Excavated:30ft by 27ft

Eroded:30ft by 27ft

Present:30ft by 27ft

Depth:32 ft Lining:Other Drainage:No

Machine Backfill

Section 2.0

518148.2825 1179,

4162675.041 28458

The feature is located approx. twenty-five (25) feet north of high voltage, overhead, powerlines. Excavate along perimeter until all sides of feature are bound by stable bed rock.

Excavate ramp down to the bottom of the hole. Ramp is intended to be parallel to existing mine workings; to create a stable and safe work area. Backfill feature with imported material: backfill shall consist of a hard, durable, and well graded material with a medium diameter of approximately twelve

(12) inches and sufficient finer particles to minimize the presents of voids. Install one hundred and ten (110) LF of wattles along downslope perimeter of feature. Rockfill IS NOT Required.

The total backfill volume is estimated at seven hundred and fifty-four (754) cubic yards of imported material. This was calculated by multiplying the surface area of the oval feature by its depth.

Excavation will require a larger excavator such as a CAT 325 Excavator (or approved equivalent).

Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

W02 Subsidence Feature

Excavated:61ft by 55ft

Eroded:61ft by 55ft

Present:61ft by 55ft

Depth:4 ft Lining:Rock +

Timber Drainage:No

Machine Backfill Section 2.0

518138.6115 41593,

4162613.075 49521

The feature is located underneath overhead powerlines. Excavate to determine extent of subsidence. Machine backfill with imported material; backfill shall consist of a hard, durable, and well graded material with a medium diameter of approximately twelve

(12) inches and sufficient finer particles to minimize the presents of voids. Install one hundred and fifty (150) LF of wattles along downslope perimeter of closure. Rockfill IS NOT Required.

The total backfill volume is estimated at two hundred and sixty-one (261) cubic yards of imported fill material. This was calculated by assuming the feature is a half ellipsoid and calculating the volume.

W03 Subsidence Feature

Excavated:41ft by 63ft

Eroded:41ft by 63ft

Present:41ft by 63ft

Depth:5 ft Lining:Other Drainage:No

Machine Backfill Section 2.0

518125.4431 41507,

4162692.865 82402

Machine backfill with imported material;

backfill shall consist of a hard, durable, and well graded material with a medium diameter of approximately twelve (12) inches and sufficient finer particles to minimize the presents of voids. Install eighty (80) LF of wattles along downslope perimeter of closure.

Rockfill IS NOT Required.

The total backfill volume is estimated at two hundred and fifty-one (251) cubic yards of imported material. This was calculated by assuming both sides of the figure 8 shaped feature are individual, half-ellipsoids and summing the two volumes.

Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

W04 Sink Hole

Excavated:3.5ft by 5ft Eroded:3.5ft by

5ft Present:3.5ft by

5ft Depth:3 ft

Lining:Other Drainage:No

Machine Backfill Section 2.0

518101.1039 09745,

4162723.938 91824

Machine backfill with onsite material; Total backfill volume is estimated at one (1) cubic yard. This was calculated by assuming the feature is a half-ellipsoid.

Wattles are NOT required. Rockfill IS NOT Required.

W05 Sink Hole

Excavated:201ft by 170ft

Eroded:201ft by 170ft

Present:201ft by 170ft

Depth:5 ft Lining:Other Drainage:No

Machine Backfill Section 2.0

517901.9583 7195,

4162870.817 18573 well graded material with a medium diameter of approximately twelve (12) inches and sufficient finer particles to minimize the presents of voids. Install two hundred (200) LF of wattles along downslope perimeter of closure. Rockfill IS NOT Required.

The total backfill volume is estimated at three-thousand, three-hundred and eighteen (3,318) cubic yards of imported material. This was calculated by summing the areas of the six subsidence features, assuming each feature takes the shape of a half-ellipsoid.

Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

W06 Sink Hole

Excavated:4ft by 5ft

Eroded:4ft by 5ft Present:4ft by 5ft

Depth:3 ft Lining:Other Drainage:No

Machine Backfill Section 2.0

517878.3652 53244,

4162897.578 09966 well graded material with a medium diameter of approximately twelve (12) inches and sufficient finer particles to minimize the presents of voids. Install twenty five (25) LF of wattles along downslope perimeter of closure.

Rockfill IS NOT Required.

The total backfill volume is estimated at two

(2) cubic yards of imported material. This was calculated by multiplying the surface area of the oval feature by its depth.

W07 Subsidence Feature

Excavated:21ft by 19ft

Eroded:21ft by 19ft

Present:21ft by 19ft

Depth:3 ft Lining:Other Drainage:No

Machine Backfill Section 2.0

518176.6481 05027,

4162596.825 23708

Excavate to find the extent of the void.

backfill shall consist of a hard, durable, and well graded material with a medium diameter of approximately twelve (12) inches and sufficient finer particles to minimize the presents of voids. Install sixty (60) LF of wattles along downslope perimeter of closure.

Rockfill IS NOT Required.

The total backfill volume is estimated at twenty-three (23) cubic yards of imported material. This was calculated by multiplying the surface area of the half ellipsoid feature by its depth.

Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

W08 Sink Hole

Excavated:6ft by 6ft

Eroded:6ft by 6ft Present:6ft by 6ft

Depth:6 ft Lining:Other Drainage:No

Monolithic Plug Section 7.0

518275.8593 82076,

4162522.771 70515

Excavate the perimeter and bottom of the feature to find the full extent of the void.

Secure opening with a monolithic plug (eight

(8) cubic yards concrete and ten (10) cubic yards of imported rockfill).

At least seven (7) days after the concrete has been poured, the contractor may backfill the remainder of the opening with onsite materials.

Install one hundred and ninety (190) LF of wattles along downslope perimeter of closure.

The contractor may re-use the existing wattles onsite if they meet specifications in Bid Item 3.0.

The Project Manager will take cylinder samples of concrete.

Item 5.0 Install Maintenance Mine Closures - Walsen Table 2.0 – Feature Work List

Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

107Walsen -Area1SF1

Subsidence Feature

Excavated:25ft by 12ft

Eroded:25ft by 12ft

Present:25ft by 12ft

Depth:6 ft Lining:N/A

Drainage:No

Grade N/A

517960.6447 06412,

4163167.107 08708

The area consists of nine (9) individual subsidence features requiring maintenance.

Grade the site to eliminate the saddles between each feature, ensuring improved drainage, and blend the depressions seamlessly into the surrounding topography.

Finally, install three hundred (300) LF of wattles along the downslope perimeter for erosion control.

Area to be graded is approximately 0.35 acres. Take care not to disturb the existing trees.

704 HL-06 Shaft

Excavated:2ft by 3.5ft

Eroded:2ft by 3.5ft

Present:2ft by 3.5ft

Depth:1.5 ft Lining:N/A

Drainage:No

Machine Backfill Section 2.0

517707.1943 21651,

4162920.940 51989

Excavate around the perimeter of the feature and backfill with onsite material. Backfill will require 0.3 cubic yards of material. Wattles are NOT Required. Rockfill IS NOT Required.

Item 5.0 Install Maintenance Mine Closures - Walsen Table 2.0 – Feature Work List

Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

748 RH-03 Air Shaft

Excavated:35ft by 35ft

Eroded:35ft by 35ft

Present:35ft by 35ft

Depth:5 ft Lining:Rock Drainage:No

Machine Backfill Section 2.0

516570.2116 09127,

4165463.248 90167

An estimated sixty (60) cubic yards of debris must be removed from feature. All trash and debris shall be hauled to a county approved landfill. Landfill invoices shall be provided by the Contractor.

Excavate the sinkhole to a solid bottom and machine backfill with the on-site waste pile material located approximately three hundred

(300) feet south-east of feature 748 RH-03.

Install fifty (50) LF of wattles along the downslope perimeter. The contractor may reuse existing onsite wattles if they meet the specifications outlined in Bid Item 3.0.

Rockfill IS NOT Required.