APPENDIX A SPECIFICATIONS.pdf

PDF 175 KB Posted

Attached to
Aztec Water Treatment Facility Clearwell Expansion
Solicitation number
2026-879
Issued by
San Juan County, New Mexico

About this file

This document is a technical specification section (01 20 00) for Price and Payment Procedures for the Aztec Water Plant Clearwell Expansion project, set for construction in 2025. The specification outlines comprehensive procedures for progress payments, change orders, and final payment applications for the construction contract. It provides detailed instructions for contractors on preparing and submitting payment applications, including requirements for a Schedule of Values, documentation of work completed, and processes for managing contract modifications.

The document specifies that payment applications must use specific forms (EJCDC C-620), include detailed line-item breakdowns, and be submitted electronically and in hard copy. Contractors must provide extensive documentation for change orders, including quantities of products, labor, equipment, taxes, overhead, and profit justifications. The payment procedures require submission of supporting documents such as construction progress schedules, partial lien releases, and affidavits for stored products. Change orders can be initiated by either the Engineer or the Contractor, with specific protocols for pricing, documentation, and approval processes.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE AND PAYMENT

PROCEDURES

01 20 00 - 1

2025-09-16 Aztec Water Plant Construction Set CLEARWELL EXPANSION

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Documentation of changes in Contract Price and Contract Time.

C. Change procedures.

D. Correlation of Contractor submittals based on changes.

E. Procedures for preparation and submittal of application for final payment.

1.02 RELATED REQUIREMENTS

A. EJCDC C-410, Bid Form for Construction Contract.

B. EJCDC C-700, Article 15

C. Section 01 23 00 - Alternates: Payment procedures relating to bid alternates.

D. Section 01 78 00 - Closeout Submittals: Project record documents.

1.03 SCHEDULE OF VALUES

A. EJCDC C-700, Article 2

B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft to Owner for approval.

C. Forms filled out by hand will not be accepted.

D. Submit Schedule of Values in triplicate within 15 days after date of Owner-Contractor Agreement.

E. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification section. Identify site mobilization.

F. Include in each line item, the amount of Allowances specified in this section.

G. Revise schedule to list approved Change Orders, with each Application For Payment.

1.04 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Submit at intervals stipulated in the Agreement.

B. Form to be used: EJCDC C‐620 Contractor's Application for Payment

C. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Owner for approval.

D. Forms filled out by hand will not be accepted.

E. For each item, provide a column for listing each of the following:

1. Item Number.

2. Description of work.

3. Scheduled Values.

4. Previous Applications.

5. Work in Place and Stored Materials under this Application.

6. Authorized Change Orders.

7. Total Completed and Stored to Date of Application.

8. Percentage of Completion.

9. Balance to Finish.

10. Retainage.

F. Execute certification by signature of authorized officer.

G. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored products.

APPENDIX A

01 20 00 - 2

H. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of work.

I. Submit one electronic and three hard-copies of each Application for Payment.

J. Include the following with the application:

1. Transmittal letter as specified for submittals in Section 01 30 00.

2. Construction progress schedule, revised and current as specified in Section 01 30 00.

3. Partial release of liens from major subcontractors and vendors.

4. Affidavits attesting to off-site stored products.

K. When Architect requires substantiating information, submit data justifying dollar amounts in question. Provide one copy of data with cover letter for each copy of submittal. Show application number and date, and line item by number and description.

1.05 MODIFICATION PROCEDURES

A. Submit name of the individual authorized to receive change documents and who will be responsible for informing others in Contractor's employ or subcontractors of changes to the Contract Documents.

B. For minor changes not involving an adjustment to the Contract Price or Contract Time, Owner will issue instructions directly to Contractor.

C. For other required changes, Engineer will issue a document signed by Owner instructing Contractor to proceed with the change for subsequent inclusion in a Change Order.

1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.

2. Promptly execute the change.

D. For changes for which advance pricing is desired, Engineer will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid. Contractor shall prepare and submit a fixed price quotation within seven days.

E. Contractor may propose a change by submitting a request for change to Engineer, describing the proposed change and its full effect on the work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation.

Document any requested substitutions in accordance with Section 01 60 00.

F. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.

1. For change requested by Engineer for work falling under a fixed price contract, the amount will be based on Contractor's price quotation.

2. For change requested by Contractor, the amount will be based on the Contractor's request for a Change Order as approved by Owner.

3. For pre-determined unit prices and quantities, the amount will be based on the fixed unit prices.

4. For change ordered by Owner without a quotation from Contractor, the amount will be determined by Owner based on the Contractor's substantiation of costs as specified for Time and Material work.

G. Substantiation of Costs: Provide full information required for evaluation.

1. On request, provide the following data:

a. Quantities of products, labor, and equipment.

b. Taxes, insurance, and bonds.

c. Overhead and profit.

d. Justification for any change in Contract Time.

e. Credit for deletions from Contract, similarly documented.

2. Support each claim for additional costs with additional information:

a. Origin and date of claim.

b. Dates and times work was performed, and by whom.

c. Time records and wage rates paid.

01 20 00 - 3

d. Invoices and receipts for products, equipment, and subcontracts, similarly documented.

3. For Time and Material work, submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract.

H. Execution of Change Orders: Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

I. After execution of Change Order, promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Price.

J. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit.

K. Promptly enter changes in Project Record Documents.

1.06 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Price, previous payments, and sum remaining due.

B. Application for Final Payment will not be considered until the following have been accomplished:

1. All closeout procedures specified in Section 01 70 00.

END OF SECTION