J.3 Answers to Questions.pdf
PDF 96 KB Posted
- Solicitation number
- AOCSSB24R0028
- Issued by
-
Architect of the Capitol
About this file
This document is a set of Answers to Questions provided by the government in response to an RFP for Senate Office Buildings Conservation and Maintenance IDIQ contract #AOCSSB24R0028. The RFP is for conservation and maintenance services for historic sculptures and other architectural elements in the Senate Office Buildings. Key details include:
The "Not Applicable" statement next to the Factor 4 section indicates there is no page limit for the Corporate Past Performance factor. The government will provide lifts and ladders as appropriate for work above 6 feet. Electrical repairs may be required for some lighting restoration work. The government will de-install all lighting, and the maintenance work will focus on stabilization and cleaning, with in-gilding only if requested by the Office of the Senate Curator. Treatment proposals and condition assessments must be submitted in advance, and task orders will be issued after contract award, but no specific start date is provided.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment J.3
Answers to Questions Senate Conservation and Maintenance Services IDIQ
RFP # AOCSSB24R0028
Reference Page, Section, Paragraph
Offeror’s Question
Government’s Response
L.4.7 FACTOR 4 Next to this section, it states, “Not Applicable”. Does this mean this is not required for this RFP
Factor 4 outlined in section L.4.7 is part of the evaluation for this RFP, therefore it is required. The “Not Applicable” phrase means there is no page number limit for Factor 4 - Corporate Past Performance.
For lighting restoration work, will electrical repairs be required?
Yes, on some occasions this will be part of the requirement.
It was noted that some lighting elements will be removed for treatment, is the removal part of this scope of work?
The Government will de-install all lighting.
Is the intention to complete in-gilding of loss if found or just stabilization and cleaning?
Mostly stabilization and cleaning, unless otherwise requested by the Office of the Senate Curator.
Will condition assessment reports and work plans need to be submitted and approved before completing maintenance work?
Treatment proposals are expected in advance, condition assessments shall be required post maintenance work.
Will AOC be providing access for elements above 6ft?
Lifts and ladders will be provided by the Government as appropriate.
Is there a planned start date for the work? Task orders will be issued once the contract has been awarded.