Answers to Questions July 3 2024.pdf

PDF 174 KB Posted

Attached to
Pumping Station 10 Force Main Condition Assessment.
Solicitation number
MMSD, 2024, Pumping Station 10 Force Main Condition Assessment.
Issued by
Dane County, Madison City, Wisconsin

About this file

This document is a memorandum containing answers to questions asked at an optional pre-proposal meeting for the Pumping Station 10 Force Main Condition Assessment project, which is being solicited by the Madison Metropolitan Sewerage District. The project involves conducting a condition assessment of the force main serving Pumping Station 10, and the district provided details on the expected shutdown sequencing for the pumping stations during the assessment work, as well as the availability of video recordings and photos of the existing infrastructure. The proposal documents for this project are available on the district's website, and proposals are due by 5:00 p.m. CST on Friday, July 19, 2024, to be submitted via email.

The memorandum also clarifies that no verbal statements from district employees will be considered binding, and that all proposal responses and their contents will be public record. The district reserves the right to reject any or all proposals, or to waive any technicality and accept any proposal that may be advantageous to the district.

View the file

Other files

File Type Posted
RFP Condition Assessment PS10FM.docx DOCX document
Answers to Questions July 10 2024.pdf PDF
Answers to Questions July 15 2024.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Memorandum

To: Firms submitting proposals

From: Jen Hurlebaus

Date: July 3, 2024

Subject: Answers to Questions asked at July 2, 2024 Optional Pre-Proposal Meeting for the Pumping Station 10 Force Main Condition Assessment Project

Question 1: How long can the station be shut down?

Answer: We have logs of previous shut down sequences for reference; however, most of those examples are shutdowns of the upstream stations (Pumping Stations 13 and 14) while still pumping at Pumping Station 10. We expect to work through specific details and determine a shutdown sequencing plan during the project planning phase. In general, Pumping Station 14 can be shut down from 3 – 6am and Pumping Station 13 can be shut down from 5 – 8am, leaving the Contractor with approximately a 2-3 hour window from ~6:30am – 9am where flows at Pumping Station 10 would be reduced to about half of the average flow. There was one instance of shutting down Pumping Station 10 to televise the end of the force main; however, the high wet well level was reached within 90 minutes. Any planned shutdown of the station will need to be carefully planned and coordinated with District staff.

Question 2: Are the air release valves along the force main accessible?

Answer: GoPro Videos are available to view for structures MH10-24760 and MH10-23080.

Pictures are available for MH10-19623. Please send an email to jenh@madsewer.org to request a link to the videos and pictures.

Question 3: Does MH07-954 have a bolted down cover?

Answer: No. The cover is non-rocking. A GoPro video is also available for MH07-954 upon request.