Answer for Question 5 M-1 New spec.pdf
PDF 237 KB Posted
- Solicitation number
- CRFQ 0603 ADJ2600000022 4
- Issued by
- Kanawha County, West Virginia
About this file
This is a mechanical engineering specification sheet for HVAC renovation work at CFMO Building 1707 in Charleston, West Virginia, prepared by The Thrasher Group, Inc. for the West Virginia Army National Guard. The document provides detailed technical specifications for a complete HVAC system installation including symbol legends, abbreviations, general mechanical notes, demolition procedures, and equipment schedules. The project scope encompasses the installation of three rooftop units (RTU-1, RTU-2, and RTU-3), 27 variable air volume (VAV) terminal units with electric reheat coils, seven electric unit heaters (EUH-1 through EUH-7), and various ductwork, diffusers, grilles, and control components. The specifications detail specific manufacturer requirements (primarily Titus and AAON equipment), electrical connections (208/3 and 480/24 volt systems), and CFM (cubic feet per minute) requirements for each unit, with cooling capacities ranging from 620 to 5,685 CFM and heating loads specified for individual zones.
The document establishes comprehensive technical and operational requirements for contractors, including mandatory coordination with other trades, protection of existing equipment to be reused, proper cabling and grounding standards, and compliance with the International Fuel Code 2018 for gas sizing calculations. All ductwork is specified as Schedule 40 metallic pipe with internal clear dimensions, flexible connections at vibration-prone connections, and 1-inch ductliner in return air ducts. The project references 1981 and 2026 bid documents, with contractors required to verify existing conditions prior to bidding and adjust installation at no additional cost to the owner. The electrical connections range from 208/3 phase for VAV units and individual heaters to 480/24 volt transformers, with the total gas load specified at 660 MBH across the three rooftop units. The specification sheet was dated June 26, 2026, with Addendum No. 1 issued on July 15, 2025.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SYMBOL LEGEND
DESCRIPTIONSYMBOL
EQUIPMENT SYMBOL - SEE LIST ON DWGS.
RIGID AIR DUCT SYSTEM
FLEXIBLE DUCT
MANUAL CONTROL DAMPER (W/LOCKING DEVICE0
CEILING SUPPLY DIFFUSER
CEILING RETURN OR EXHAUST GRILLE
DUCT SIZE INSIDE DIMENSIONS - 24"W x 10"D
DUCT SIZE - 10" DIAMETER
THERMOSTAT / SENSOR
PLAN NOTE
NEW TO EXISTING
POINT OF DEMOLITION
24”x10”
10ӯ
T S
A
DIFFUSER SYMBOL - SEE SCHEDULE
NECK SIZE
DESIGN CUBIC FEE PER MINUTE OF AIR
QUANITY FOR ROOM OR SPACE
D1 8ӯ
(2)
ABBREVIATIONS
AFF ABOVE FINISHED FLOOR
BF BELOW FLOOR
BCU BLOWER COIL UNIT
CFM CUBIC FEET PER MINUTE
COP COEFFICIENT OF PERFORMANCE
CU CONDENSING UNIT
DN DOWN
DB DRY BULB
DU DUCTLESS UNIT
EA EXHAUST AIR
EAT ENTER AIR TEMPERATURE
EC ELECTRICAL CONTRACTOR
ECH ELECTRIC CEILING HEATER
EER ENERGY EFFICIENCY RATIO
EF EXHAUST FAN
ESP EXTERIOR STATIC PRESSURE
EUH ELECTRIC UNIT HEATER
EWH ELECTRIC WALL HEATER
FD FIRE DAMPER
FPD FEET PER MINUTE
GC GENERAL CONTRACTOR
GUH GAS UNIT HEATER
KW KILOWATTS
HP HORSEPOWER
L LOUVER
LAT LEAVING AIR TEMPERATURE
MAU MAKE-UP AIR UNIT
MH MOUNTING HEIGHT
MBH THOUSAND BTU/HR
MOD MOTORIZED DAMPER
NIC NOT INCLUDED IN CONTRACT
NTS NOT TO SCALE
O.A. OUTSIDE AIR
PC PLUMBING CONTRACTOR
PD PRESSURE DROP
RA RETURN AIR
RH RELATIVE HUMIDITY
RPM REVOLUTIONS PER MINUTE
RTU ROOFTOP UNIT
SA SUPPLY AIR
SD SMOKE DETECTOR
SF SUPPLY FAN
STR STARTER (MOTOR)
TS TIP SPEED
TSP TOTAL STATIC PRESSURE
(TYP) TYPICAL
TZ TRANSFORMER
UNO UNLESS NOTED OTHERWISE
W/ WITH
WH WATER HEATER
WB WET BULB
W/O WITHOUT
WP WEATHER PROOF
GENERAL MECHANICAL NOTES:
1. PROVIDE ALL MATERIALS AND EQUIPMENT AND PERFORM ALL LABOR REQUIRED TO
INSTALL COMPLETE AND OPERABLE HVAC SYSTEM AS INDICATED ON THE DRAWINGS,
AS SPECIFIED AND AS REQUIRED BY CODE.
2. CERTAIN ITEMS SUCH AS RISES AND DROPS IN DUCTWORK, ACCESS DOORS, VOLUME
DAMPERS, ETC., ARE INDICATED FOR CLARITY IN CERTAIN AREAS. THIS DOES NOT
RELIEVE THE CONTRACTOR OF PROVIDING THESE ITEMS NOT SHOWN IN OTHER
AREAS AS REQUIRED FOR A COMPLETE INSTALLATION.
3. UNLESS NOTED OTHERWISE, LOCATE ALL ROOM THERMOSTATS 5'-0" ABOVE FINISH
FLOOR.
4. ALL DUCTWORK SHALL CLEAR DOORS AND WINDOWS.
5. ALL DUCTWORK DIMENSIONS, AS SHOWN ON DRAWINGS, ARE INTERNAL CLEAR
DIMENSIONS. DUCT SIZE SHALL BE INCREASED IN SIZE TO COMPENSATE FOR
INTERNAL LININGS.
6. COORDINATE DIFFUSER, REGISTER, AND GRILLE LOCATIONS WITH ARCHITECTURAL
PLANS, LIGHTING, AND OTHER ITEMS LOCATED IN CEILING.
7. LOCATE ALL MECHANICAL EQUIPMENT FOR UNOBSTRUCTED ACCESS TO UNIT ACCESS
PANELS, CONTROLS, AND VALVING.
8. PROVIDE FLEXIBLE CONNECTIONS IN ALL DUCTWORK SYSTEMS CONNECTED TO AIR
HANDLING UNITS, FANS, AND OTHER EQUIPMENT THAT REQUIRE VIBRATION
ISOLATION. FLEXIBLE CONNECTIONS SHALL BE PROVIDED AT THE POINT OF
CONNECTION UNLESS NOTED OTHERWISE.
9. RUNS OF FLEXIBLE DUCTWORK SHALL NOT EXCEED 5 FEET.
10. ALL DUCTS SHALL BE GROUNDED ACROSS FLEXIBLE CONNECTIONS WITH FLEXIBLE
COPPER GROUNDING STRAPS.
11. TURNING VANES SHALL BE INSTALLED IN ALL RECTANGULAR DUCT ELBOWS THAT
EXCEED 45° CHANGE IN DIRECTION.
12. INSTALL 1" DUCTLINER IN FIRST 15' OF ALL RETURN AIR DUCTS.
13. SMOKE DETECTORS SHALL BE FURNISHED AND WIRED BY THE ELECTRICAL
CONTRACTOR. THE MECHANICAL CONTRACTOR SHALL INSTALL THE SMOKE
DETECTOR IN THE DUCTWORK.
14. CONTROL RELAYS SHALL BE WIRED BY THE ELECTRICAL CONTRACTOR. THE
MECHANICAL CONTRACTOR SHALL FURNISH AND INSTALL THE RELAY IN THE
EQUIPMENT.
1. COORDINATE HVAC DEMOLITION WITH OTHER TRADES AND GENERAL CONTRACTOR.
DO NOT DEMOLISH EQUIPMENT OR COMPONENTS WITHOUT APPROVAL.
2. UNDER NO CIRCUMSTANCE SHALL DEMOLITION CAUSE DAMAGE OR REMOVAL IN
WHOLE OR IN PART OF ANY STRUCTURAL MEMBER WITHOUT EXPRESS APPROVAL OF
THE GENERAL CONTRACTOR.
3. CAP AND PROTECT ANY EXPOSED EQUIPMENT, DUCT, PIPE OR ELECTRICAL CABLE /
CONDUIT THAT RESULTS FROM DEMOLITION. UNDER NO CIRCUMSTANCE WILL
DEMOLITION RESULT IN THE PERMANENT EXPOSURE OF ANY CHARGED OR LIVE
COMPONENT OR ANY EQUIPMENT TO BE RE-USED.
4. PROTECT ANY EQUIPMENT, SYSTEM, OR COMPONENT THEREOF THAT SHALL BE RE-
USED.
5. COORDINATE DISPOSAL OF ALL REMOVED ITEMS WITH THE GENERAL CONTRACTOR.
TURN OVER ANY COMPONENTS TO THE OWNER AS DESIGNATED IN CLEAN
CONDITION, WITHOUT DAMAGE, AND WITH OPENING SEALED. FURNISH RECEIPTS OF
PROPER DISPOSAL OF ALL ITEMS REMOVED TO THE GENERAL CONTRACTOR UPON
REQUEST. RECEIPTS SHALL INDICATE DISPOSAL IN ACCORDANCE WITH ALL LOCAL,
STATE AND FEDERAL REGULATIONS.
6. ALL DUCTWORK, PIPING AND EQUIPMENT SHOWN ON THE DRAWINGS WERE BASED ON
1981 AND 2026 BID DOCUMENTS, CONTRACTOR SHALL VERIFY ALL EXISTING DUCT AND
EQUIPMENT LOCATIONS PRIOR TO BID AND SHALL ADJUST INSTALLATION F NEW WORK
ACCORDINGLY AT NO ADDITIONAL COST TO OWNER.
DEMOLITION NOTES
VAV BOX SCHEDULE
VAV1-1
NOTES:
1-4TITUS DESV 325 4.5 SCR 55 95605 208/3
VAV 1-2
VAV 1-3
VAV 1-4
435 6.0 55 95700
310 4.0 55 95640
535 7.0 55 951080
305 4.0 55 95550
190 2.5 55 95415
330 4.5 55 95420
1-4
1-4
1-4
1-4
1-4
1-4
300 4.0 55 95635 1-4
445 6.0 55 95980 1-4
215 3.0 55 95525 1-4
125 2.0 55 95350 1-4
445 5.5 55 951010 1-4
280 3.5 55 95610 1-4
145 2.0 55 95360 1-4
200 2.5 55 95465 1-4
370 5.0 55 951060 1-4
220 3.0 55 95405 1-4
220 3.0 55 95450 1-4
670 9.0 55 951120 1-4
300 4.0 55 95695 1-4
210 3.0 55 95520 1-4
1. SINGLE-DUCT VAV TERMINAL UNIT WITH ELECTRIC REHEAT COIL WITH CONTROL PANEL, SCR ELECTRIC HEAT CONTROL, DIGITAL DISPLAY
ZONE SENSOR, 208/24 VOLT AND 480/24 VOLT TRANSFORMER.
2. DISCONNECT SWITCH AND POWER FUSE.
3. FOUR POINT AVERAGING TEMPERATURE SENSOR.
4. STANDARD ACTUATOR.
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
SCR
NOTES
MARK
SIZE
CFMCFM
KW
INLET
(VAV) HEATINGCOOLING
ELECTRIC REHEAT COIL
MANUFACTURER MODEL NO.
MAX. MIN.
STEPS (°F)
EAT
(°F)
LAT
(IN)
APDMBH VOLTS/PHASE
VAV 1-5
VAV 1-6
VAV 1-7
VAV 2-1
VAV 2-2
VAV 2-3
VAV 2-4
VAV 2-5
VAV 2-6
VAV 2-7
VAV 2-8
VAV 2-9
VAV 2-10
VAV 2-11
VAV 2-12
VAV 2-13
VAV 2-14
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
208/3
6" 8.54
10" 17.08
6" 10.24
6" 8.54
10" 30.74
6" 6.83
8" 11.95
10" 20.49
6" 6.83
8" 10.24
10" 20.49
8" 13.66
8" 10.24
8" 13.66
8" 15.37
6" 8.54
8" 13.66
10" 23.90
8" 13.66
8" 20.49
8" 15.37
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
TITUS DESV
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
RTU-1 AAON RN-013-3-0-GAAY-V0-21-000-A 2040 4410
1.05"
0.84"
5.0 2099
138.7
172.8
108.9
149.5
77.1/63.8 53/52
53/52
195.0
270.0
158.0
218.7
208/3
208/3
1-5
76.9/62.5
97.3
76.0 100.0 11.95/14.9
RTU-3 3490 0.75" 1701 102.2 91.21 53/52 158.0 106.376.7/62.1 65 90
RTU-2 2772
1868 208/3
86.0 110.0 11.17/15.19
49.0 70.0 12.84/15.783130 360
1-5
1-5
5.0
2.0
MANUF.
SEN. L.A.T.E.A.T.
MARK
NOTES:
MODEL NO. WEIGHT H.P.E.S.P. RPM
DB/WBMBH
TOTAL
MBH DB/WB MBH INPUT
TOTAL TOTAL
MBH OUTPUT
ROOFTOP UNIT SCHEDULE
CFM SUPPLY FAN COOLING HEATING
REMARKSVOLTS/PHASEL.A.T.E.A.T. MCA MOCP
1. PACKAGED DOWNFLOW VAV ROOFTOP UNIT WITH SINGLE POINT POWER WITH NON-FUSED DISCONNECT SWITCH, DUAL COMPRESSOR, PHASE FAILURE MONITOR, 2" THICK THROW AWAY FILTERS; POWERED CONVENIENCE GFi RECEPTACLE OUTLET; 100% COMPARATIVE ENTHALPY CONTROL ECONOMIZER WITH BAROMETRIC RELIEF DAMPER; EXHAUST FANS; HAIL GUARDS; MICROPROCESSOR CONTROLLER; BUILT IN DISCONNECT.
2. PROVIDE WITH FACTORY INSTALLED SENSORS FOR COIL LEAVING TEMP, DUCT HIGH LIMIT SWITCH, RETURN AIR TEMP, LEAVING AIR TEMP, RETURN AIR ENTHALPY, OUTSIDE AIR ENTHALPY, DIRTY FILTER, AND SUPPLY FAN AIR
PROVING.
3. PROVIDE CURB ADAPTOR.
4. PROVIDE WITH MODULATING GAS HEAT.
EER/IEERSUPPLY
AIR CFM
RETURN
AIR CFM
OUTSIDE
AIR CFM (MIN) QTY
AAON
AAON
RN-016-3-0-GAAY-V0-21-000-A
RN-011-3-0-GAAY-V0-21-000-A
5. PROVIDE RETURN AIR DUCT SMOKE DETECTOR.
MODEL NO.
NOTES:
MARK
EUH-1
KW BTU VOLTS / PHASE NOTESMANUFACTURER WEIGHT
(LBS)
QMARK MUH05-81 27 5.0 208/3 117.0
1. FAN-FORCED UNIT WALL HEATER WITH BUILT-IN THERMOSTAT; THERMAL OVERLOAD
PROTECTION; FAN DELAY SWITCH; POWER; MOUNTING BRACKETS.
EUH-2,3,4,5 QMARK MUH-10-8 38 10.0 208/3 134.1
EUH-6,7 QMARK MUH-15-8 53 15.0 208/3 151.2
ELECTRIC HEATER SCHEDULE
DESCRIPTIONUSEMODEL
NO.MANUFACTURERMARK NOTES
A. SIZE OF NECK FOR ABOVE ARE SHOWN ON PLAN.
B. SIZE OF GRILLE FOR ABOVE ARE SHOWN ON PLAN.
GENERAL NOTES:
1. STEEL
2. ALUMINUM
3. WHITE FINISH
NOTES:
D1
R1
R2
TITUS TMS
PAR
25RL
SUPPLY
RETURN
RETURN
SQUARE FULL LOUVER FACE CEILING DIFFUSER WITH FRAME
TYPE-3 FOR LAY-IN.
24"x24" SQUARE FLUSH PERFORATED FACE CEILING
DIFFUSER WITH FRAME TYPE-3 FOR LAY-IN.
1,3
2,3
2,3
TITUS
TITUS
D2 TITUS S300FS SUPPLY INDIVIDUALLY ADJUSTABLE BLADES DOUBLE DEFLECTION
GRILLE, WITH EXTRACTOR SET AT 45° ANGLE.
2,3
D3 TITUS 301RL SUPPLY ADJUSTABLE BLADES SUPPLY GRILLES WITH FRAME TYPE-1
FOR SURFACE MOUNT.
2,3
ADJUSTABLE BLADES RETURN GRILLES WITH FRAME TYPE-1
FOR SURFACE MOUNT.
GRILLE, REGISTER AND DIFFUSER SCHEDULE
GAS LOAD SCHEDULE
SIZING IN ACCORDANCE WITH INTERNATIONAL FUEL CODE 2018,
TABLE 402.4 (2) SCHEDULE 40 METALLIC PIPE AT 7" WC AND 300'
TOTAL DEVELOPED LENGTH. VERIFY PRESSURES AND EQUIPMENT
BTUS, ADJUST SIZES ACCORDINGLY.
RTU-1
RTU-2
RTU-3 195
IDENTIFICATION GAS LOAD (MBH)
TOTAL CONNECTION 660
SHEET No.
C
AD
F
IL
E:
PROJECT No.
DRAWN:
CHECKED:
DATE:
DATE:
LA
YO
U T
TA
B:
PL
O
T D
AT
E/
TI
M
E:
U
SE
R
P (304) 624-4108
600 WHITE OAKS BLVD.
P.O. BOX 940
BRIDGEPORT, WV 26330
www.thethrashergroup.com
F (304) 624-7831
N O
BY
D
AT
E D
ES
C
R
IP
TI
O
N
THE INFORMATION CONTAINED HEREIN IS
THE SOLE PROPERTY OF THE THRASHER
GROUP, INC. REPRODUCTION OF THESE
DOCUMENTS IN WHOLE, OR IN PART FOR
ANY REASON WITHOUT PRIOR WRITTEN
PERMISSION IS STRICTLY PROHIBITED.
COPYRIGHT © 2024
THE THRASHER GROUP, INC.
6/
/2
8:
:2
AM
Au to de sk
D oc s:
//W
VA
N
G C
FM
O
B
LD
G
H
VA
C R
EN
O
/W
VA
N G
_M
EP
_R
.rv t
JU
N
E
TT
G
C O
N
ST
R U
C
TI
O N
D O
C U
M
EN
TS
M1.01
LE
G
EN
D
, N O
TE
S
SC
H
ED
U
LE
S
TTG 07/15/2025
T60-11492
W
VA
N G
C
FM
O B
LD
G
H
VA
C
R
EN
O
VA
TI
O
N
C H
AR
LE
ST
O
N , W
ES
T
VI
R
G
IN
IA
LEGEND, NOTES &
SCHEDULES
KES 07/15/2025
W
ES
T
VI
R G
IN
IA
A R
M Y
N
AT
IO
N
AL
G
U
AR
D
TT
G
/2 6/
AD
D
EN
D
U M
N O
.1
| Sheets |
| M1.01 - LEGEND, NOTES & SCHEDULES |
File details come from the government source that posted it. Updated .