This document is a Statement of Work (SOW) for the renovation of 8 apartments (# 42 to # 49) at the Enclave Compound in New Delhi, India for the U.S. Embassy. The total floor area is approximately 11,000 sq. ft.

The key scope of work includes complete renovation of the bathrooms, laundry, and kitchens with new fixtures, plumbing, and electrical work. It also covers upgrading the living/dining rooms and bedrooms with new flooring, lighting, and electrical outlets. Additional work includes installing a new Kota stone patio, raising the staircase railing, and exterior/interior painting. The contractor is required to provide all labor, materials (except government-furnished items), equipment, and supervision to complete the project within 100 working days. Professional craftsmanship and safety compliance are emphasized. The U.S. Embassy will provide all materials needed for the renovation.

View the file

Other files

File Type Posted
QA sheet.xls XLS spreadsheet
Annexure-3-SOW-Apartments 50 to 54.pdf PDF
SOLICITATION-RENOVATION-37 THRU 54.pdf PDF
Annexure-1-SOW-Apartments 37 to 41.pdf PDF
COVER LETTER.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US EMBASSY, NEW DELHI

STATEMENT OF WORKS (Phase # 1) FOR RENOVATION OF APARTMENT # 42 to 49

ATENCLAVE COMPOUND

1.0 BRIEF DESCRIPTION OF WORK:

1.1 The United States Embassy, New Delhi has a requirement to repair and renovate

8 apartments (11000 sq.ft. floor area for both floors) at Enclave Compound as per SOW details.

1.2 Complete renovation of apartments with demolition of existing kitchen, bathrooms, laundry, store, removal of existing exterior uPVC doors / windows, removal of existing metal door at exterior store room, new wall/floor tiles for kitchen & bathroom, new plumbing pipe, new electrical wiring with conduit, switch/socket, new fitting/fixtures, new lights, new kitchen cabinets, new floor in entire apartment, installation of kota stone paving, installation of S/S manhole cover & gratings and complete interior/exterior painting.

1.3 Project requires a professional team journeyman to perform apartments renovation as per scope of work.

1.4 Contractors are advised to visit the site, verify requirements as mentioned in the

SOW.

1.5 Any ambiguity found later will be at the discretion of the contracting officer for any modification.

1.6 The contractor shall be given total 100 working days to complete this project.

2.0 GENERAL GUIDELINES

2.1 The Contractor shall provide all required labor, material (except the GFI), equipment, tools, ladder/scaffolding and supervision to complete the project.

2.2 Contractors are advised to conduct the site visit to understand the requirement and verify measurements.

2.3 Contractors are recommended to seek clarifications regarding this statement of work and site conditions at the time of walk thru from the COR of this project.

2.4 The contractors can write the uncleared queries to the contracting office after the walk thru.

2.5 Embassy contracting office will consult with COR and respond to all the queries in writing before the due date of the submission of quotes.

2.6 Embassy expects professional craftsmanship and supervision from the bidders.

Contractor is responsible to provide a quality assurance and quality control supervisor.

2.7 The contractor must adhere to the safety mandates explained in this document,

2.8 The contractor and his/ her staff must wear Personnel Protective Equipment

(PPE) while at embassy construction site. The contractor shall include the cost of the PPEs and other logistical expenses to manage the safety and PPE guidelines while bidding. The contractor shall comply with the PPE guidelines 100% of the time at USG facilities. Contractor will be countable for the delay caused by non-compliance.

2.9 No work will be allowed to perform at USG construction sites without the use of

PPE and the contractor will be accountable for the delays caused due to the safety issues.

2.10 PPE includes steel toe shoes, protective goggles, hard hats, coveralls and

COVID -19 protective masks.

2.11 The contractor will be held responsible and accountable for any deviations from the safety and PPE guidelines specified in this document.

2.12 All work shall be performed by skilled and competent crew.

2.13 The Contractor shall follow security and safety directions as mentioned in the statement of works and explained by the COR.

2.14 The Contractor shall submit the construction time-line /bar chart to the COR within 2 working days upon obtaining the letter to proceed from the contracting office.

2.15 The Contractor shall submit all the cut sheets / broachers and material samples for COR approval before delivery of material at site.

2.16 All materials shall be delivered, hoisted on the exterior and stored as per space allotted.

2.17 Contractor shall dispose of all the debris from the site and keep the site clean and in workable condition throughout the project duration.

2.18 Contractor shall install green felt barricading with required frame around the construction site. Why needed?

3.0 SCOPE OF WORK FOR REPAIR AND RENOVATION 8 APARTMENTS - # 42

to # 49.

Gross Area

Apt. # 42 to 45 – Kitchen, living/dining, laundry, two bedrooms and two bathroom – 1260 Sq. ft each apartment (both floor area).

Apt. # 46 to # 49 – Kitchen, living room, dining room, laundry + powder room, three bedrooms and two bathrooms – 1450 Sq.ft.-Each Apartment ( both floor area)

3.1 Upgradation of bathroom and laundry:

3.1.1 Remove existing fixtures/fittings, wall and floor tiles complete with plumbing and electrical fittings/fixtures, both surface mounted and hidden in walls.

Install new cold and hot water supply line (copper pipe) with fittings & control valve, inside the bathroom & laundry with embassy provided materials. Insulate both hot and cold-water pipeline with embassy provided insulation tape before concealing the pipes.

The new internal pipes shall be connected to the exterior pipe by the contractor as per the direction given by COR. The contractor shall do preparation for installation of wall hung W/C with conceal flush tank. Contractor shall do the pressure testing of all newly laid plumbing pipes before plastering.

3.1.2 Install new copper cold water supply to solar water heaters and copper return piple from solar to the apartment with insulation. All pipes at roof level shall be supported on raised metal stand provided by the embassy and are to be insulated for exterior installation.

3.1.3 Install new switch/sockets as per approved locations complete with rigid PVC conduit, PVC insulated 4.0 sq.mm. as well as 2.5 sq. mm copper wire and 2.5 sq.

mm. and 1.5 sq mm ground wire as per circuit standards. All conduits shall be recessed in the wall/ceiling. Each bathroom shall have 2- 5 amp outlet and 1 power outlet. All ceiling lights and wall lights shall be connected to main switch board. Do all related works including electrical connections at all places with back up circuit breakers. Install required metal box for switch board and power/light outlets.

3.1.4 Install embassy provided ELCB with enclosure in bathroom/kitchen/laundry / electrical outlets on exterior surface and do all other related works including wiring and test the ELCB for safety.

3.1.5 Provide and install dedicated circuits for laundry washer/dryer with 4 mm sq.

wires. Washer /dryer shall be connected with ELCB.

3.1.6 Remove concealed stopcock from the bathroom and install new embassy provided shower panel, mixture, and shower head.

3.1.7 Install embassy provided wall tiles with spacer in bathrooms, and laundry up to ceiling height with cement-based tile adhesive. The contractor must prepare the surface for installation of new tiles as required after removing all existing mortar.

The tiles shall be installed properly a lined with all the tile joints leveled and straight. All tile joints shall be filled evenly with embassy provided grouting material. Prior to the contractor installing any type of tile, they must prepare a 1m x 1m made up sample, showing tiles, joints, squareness, and grout joints. The approved sample boards are to remain on the project site for the entire project.

3.1.8 Install embassy provided floor tiles in bathroom and laundry with base mortar.

The contractor must prepare base for installation of new tiles as required after removing all existing mortar. The tiles will be installed with pidilite tile adhesive.

All tile joints will be filled with good quality grouting material. The floor shall be properly slopped as per the layout and location of floor drain. Prior to the contractor installing any type of tile, they must prepare a 1m x 1m made up sample, showing tiles, joints, squareness, and grout joints. The approved sample boards are to remain on the project site for the entire project.

3.1.9 Install granite stone to match wall tiles or washbasin counter on the edge of bathroom window.

3.1.10 Install drain for shower area and connect to the existing floor trap. The contractor shall use 2” dia PVC drainpipe. The drain pipe shall be properly connected to SS drain grating.

3.1.11 Slop of the shower area shall be towards drain so that no water should stand on the floor in shower area.

3.1.12 Install and built 3” high curb for shower area. Installation of shower glass shall be done by the fabricator.

3.1.13 Install embassy provided wall hung WC, wash basin with counter and vanity cabinet. Note: Do necessary modification of floor trap as per location of the fixture.

3.1.14 Install embassy provided bottle trap, as well as health faucet, angle valve, shower panel for washbasins and WC completes with ½” CP pipes.

3.1.15 The contractor shall install Embassy provided vanity cabinet with granite counter slab for washbasin in each bathroom. Cutting of granite as per the washbasin and vanity cabinet shall be done by the contractor.

3.1.16 The contractor shall install bathroom accessories (towel rod, towel ring, toilet paper holder, etc.) provided by the Embassy.

3.1.17 Install embassy provided mirror lights as per the layout of bathrooms.

3.1.18 Install dry-wall / gypsum board false ceiling with metal frame. The contractor shall do wiring for recess ceiling lights and exhaust fan in all the bathrooms with conduiting/wiring/switches as per electrical standard. Recess lighting and exhaust fan will be provided by the Embassy.

3.1.19 The contractor shall make required size opening in exterior wall of bathroom for installation of exhaust pipe and hood.

3.1.20 Each bathroom will have two decorative niches with LED drop lights. The niche shall be 4” deep and recessed in the wall. The niche side wall shall be finished with granite stone same as installed on vanity counter. All the edges of granite stone shall be grinded and round molding shall be made.

3.1.21 Existing door and frame shall be scrapped completely. All doors and frame shall be sanded smooth, cleaned and have two coats of polyurethane paints with primer and top coat as per standard PU painting specifications.

3.1.22 The contractor shall install new hardware (door lock, tower bolt hinges, etc.)

provided by the embassy.

3.2 Upgrade of kitchen

3.2.1 Remove existing kitchen cabinets, counter slab, sink, fixtures/fittings, wall and floor tiles complete with plumbing and electrical fittings/fixtures.

Install new cold and hot water supply line (copper pipe) with control valve, inside the kitchen with embassy provided pipe. Insulate both hot and cold-water pipeline with embassy provided insulation. The new internal pipes shall be connected to the exterior pipe by the contractor. Contractor shall do the pressure testing of all newly laid plumbing pipes before plastering.

3.2.2 Install new switch/sockets, power/light outlets of kitchen complete with rigid

PVC conduit, PVC insulated 4.0 sq.mm. as well as 2.5 sq. mm copper wire and

2.5 sq. mm. and 1.5 sq mm ground wire. All conduit shall be recessed in the wall or in ceiling. Each kitchen shall have 6 – 20-amp power outlets. All the switches for ceiling lights, wall lights or lights under the cabinet shall be connected to main switch board in kitchen. All switches are to be wired the same way. Do all related works including electrical connections at all places with back up circuit breakers.

Install required module box for switch board and power/light outlets.

3.2.3 Install embassy provided ELCB with enclosure in kitchen and do all other related works including wiring and test the ELCB for safety. Why not install GFCI in circuit panel? Why have another?

3.2.4 A dedicated electrical power outlet to be provided for the water distiller or Nano water filter.

3.2.5 Install embassy provided wall tiles with spacer in kitchens up to ceiling height with cement-based tile adhesive. The contractor must prepare the surface for installation of new tiles as required after removing all existing mortar. All tile joints shall be filled with embassy provided grouting material. Prior to the contractor installing any type of tile, they must prepare a 1m x 1m made up sample, showing tiles, joints, squareness, and grout joints. The approved sample boards are to remain on the project site for the entire project.

3.2.6 Install embassy provided Italian marble at kitchen floor with base mortar. The contractor must prepare base for installation of new marble floor as required after removing all existing mortar/floor. The marble shall be installed with cement slurry over the cement mortar bed. All tile joints will be filled with grouting material.

3.2.7 The new marble floor shall be grinding and polished as per standard polishing process starting from # 00 abrasive to # 200 abrasive. All grinding/polishing abrasives and machine shall need to be provided by the contractor.

3.2.8 Install Embassy provided counter slab with sink as per the layout over the base cabinets. Cutting of marble slab as per required measurements shall be done by the contractor.

Note: modular kitchen cabinets (base cabinets as well wall cabinets) will be fabricated and installed by third contactor.

3.2.9 Install granite stone matching to wall tiles or kitchen counter on the edge of kitchen window.

3.2.10 Install sink drain with P-trap and connect it to floor drain concealed in wall/floor.

The contractor shall use 2” dia PVC drainpipe.

3.2.12 Install embassy provided chimney above the cooking stove as per approved layout for kitchen complete with electrical wiring and power outlet with required duct & hood. Provide metal vent to exit on the outside wall. Terminate vent with exterior vent cover.

3.2.13 Install dry-wall false ceiling with metal frame. The contractor shall do wiring for recess ceiling lights and exhaust fan, that vents to the outside, in all the kitchens with conduiting/wiring/switches as per electrical standard.

3.2.14 Existing door and frame shall be scraped and sanded completely. All doors and frame shall be provided with two coats of polyurethane paints with primer and top coat as per standard PU painting specifications.

3.3 Upgradation of Living/Dining room and Bedrooms :

3.3.1 Install new switch/sockets for all power/light outlets, wall lights, ceiling fans in living room, dining room, bedrooms, store rooms and stair-case complete with rigid PVC conduit, PVC insulated wire : 4.0 sq.mm. with 2.5 sq. mm copper wire and 2.5 sq. mm. wire with 1.5 sq mm ground wire, shall be recessed as per the requirement. Each room shall have 2 power outlets and 8 – 5amps outlets, need to have two outlet on each wall at least, not more than 12’ apart. Outlets with 4.0mm sq & 2.5 mm sq. wiring respectively. Do all related works including electrical connections at all places with. Selection of proper module box to be done for switch board plates as per the requirement so that blanks are not used.

3.3.2 Remove existing floor tiles complete with base mortar. Repair the base floor.

Install new 800mm X 800mm floor tiles with cement mortar/tile adhesive throughout the bedrooms, living/dining room with 4” skirting. The floor tiles shall be filled with grouting materials provided by embassy.

3.3.3 Remove existing floor finish from stair-case steps/landing. Clean and remove old residue /mortar. Install embassy provided seasoned wood for parquet flooring on steps and landing with Fevicol glue as per approved pattern, approx. new parquet flooring shall be grinded, sanded and polished by the contractor with MRF / or equivalent polyurethane coating in matt finish. All or any gap shall be filled wooden strips or sawdust before polishing. After grinding and sanding two coats of polyurethane (MRF makes) after two coats of sealer on the parquet floor.

Provide 1m x 1m sample mockup of wood floor, showing wood, joints, sanded surface and final finish. Sample to remain on site, until completion of the project.

3.3.4 The contractor shall do civil work, make required chase in wall for replacement of existing fan-coil units. The chase shall be made to expose existing chill water line and to connect new FCUs as per the approved location. Approx. wall chase area for one fan coil unit shall be 6’ X 1’. Once all chill water pipes are connected, the contractor shall fill the chase with cement mortar and finish the wall as per existing, ready for painting. How many fan coils, location, height, etc.

3.3.5 Replace existing distribution board with new 12 way distribution board as per the existing location. What type of distribution board?

3.3.6 The contractor shall raise existing staircase railing to increase the height up to 42”. The wooden handrail shall be re-installed after raising the railing. Also add addition balusters between existing railing.

3.3.7 Install S/S curtain rods with bracket at all exterior sliding doors and bedroom windows.

3.3.8 Remove all existing wardrobes and repair the walls for any damage before the installation of new modular wardrobe.

3.4 PATIO PAVING

Install 30mm thick – 600mm X 600mm KOTA stone with granite boarder over the existing concrete at back patio with cement base mortar (approx.. area 2500 sq. ft.

for 5 apartments). Contractor shall prepare the base with cement mortar (1:3, cement, and coarse sand mortar) before installation of KOTA stone. Put a coat of bonding agent; Sika Latex multipurpose polymer coating shall be done over new concrete before laying base mortar. Provide 1m x 1m sample mock up of stone floor, showing wood, joints, sanded surface and final finish. Sample to remain on site, until completion of the project.

3.4.1 Grind complete KOTA stone flooring, starting with abrasive stone #0 till # 2L as per masonry standard specifications. (Contractor shall provide all material required for grinding of KOTA stone including grinding machine and abrasives)

3.4.2 KOTA stone shall be installed in level and provide proper slop towards existing drain channel so that water will not be standing.

3.4.3 Install 4” wide granite boarder on the edges of the platform. Grouting of stone shall be done once installation of KOTA stone and granite boarder completed.

3.4.4 Fill the joints along the exterior apartment wall after the surface is completely dry with polysulphide compound provided by Embassy.

3.4.5 The surface will be watered and ground evenly with a grinding machine using abrasive stones. The surface should be grouted with cement for the topping after grindings.

3.4.6 After each grinding the floor should be allowed to dry and wet cured as per masonry standard specifications

3.4.7 Raise all manholes covers/drain grating located in patio area as per new floor level. Replace all manholes/grating with embassy provided new SS drain grating.

3.4.8 Install embassy fabricated aluminum gate at rear boundary wall.

3.5 EXTERIOR / INTERIOR PAINTING

Exterior Painting

• The contractor shall repair all cracks on exterior façade walls, overhangs, parapet wall, loose plaster, structural cracks on walls, overhangs, parapet walls, and boundary wall. The contractor removes all loose plaster /concrete and re-do the same with 1:4 cement plaster/ 1:2:4 cement concrete. The contractor shall use chicken mesh for strength/reinforcement for plastering area more than one square foot. Pattern for new plaster shall match with existing wall finish.

• The contractor shall repair visible cracks in walls. The crack shall be enlarged in

V-shape at least 1-1/2" wide and 2" deep to repair. The crack shall than be filled with 1:3 ratio cement mortar in two layer. Approved quality bonding agent shall be applied on V-grove before new plastering.

• The contractor shall have to use Embassy provided bonding material for patch repair per the condition of the cracks. It is the contractor responsibility to inspect the cracks and area to be painted at the time of walkthrough. The maintenance representative shall inspect the site to make sure all the loose/dead plaster has been removed before starting the painting. The contractor shall not start any painting unless all repair work shall finish and set properly.

• Contractor must prepare all surfaces for painting by removing any loose paint or rust, and then sand, and clean all surfaces to be be painted.

• The contractor shall paint the exterior façade of apartment block along with front and back trellis work at roof level including rear boundary walls with minimum two coats of paint. All wall surfaces shall be painted with exterior emulsion paint after a coat of primer on freshly repaired surfaces.

• Contractor shall clean, remove all loose paint, dirt, rust, and clean the metal surfaces before painting metal trellis with two coats of polyurethane paint of VEKTOR PU Paint of ICI make or equivalent provided by Embassy after a coat of primer.

• All surfaces shall be pressure washed and sanded per standards before starting painting.

• All painting rollers, brushes, tools, paint tray, rugs, pressure washer, ladder and scaffolding shall be provided by the contractor.

Interior Painting

• Paint the interior of complete apartment, including walls/ceiling and stair-case with two coats of paint as per standard specifications for interior painting. All painting material will be provided by the Embassy. Inside of the apartment should be painted with ‘Interior paint – Premium Acrylic Emulsion Paint and water-based enamel paint. The kitchen, laundry room, bathroom are to be painted with lead free embassy provided water based white enamel paint. All interior doors shall be scrapped and painted with PU paint after a coat of primer. Doors shall be painted with spray gun to have even finish.

• The contractor shall repair all cracks, loose plaster, repair surfaces damaged due to seepage and undulation on interior surface.

• Contractor shall follow standard specifications for interior painting.

• The contractor shall make-sure all the doors, window shutters, wardrobe doors and cabinet drawers and shutter should be opened and closed smoothly after painting. (How many hinges, what will doorknobs be, locking for bed room?

• Remove hardware with all accessories, plates, light fixtures, and items in place that are not to be painted, shall provide protection such as taping with 2” thick masking tape prior to surface preparation and painting (taping includes windows, door jams). Remove temporary protective wrappings after completion of painting operations.

• All interior doors shall be scrapped, and painted with white PU finish as per standards specifications, including the wooden door frame. PU painting shall be done through spray gun. The doors shall be properly scrapped and finish smoothly with putty before painting. The doors shall have minimum two coats of paint to get smooth professional finish.

• All painting rollers, brushes, tools, paint tray, rugs, pressure washer, paint spray machine with compressor ladder and scaffolding shall be provided by the contractor.

3.5 STAIR CASE RAILING

The existing stair-case railing shall be modified to increase the height to 34”.

The contractor shall remove existing handrail with base metal strip. Extended vertical baluster with matching to existing MS rod to required height.

The joint between existing and new baluster shall be very smooth and shall be done professionally. All materials for extension of railing shall be provided by the Embassy.

3.6 MATERIALS

Government Supplied Materials:

• 100% materials will be provided by Embassy.

• The contractor shall provide all required tools, ladders, scaffolding, pressure washer, mortar pans, grinding machine for floor polishing, polishing abrasives or stones, roller, brushes, copper brazing gas set (DA & oxygen gas bottle with regulator and trolly for transporting), welding machine, welding rods, pressure testing machine for plumbing and PPE for supervisor, professional foremen and technicians.

3.8 DISPOSAL

o Removal of demolition or construction debris shall be done by the embassy.

o Disposal of all the re-cyclable items /scarp shall be Embassy’s responsibility. The contractor shall segregate scrap from debris and keep separate lot of each item for easy disposal.

o Contractor shall keep the site clean, all debris shall be properly managed to avoid any tripping hazard and hindrance to work at site.

3.9 CONTRACTOR’S RESPONSBILITY

o The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this contract. The Contractor shall correct or revise any errors or deficiencies in its construction and other services without additional compensation, o The Contractor shall identify a Project Manager/Supervisor who shall be responsible for the overall management of this Contract. Project Manager shall be qualified and have the experience in same type of job. The contractor’s supervisor should always be present at site.

o The Contractor is responsible for safety and shall comply with all local labor laws, regulations, customs, and practices pertaining to labor, safety, and similar matters. The Contractor shall promptly report all accidents resulting in lost time, disabling, or fatal injuries to the COR.

o The Contractor shall be responsible for connection of temporary utilities to existing utilities including water and power. All temporary connections to local water and power shall be coordinated with the Embassy.

o All expenses towards mobilization at site and demobilization including bringing in equipment, workforce and materials, profit and overheads, dismantling the equipment, clearing the site etc. should be included in the rates quoted by the contractor. No separate payment on such expenses shall be entertained.

o Contractor should keep the site clean and accessible to Embassy employee all time.