File Type Posted
Attachment 0005 - Cost-Price Matrix - 8 April 2021.xlsx XLSX spreadsheet
W52P1J-20-R-0050 Amendment 0003 - 9 April 2021.pdf PDF
W52P1J-20-R-0050 Amendment 0002 - 6 April 2021.pdf PDF
Attachment 0002 - Staffing and Labor Mix - 30 March 2021.xlsx XLSX spreadsheet
Attachment 0005 - Cost-Price Matrix - 6 April 2021.xlsx XLSX spreadsheet
Attachment 0007 - DoL WD 2015-5337 Rev 12 - 21 Dec 2020.pdf PDF
Attachment 0005 - Cost_Price Matrix - 18 March 2021.xlsx XLSX spreadsheet
Attachment 0002 - Staffing and Labor Mix - 11 March 2021.xlsx XLSX spreadsheet
Attachment 0001 - PWS - 24 March 2021.pdf PDF
W52P1J-20-R-0050 Amendment 0001 - 26 March 2021.pdf PDF
Appendix B - UME - RESERVED.docx DOCX document
Appendix A - PAAT.DOCX DOCX document
Exhibit B - Fort Riley CDRL Portfolio.pdf PDF
Attachment 0006 - SF1408 Preaward Survey of Prospective Contractor Accounting System 07OCT2020.pdf PDF
Appendix D - SLA.DOCX DOCX document
Annex A Maintenance PRS.docx DOCX document
Attachment 0015 - Subcontractor Cost Information Submission 07OCT2020.docx DOCX document
Attachment 0011 - Contract References Spreadsheet 07OCT2020.xlsx XLSX spreadsheet
Attachment 0009 - Fort Riley Purchasing Invoicing Guide 07OCT2020.pdf PDF
Attachment 0001 Fort Riley PWS.pdf PDF
Annex B Supply PRS.docx DOCX document
Annex D Environmental Requirements.docx DOCX document
Attachment 0010 - Blocked File Extensions 07OCT2020.pdf PDF
Attachment 0007 - DOL Wage Determination 30JUN2020.pdf PDF
Attachment 0005 - Cost-Price Matrix.xlsx XLSX spreadsheet
Attachment 0004 - Letter of Consent 07OCT2020.docx DOCX document
Annex E Definitions Acronyms Abbreviations.docx DOCX document
Appendix C - Tactical SSA.DOCX DOCX document
Appendix E - All Army Excess.docx DOCX document
Annex F Publications and Forms Update 7-15.docx DOCX document
Attachment 0003 - Performance Questionnaire 07OCT2020.docx DOCX document
Attachment 0002 - Staffing and Labor Mix 12NOV2020.xlsx XLSX spreadsheet
W52P1J-20-R-0050 - issued 4 March 2021.pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Task/Requirement

Standard
Sampling Method, Lot & Acceptable Quality Level (AQL)

TRANSPORTATION - GENERAL

5.26.3 Provide reports and statistical data Timeliness: Reports and statistical data delivered by the due date.

Quality: IAW DLRS ITD-01 Accurate and complete Surveillance activity report

Lot: Inspect reports submitted per quarter.

AQL: 95%

PERSONAL PROPERTY OPERATIONS

5.27.1 Provide disposition instructions to current DPM contractor for shipments on-hand after expiration of previous DPM contract period.

Timeliness: Disposition documents will be completed prior to the 180th day following the end of the current contract.

Quality: Disposition instructions for shipments on-hand after the end of contract period will be complete and accurate.

Surveillance activity report

All shipment remaining after expiration of current contract at time of surveillance.

AQL: 100%

5.27.1 Process Incentive Payments and Reimbursements.

Timeliness: Payments and reimbursements will be submitted to the Government rep, within 3 business days of receipt.

Approved payments and reimbursements will be forward to BMO daily and to DFAS weekly.

Quality: Incentive payments and reimbursements will be accurately prepared using applicable government rates in effect at the time of the move and a complete copy will be provided to QAE upon request.

Weights will be entered accurately and completely into AIS.

Random sampling

Each reimbursement completed at time of surveillance.

AQL: 100%

5.27.1 Statement of Accessorial Services performed.

Timeliness: Submit 619 receipt from TSP statement of accessorial services performed will be submitted to government rep, within 5 business days of receipt and to QAE upon request.

Quality: Shipment documents will correspond to the appropriate shipment record.

Random sampling

Lot: Each statement of accessorial services performed at time of surveillance.

AQL: 100%

5.27.1 Process payments for additional services.

Timeliness: Approved SF 1034 submitted to DFAS within 3 business days of receipt from Government representative.

Quality: Services performed are verified as rendered. SF 1034 is accurate and complete.

Random sampling

Lot: Each SF 1034 completed at time of surveillance.

AQL: 100%

5.27.1 Process certified NTS quarterly invoices from TSP.

Timeliness: Invoices will be submitted to the appropriate DFAS and BMO within 3 business days of receipt from Government representative.

Quality: NTS Quarterly invoice will be accurate, current, and complete.

Random sampling

Lot: Each invoice in process or completed at time of surveillance.

AQL: 95%

5.27.1 Statement of Accessorial Services performed Timeliness: Approved SF 1034 submitted to DFAS within 3 business days of receipt from Government representative.

Quality: Services performed are verified as rendered. SF 1034 is accurate and complete.

Random sampling

Lot: Each SF 1034 completed at time of surveillance.

AQL: 100%

5.27.2 Counsel customers Timeliness: In conjunction with shipment application and/or movement request.

Quality: Customers will be counseled IAW DTR Part IV, and/or service guidance. Copy will be provided to QAE on request.

Random sampling

Lot: Counseling completed at the time of surveillance.

AQL: 99%

5.27.2 Counsel personnel on entitlements and procedures for pickup, delivery and/or storage of personal property/household goods Timeliness: Personnel counseled with 3 hours of arrival/walk-in time and/or 1 hour of appointment time

Random sampling

Lot: Percent of personnel counseled within 3 hours of arrival/walk-in time; percent counseled within 1 hour of appointment time.

AQL: 90%

5.27.3 Provide Specialized, Expedited Assistance for Sensitive circumstances Timeliness: To meet member/family member’s needs.

Quality: Blue Bark shipments will be handled IAW DTR Part IV, 410-E, and a complete copy will be provided to QAE on request.

Random sampling

Lot: Blue Bark/Sensitive shipments Completed at the time of surveillance.

AQL: 100%

5.27.4 Route and award personal property shipments for pick up.

Timeliness: Personal Property will be routed and awarded prior to pick up date in shipment application.

Quality: IAW DTR Part IV requirements Random sampling

Lot: Each shipment or storage lot offered for acceptance.

AQL: 100%

5.27.6 Prepare shipment applications and personally procured movement (PPM) Requests.

Timeliness: Assist DPS customers when required.

Quality: Will be completed IAW DTR Part IV and governing service regulations and a complete copy will be provided to QAE on request.

Random sampling

Lot: Shipments applications and self-movement requests completed at the time of surveillance.

AQL: 95%

5.27.8 Conduct Quality Control inspections for personal property movements Timeliness: Conduct in person QC inspections on a minimum of 50 percent of personal property movements during pack-out or move-in. Conduct QC inspections on 100 percent of Blue Bark and Gold Star Shipments

Random sampling

Percent of in-person QC inspections conducted.

AQL: 50%

5.27.9 Collect Excess Costs.

Timeliness: DD 139 prepared within the same week excess costs are discovered / determined; approved 139 will be submitted to DFAS as required. DD1131 prepared in the same week monies are received; submitted to Government rep, for deposit weekly.

DD Form 139 or DD Form 1131 will be prepared and maintained completely and accurately. Provide a copy to QAE upon request.

Random sampling

Lot: Collection forms completed at time of surveillance.

AQL: 100%

5.27.9 Process request for extension of travel and transportation entitlements.

Timeliness: Review and forward to Government rep, within 5 business days of receipt.

Approved requests will be returned to the requestor the next business day.

Quality: Requests will be reviewed for eligibility. Requests forwarded to ITO will be complete, accurate, and contain all appropriate supporting documents/copies required by the JTR and an approval/recommendation letter for ITO signature and provide a copy to QAE upon request.

Random sampling

Lot: Each extension in process or completed at time of surveillance.

5.27.9.1 Process change in destination Requests.

Timeliness: Initiate tracer action Diversions: Initiate diversion immediately upon notice of change in destination.

Delivery from SIT/DPM Warehouse: Coordinate the release from warehouse within 5 days of receipt of request for shipment.

Quality: Certificates of diversion, Certificates for Long Delivery-Out-of-SIT, and DPM reshipment instructions prepared, completed, approved and distributed accurately and completely and a complete copy will be provided to QAE on request.

Random sampling

Lot: Each change In destination in process or completed at time of surveillance.

AQL: 95%

PASSENGER MOVEMENTS - Reserved

MOTOR POOL OPERATIONS

5.29.1 Control & Account for GSA vehicles, keys, and credit cards report loss/abuse Timeliness: By COB daily notify COR upon discovery.

Quality: Complete & accurate Random sampling

Lot: Each GSA vehicle hand receipt completed at time of surveillance.

AQL: 99%

5.29.1 Maintain hand receipts on GSA vehicles Timeliness: Hand receipts updated annually, as a minimum.

Quality: Complete & accurate Random sampling

Lot: Each GSA vehicle hand receipt completed at time of surveillance.

AQL: 98%

5.29.1 Pick up and deliver vehicles Timeliness: Vehicles pickup within (5) business days when notified.

Quality: Pick up & delivery to designated area.

Random sampling

Lot: Each vehicle requiring pickup and delivery completed at time of surveillance.

AQL: 98%

5.29.1 Maintain a copy of justification on each motor vehicle utilized for official use and notify users when it is due to expire excluding LSEV.

Timeliness: Annually

Quality: Justification must meet the requirements of AR 58-1.

Random sampling

Lot: GSA vehicle justifications prepared each year.

AQL: 100%

5.29.3 Receive requests for motor transportation Timeliness: Requests reviewed and submitted to government rep, by COB.

Quality: Requests are complete and accurate prior to government rep, manual or telephonic approval.

Random sampling

Lot: Each request for motor transportation completed at time of surveillance.

AQL: 99%

5.29.3 Inspect & dispatch GSA vehicles and GSA credit cards Timeliness: Vehicle inspected at time of dispatch and upon return. LSEV inspected and dispatch quarterly. FORSCOM decal affixed prior to initial dispatch

Quality: Inspection shall be performed accurately Random sampling

Lot: Each GSA vehicle dispatch in process or completed at time of surveillance.

AQL: 100%

5.29.4 Operate buses and other non-tactical vehicles Timeliness: To meet mission requirements.

Quality: Vehicles operated safely.

Random sampling

Lot: Each special mission requirement completed at time of surveillance.

AQL: 99%

5.29.11 Schedule for Maintenance of GSA vehicles.

Timeliness: Users notified 5 business days prior to scheduled maintenance date

Quality: Scheduled maintenance performed.

Surveillance activity checklist

Lot: Each GSA vehicle requiring maintenance completed at time of surveillance.

AQL: 95%

UNIT MOVEMENTS - Reserved

CARGO MOVEMENTS

5.31.1 Route military cargo and equipment.

Timeliness: To meet mission requirements

Quality: Shipment will be routed IAW DTR PART II. Data entry into ETA/FAST/GFM CMOS will be accurate and complete.

Random sampling

Lot: Each shipment competed at time of surveillance.

AQL: 100%

5.31.2 Hazardous materials, oversized, sensitive items properly identified, documented, marked, labeled, and/or placarded Timeliness: Prior to preparation of GBL/CBL.

Quality: Certified HazMat preparers are verified; documents are complete and accurate.

Random sampling

Lot: Each hazardous materials, oversized, sensitive shipments in process or completed at time of surveillance.

AQL: 100%

ARRIVAL/DEPARTURE AIRFIELD CONTROL GROUP (A/DACG) - Reserved

CONTAINER YARD OPERATIONS

5.33.1 Download, upload, reposition, retrieve, and transport containers Timeliness: To meet training exercise/deployment requirements with no additional commercial charges being incurred.

For non-deployment movement, when current scheduled workload permits support.

Quality: Containers placed safely and correctly at designated location.

Random sampling

Lot: Each container transported in process or completed at time of surveillance.

AQL: 99%

5.33.1 Issue & Receive ISO containers & MILVANS Timeliness: Control document prepared for each asset at the time of transfer.

Quality: Completely & accurately.

Random sampling

Lot: Each control document in process or completed at time of surveillance.

AQL: 100%

5.33.1 Inspect & certify ISO containers.

Timeliness: NLT 2 1/2 years from date of last certification.

Quality: To meet international CSC standards.

Random sampling

Lot: Each ISO container in process or completed at time of surveillance.

AQL: 95%

5.33.1 Arrange for scheduled and/or emergency maintenance of light sets.

Timeliness: Scheduled: IAW manufacturer’s recommendation Emergency: Same day

Quality: Required maintenance scheduled.

Random sampling

Lot: Each light set scheduled for maintenance at time of surveillance.

AQL: 100%

5.33.1 Reposition or retrieve light sets Timeliness: Within 48 hours of directive.

Quality: Lights sets relocated safely to designated location.

Random sampling

Lot: Number of light sets repositioned/retrieved or completed at time of surveillance.

AQL: 95%

5.33.2 Conduct inventory of ISO containers and light sets Timeliness: Containers: Inventoried & reported quarterly.

Light sets: Reported NLT 5th business day of each month.

Quality: Completely & accurately Random sampling

Lot: Each inventory completed at time of surveillance.

AQL: 99%

5.33.2 Manage containers Timeliness: 100 percent of containers used for movement are ISO compliant prior to use

Random sampling

RAIL OPERATIONS - Reserved