This document is a Statement of Work (SOW) for providing a temporary chiller unit at USCG Station Annapolis, Maryland. The U.S. Coast Guard requires a contractor to install a 28-ton chiller unit for a minimum of two months, with potential extension through September, to address the station's current inoperable cooling system. The contractor must provide all necessary labor, materials, and equipment, including specialized personnel like electricians and HVAC technicians, to complete the installation, ensure proper connections to existing building infrastructure, and demonstrate proper system operation.
Key requirements include comprehensive site preparation, system commissioning, and adherence to strict safety and environmental regulations. Contractors must submit detailed employee information, obtain necessary permits, maintain site cleanliness, and coordinate with station personnel, including the designated Contracting Officer's Representative, MKC Preston Humbard. The solicitation (Number: 70Z0G825QBNCR0011) is issued by the Department of Homeland Security's U.S. Coast Guard, with potential bidders strongly encouraged to conduct a site visit prior to submission and familiarize themselves with specific installation requirements and operational conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - Pricing Spreadsheet.xlsx | XLSX spreadsheet | |
| 12a. RFQ Schedule 70Z0G825PBNCR0011.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
15Apr2025
SCOPE OF WORK: TEMPORARY CHILLER FOR STATION ANNAPOLIS
1. GENERAL REQUIREMENTS: The work consists of providing all labor, materials and equipment as required to provide a temporary chiller unit at USCG Station Annapolis, located at 3245 Thomas Point Rd. Annapolis, Maryland. The current chiller unit at STA Annapolis is inoperable and the unit is without air condition due to contractual lead times.
2. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: Upon acceptance the contractor shall commence work NLT five (5) days after notice to proceed and work diligently to complete the entire work ready for use by two (2) working days after contract award.
3. SCOPE OF WORK: Contractor shall provide all services, materials, and equipment to install a temporary 28 Ton chiller unit for a minimum of two (2) months with the option to extend two (2) months, through the end of September, at the discretion of the government. Contractor shall provide all required fittings, connections, hoses, or piping required to tie provided chiller into building’s existing chill water piping. Contractor shall ensure adequate fittings, connections, hoses, or piping are on hand regardless of distance between provided unit and building chill water connections. Contractor will provide all equipment required for unloading trailers, trucks, or equipment. Contractor will provide all specialized or certified laborers (e.g. electrician, HVAC technician, forklift operator, or crane operator). Contractor will make all electrical and plumbing connections, fill chill water system with appropriate fluid, energize the temporary unit, blead all air from the system, and ensure proper operation. The contractor shall familiarize unit personnel with emergency shut down procedures prior to departing the facility.
4. SITE VISIT: All bidders are strongly encouraged to visit the site to identify any considerations before submitting bids. Interested parties shall make arrangements for a site review with MKC Preston Humbard @ 804-514-1633.
5. DESIGNATED CONTRACTING OFFICER’S QA EVALUATOR (QAE) REPRESENTATIVE: The designated contracting officer’s QAE representative and Point of Contact for this project is MKC Preston Humbard @ 804-514-1633. Inquiries concerning any phase of the specification before or after award shall be made to MKC Preston Humbard.
6. CONDITIONS AFFECTING THE WORK: The Offeror should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, the general and local conditions which can affect the cost of the work thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The government will assume no responsibility for any misunderstanding or misrepresentations concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the request for quotes, the specification or related documents.
7. AFTER AWARD OF THE CONTRACT: The contractor must immediately notify the contracting officer’s QAE representative of the intended start date. The work shall be done in accordance with the specification.
8. ORAL MODIFICATION: No oral statement of any person other than the contracting officer shall in any manner or degree, modify or otherwise affect the terms of this contract.
9. WORKMANSHIP: All work shall be accomplished with the best standard practices, and by workmen thoroughly experienced in the required trades. The work shall be supervised by experienced personnel and shall be satisfactory to the Contracting Officer.
10. PERMITS: The contractor shall without additional expense to the government, obtain all appointments, licenses, and permits required for the prosecution of the work. The contractor shall comply with all applicable federal, state and local laws.
11. CLEAN UP: All trash and debris shall be removed from the site daily. The job site shall be left in a clean and neat manner.
12. WORK OUTSIDE REGULAR HOURS: If the contractor desires to carry on work on Saturday, Sunday, holidays or outside the station’s regular hours, they may submit a request in writing to the Contracting Officer’s QAE Representative for approval consideration. The contractor shall allow ample time to enable satisfactory arrangements to be made by the government for inspecting the work in progress.
13. UPON COMPLETION OF WORK: Contact the Contracting Officer QAE Representative to arrange for inspection/acceptance of work.
14. IDENTIFICATION OF CONTRACTOR PERSONNEL AND VEHICLES: The contractor shall provide a detailed list of all employees to the QAE Representative five (5) days prior to commencing work. The employee list shall contain the employee’s full name, date and place of birth, current address and last four (4) of SSN. The Station Annapolis Security Officer will be given a copy of the employee list, and a pass will be issued for entry. Each contractor provided vehicle, or towed trailer shall show the contractor’s name so that it is clearly visible on the vehicle. A valid state license plate and safety inspection sticker is required. All vehicles operated on government property shall be maintained in a good state of repair.
15. SAFETY REQUIREMENTS:
1. Responsibilities:
a. All contractors working on Station Annapolis shall abide by all federal environmental regulations as published by the Environmental Protection Agency, 40 CFR (series). Contractor written environmental management and pollution prevention programs shall be reviewed by the Environmental Protection Specialist CWO4 Matthew Thornton @ 443-610-8459 prior to starting work and must be in accordance with ICSPORTSVA INSTM5090.2, the Unit Environmental Guide.
b. Written notification must be provided to USCG Station Annapolis Safety Officer, BM1 David Pena or MKC Preston Humbard in their capacity as Base Fire Marshal of any activity that could potentially cause fire or explosion or that changes or reduces the capability of fighting a fire or explosion. Some examples of qualifying activities are: a fire hydrant or fire suppression system that must be taken out of service for any reason, electrical work that affects fire alarm systems, introduction of hazardous or flammable material onto the Base, and blocking of any egress routes or emergency vehicle routes. Inclusion of this information in the contract constitutes written notification if the outsource review sheet is signed by Base Safety Officer.
c. Copies of the following must be provided to the Base Safety Officer prior to starting work in affected areas: Confined Space Entry Permits, Hot Work Chits, and Dig Chits. Confined space clearance must be conducted by a certified marine chemist and permit required spaces will have a copy of the permit posted on site during work. Hot work will only be conducted with permission and a fire watch must be posted during work. A facility dig chit is required in addition to a Miss Utility dig chit. The systems on USCG Station Annapolis are not limited to what the City of Annapolis has on file. In order to ensure electrical safety and integrity of systems, a facility chit is required.
d. Lock Out/Tag Out requires notification and coordination with facilities and will not be conducted by a contractor on Station Annapolis. A USCG Station Annapolis representative is required for all contractor Lock Out/Tag Out needs.
2. Rights:
a. Every employee working on USCG Station Annapolis has the right to a safe and healthy workplace. The contractor has the responsibility and right to stop unsafe work. QAE’s and the Safety Officer may also institute a work stoppage relating to unsafe practices or immediate danger to life and health situations.
16. ENVIRONMENTAL PROTECTION REQUIREMENTS:
a. All contractors working on USCG Station Annapolis shall abide by all federal environmental regulations as published by the Environmental Protection Agency, 40 CFR (series). Contractor written environmental management and pollution prevention programs shall be reviewed by the Environmental Protection Specialist, CWO4 Matthew Thornton @ 443-610-8459 prior to starting work and must be in accordance with ICSPORTSVA INSTM5090.2, the Unit Environmental Guide.
b. Written notification must be provided to the Environmental Protection Specialist of any activity that could potentially cause a permit violation on USCG Station Annapolis. Some examples of qualifying activities are: any activity that could result in a spill or discharge into a waterway or introducing a hazardous material into the environment.
c. Copies of the following must be provided to the Environmental Protection Specialist prior to starting work in affected areas: Material Safety Data Sheets, permits, and notices of intent.
d. Hazardous materials used by a contractor are required to be disposed of by that contractor. Disposal must be in accordance with federal, state, and local guidelines.