Angling Elementary - Site Clearing - Project Manual.pdf

PDF 9 MB Posted

Attached to
ANGLING ROAD ELEMENTARY - SITE CLEARING PACKAGE
Solicitation number
RFP PPS 270000000316 2
Issued by
Kalamazoo County, Michigan

About this file

Summary

This is a Construction Manager's Project Manual for the Angling Road Elementary Site Clearing Package issued by Portage Public Schools in Michigan on November 4, 2026. The project involves complete site clearing and demolition work, including earthwork, temporary tree protection, soil erosion control, site demolition of pavements and utility structures, and debris removal and hauling. A pre-bid site inspection is scheduled for November 11, 2026, at 9:00 AM at 5353 Angling Road, Portage, Michigan. Sealed bids in triplicate must be submitted by 2:00 PM local time on Monday, November 30, 2026, to the Portage Public Schools Administration Building or mailed to Owen-Ames-Kimball Co.'s Kalamazoo office. Bidders must have at least five years of successful experience on similar work, possess required licenses, and demonstrate adequate financial resources. The bid security must equal 5 percent of the bid amount in the form of a certified check, cashier's check, or bid bond from a surety company rated A- or better. Award notifications will be issued after the bid opening, with contracts awarded under AIA Document A132-2019.

The bid sum includes all applicable Michigan Sales and Use Tax, labor, materials, equipment, and the cost of furnishing Performance and Payment Bonds at 100 percent of the base bid for contracts exceeding $50,000. Three unit prices are required: supplemental excavation with satisfactory soil fill, supplemental excavation with engineered fill, and hauling off additional debris, all measured in cubic yards. Contractors must provide labor rates for additional work and fees of 10 percent for work by the contractor's own forces and 5 percent for subcontractor work. A Familial Disclosure Statement sworn and notarized in accordance with Michigan's Revised School Code Section 1267 and an Affidavit of Compliance with the Iran Economics Sanctions Act are mandatory. The successful bidder must submit insurance documentation, cost breakdowns, subcontractor lists, manufacturer information, and schedule details within ten days of the Notice of Pending Award. Owen-Ames-Kimball Co. will serve as Construction Manager and coordinate all project activities, meetings, submittals, and safety requirements in compliance with their established safety manual and policies.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PORTAGE PUBLIC SCHOOLS

ANGLING ROAD ELEMENTARY – SITE CLEARING PACKAGE

CONSTRUCTION MANAGER’S

PROJECT MANUAL

NOVEMBER 4th, 2026

Construction Manager:

Owen-Ames-Kimball Co.

2700 Stadium Dr. Suite 2

Kalamazoo, MI 49008

269-276-9700

Send RFIs and Substitution Requests to: Anastasiaw@oakmi.com by

11/13/26 at 2:00pm mailto:Anastasiaw@oakmi.com

Portage Public Schools, Angling Road Elementary – Site clearing Package www.owen-ames-kimball.com

Construction Management Project Manual Index

Bidding Requirements

Advertisement for Bids

Instruction to Bidders

Statement of Participation

Certificate of Insurance and Endorsement

Bid Form

Familial Disclosure Statement, Affidavit of Compliance

Safety Data Questionnaire

General Conditions

Specifications

Division 1 - General Requirements

01010 Summary of Work

01026 Unit Prices

01040 Project Coordination

01045 Cutting and Patching of New Work

01050 Field Engineering

01095 Reference Standards and Definitions

01200 Project Meetings

01300 Submittals

01400 Quality Control

01500 Temporary Utilities

01600 Material and Equipment

01650 Starting Systems

01700 Contract Close Out

Preliminary Construction Schedules

Subcontractor Submittal Form

Referenced Documents Available for Online Viewing

AIA A132 – 2019 – Standard Form of Agreement Between Owner and Contractor:

https://tinyurl.com/2p8pnk2b

Owen-Ames-Kimball Co. Safety Manual:

https://tinyurl.com/34zxyj49 https://tinyurl.com/2p8pnk2b

ADVERTISEMENT FOR BIDS

BID PROPOSAL

Sealed bids, in triplicate, for the Angling Road Elementary – Site Clearing Package, and Portage Public Schools, will be received until 2:00pm local time, Monday, November 30th, 2026 at Portage Public Schools Administration Building, 8107 Mustang Dr, Portage, MI 49002 and handed to an Owen-Ames-Kimball Co. employee. Please do not mail bids to the Portage Admin building. Bids received after this time will neither be considered nor accepted.

Bids may be mailed or dropped off to O-A-K Kalamazoo’s Office, 2700 Stadium Dr, Suite 2 Kalamazoo, MI 49008.

Mailed bids must be received prior by 11:00am November 30th, 2026. FAXED, EMAILED OR UPLOADED TO BUILDING

CONNECTED BIDS WILL NOT BE ACCEPTED.

In accordance with Section 1267 of the Revised School Code each bid must be accompanied by a sworn and notarized Familial Disclosure Statement completed by the bidder disclosing any familial relationship between the

Owner or any employee of the Bidder and any member of the District’s Board of Education or the Superintendent of the District.

SITE INSPECTION

A construction pre-bid meeting will be held at 5353 Angling Road, Portage, MI 49024 (Enter site off Vincent Ave drive)

9:00am local time, Wednesday, November 11th, 2026. All bidders are encouraged to attend.

BID DOCUMENTS

The Bidding Documents may be examined at the following locations:

• Owen-Ames-Kimball Co. Website: http://www.owen-ames-kimball.com/subcontractors/

• Builders Exchange plan rooms in Grand Rapids, Kalamazoo, Lansing and Traverse City.

BIDDER QUALIFICATIONS

Bidders submitting a Bid for this Project shall have qualifications as follows:

a. Shall be a reputable, recognized organization, with at least five (5) years successful experience on work of this type and scope of this project.

b. Shall have a license where required by public authorities having jurisdiction.

c. Shall have ample financial resources for work of this magnitude.

BID SECURITY - PERFORMANCE BONDS

Each bid shall be accompanied by good and sufficient bid security or bid bond in an amount not less than 5% of the

Bid amount and shall secure the Owner from loss or damage by reason of the withdrawal of the Bid by a Bidder or by failure of the successful Bidder to enter into a Contract with the Owner if his Bid is accepted by the Owner.

Bid securities will not be released or returned until the bid “hold-firm” date or a subcontract has been successfully executed for the specific bid category of work, whichever occurs first.

Bid security may be provided by furnishing a bond from a surety company having a rating of A- or better or certified check. Owen-Ames-Kimball is not responsible for the loss of bid security if provided by certified check.

The successful Bidder will be required to secure Performance, Labor and Material bonds for all contracts exceeding

$50,000, from a surety company having a rating of A- or better, for the full amount of the Contract.

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 1 of 9

SUPPLEMENT TO INSTRUCTIONS TO BIDDERS

STANDARD AIA FORMS

The Instructions to Bidders (AIA Document A701-2018 Edition), Articles 1 through 8, and as herein amended or added to, are a part of the Contract Documents, and shall apply to all Contractors, and/or Subcontractors.

ARTICLE 1 – DEFINITIONS Add Subparagraph 1.10 as follows:

1.10 All references made to Owner shall be implied to refer to the Construction Manager.

ARTICLE 3 – BIDDING DOCUMENTS

3.1 Distribution Add Subparagraph 3.1.6 as follows:

3.1.6 The Bidding Documents, including drawings, specifications, and necessary forms, can be examined at the following locations.

• Owen-Ames-Kimball Co. website: www.owen-ames-kimball.com/subcontractors/

• Builders Exchange plan rooms in Grand Rapids, Kalamazoo, Lansing, and Traverse City.

List a location of bid documents, in addition to OAK’s Office include Architect’s Office, Owner’s Office and Plan Room if applicable.

3.2 MODIFICATION OR INTERPRETATION OF BIDDING DOCUMENTS Revise Subparagraph 3.2.2. as follows:

Line 2 shall read “…ten days…”

ARTICLE 4 – BIDDING PROCEDURES

4.1 PREPARATION OF BIDS Revise Subparagraph 4.1.1. and Add Subparagraph 4.1.6.1, 4.1.9 and 4.1.10 as follows:

Bids shall be submitted, in triplicate, on the Bid Proposal Form included within the bidding Documents.

4.1.6.1 Proposals will be accepted for one (1) Bid Category only, or a combination of two (2) or more Categories. If the Bidders wish to have their combined bid considered for separate categories, they must submit separate proposals for the individual category along with their combined bid proposal.

4.1.9 A Pre-Bid Conference will be held in accordance with the following schedule:

Date: Wednesday, November 11th, 2026

Place: 5353 Angling Road, Portage, MI 49024 – Site Access off Vincent Ave

Time :9:00am

4.1.10 In accordance with Section 1267 of the Revised School Code each bid must be accompanied by a sworn and notarized Familial Disclosure Statement completed by the bidder disclosing any familial relationship between the Owner or any employee of the Bidder and any member of the District’s Board of Education or the

Superintendent of the District.

4.2 BID SECURITY Add Subparagraphs 4.2.1.1, 4.2.1.2 and Revise Subparagraph 4.2.3 as follows:

4.2.1.1 Bid security shall be required for each bid tendered.

4.2.1.2 Bid security shall be in the form of either a CERTIFIED or CASHIER’S CHECK on an open and solvent bank or bid bond issued by surety company payable to the Owner in an amount equal to five percent (5%) of the base bid.

4.2.3 Revise Lines 1 and 2 to read “If a surety bond is provided the attorney-in-fact who …”.

http://www.owen-ames-kimball.com/subcontractors/

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 2 of 9

4.3 ADDENDA Revise Subparagraph 4.3.3 as follows:

4.3.3 Addenda will be issued no later than two days prior to the date for receipt of Bids except an Addendum withdrawing the request for Bids or one which includes postponement of the date for receipt of Bids.

4.4 MODIFICATION OR WITHDRAWAL OF BIDS Revise Subparagraph 4.4.3 as follows:

4.4.3 After the time and date of receipt of Bids, a bid may not be modified, withdrawn or cancelled by the Bidder for sixty (60) days.

ARTICLE 5 – CONSIDERATION OF BIDS

5.3 ACCEPTANCE OF BID (AWARD) Revise Subparagraph 5.3.2 and add Subparagraph 5.3.4 as follows:

5.3.2 Revise Line 1 to read “…right to accept Mandatory and Voluntary Alternates in any order…”

5.3.3 Owner reserves the right determine which bidders are considered the lowest qualified bidder and to award to said bidder.

5.3.4 After the Owner has awarded the Bid Categories the Construction Manager will prepare and send a Notice of

Pending Award to the successful Bidders.

ARTICLE 6 – POST-BID INFORMATION

6.1 CONTRACTOR’S QUALIFICATION STATEMENT Revise Subparagraph 6.1 as follows:

The Owner, Architect and Construction Manager may make such investigations as they deem necessary to determine the ability of the Bidder to perform the work. The Bidder shall furnish all such information and data for this purpose as the Construction Manager may request within twenty-four (24) hours, including, but not limited to, lists of projects completed, financial statements for the past two (2) years, a current list of work in progress. The Owner reserves the right, based on the advice of the Construction Manager and

Architect, to reject any bid if the evidence submitted, or investigation of such Bidder, fails to prove that such

Bidder is properly qualified to carry out the obligations of the contract and to complete the work contemplated therein.

6.3 SUBMITTALS Revise Subparagraph 6.3.1, replace Subparagraphs 6.3.1.1 thru 6.3.1.3 and add

Subparagraphs 6.3.1.4 thru 6.3.1.6 as follows:

6.3.1 The Bidder shall within ten (10) days upon issuance of a Notice of Pending Award furnish to the Owner through the Construction Manager the following:

6.3.1.1 The necessary insurance forms as specified in the Bidding Documents.

6.3.1.2 A cost breakdown on the continuation sheets of the “Application and Certificate for Payment”, AIA

Document G703 showing all major work items, separated by both material and labor.

6.3.1.3 A list of the work which will be performed with the Bidder’s own forces, a list of their subcontractors and a list of work that will be performed by the subcontractor’s forces.

6.3.1.4 Names of the manufacturer’s, products and suppliers of principle items, materials or systems proposed for the work.

6.3.1.5 Schedule information.

6.3.1.6 The Bidder will be notified in writing if any of the above items are not acceptable.

ARTICLE 7 – PERFORMANCE BOND AND PAYMENT BOND

7.1 BOND REQUIREMENTS Revise Subparagraph 7.1.1 as follows and Delete Subparagraph 7.1.3

7.1.1 Revise first sentence to read “For Contracts exceeding $50,000 the Bidder shall furnish separate Performance and Payment Bonds covering the…”

7.2 TIME OF DELIVERY AND FORM OF BONDS Delete Subparagraph 7.2.2

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 3 of 9

ARTICLE 8 – ENUMERARTION OF THE PROPOSED CONTRACT DOCUMENTS

8.1 Revise sentence to read: Copies of the proposed Contract Documents will be made available to the Awarded

Bidder as modified and would include but not limited to the following documents as issued by the Construction

Manager.

ARTICLE 9 – INSURANCE

9.1 INSURANCE REQUIREMENTS The required insurance will name Owen-Ames-Kimball Co., Owner and

Architect, along with their respective officers, agents and employees are named as additional insureds for the auto liability and general liability on a primary and non-contributory basis for ongoing and completed operations. The ONLY acceptable endorsement for the additional insureds requirements is ISO form CG 20

37 07 04.

9.1.1 Commercial General Liability – ISO Occurrence form CG 20 10 07 04 and CG 20 37 07 04 are the required forms.

ARTICLE 10 – DESCRIPTION OF WORK Add paragraph 10.1 and 10.2

10.1 BID CATEGORIES Add Subparagraphs 10.1.1, 10.1.1.1., 10.1.1.2, 10.1.1.3 as follows:

10.1.1 Bid Categories have been established to guide Bidders in determining scope of work where trade jurisdiction is not clearly defined. These descriptions are not meant to be all inclusive of work to be included in the Bid.

If a conflict in the assignment of work exists between the Bidding Documents and the descriptions of these bid categories, the requirements of the bid category description(s) shall take precedence and the

Construction Manager shall immediately be notified of the conflict. Bidders are to familiarize themselves with all Bid Categories.

10.1.1.1 Requirements for a specific Bid Category, trade or contract will generally be described in that portion of the

Specifications or Drawings related to that trade or contract. Such requirements may, however, be described in other sections of the contract documents. Contractors will be held responsible for having carefully examined all drawings and read all divisions of the specifications and all contract documents to avoid omissions or duplications and to ensure a complete job.

10.1.1.2 There is not necessarily a direct relationship between the Bid Category numbers or names and the

Specification Division or Section numbers.

10.1.1.3 Unless specifically noted as being furnished only, scopes include the complete installation including materials, labor, equipment, interface with the work of other trades, etc.

10.2 INDEX OF BID CATEGORIES Add paragraph 10.2

Bid Category No. 01 – Earthwork – Site Clearing

10.3 BID CATEGORY DESCRIPTIONS Add paragraph 10.3

Bid Categories have been established to guide Bidders in determining scope of work where trade jurisdiction is not clearly defined. These descriptions are not meant to be all inclusive of work to be included in Bid.

Unless specifically noted as being furnished only or install only, scope includes complete installation including all labor, material, equipment, etc.

Bidders are required to familiarize themselves with all Bid Categories and Alternates.

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 4 of 9

BID CATEGORY NO. 01 – EARTHWORK

Include:

1. Complete site related and demolition work as shown on the drawings and as specified in the following sections:

Division 01 – General Requirements

31 1000 Site Clearing

31 2000 Earthwork

32 9300 Plants

2. All necessary surveying and staking for this contractor’s work. The Construction Manager will supply building control points and establish a benchmark.

3. Applicable fees, permits, inspections, etc. as required for the completion of the work in this bid category.

4. Responsible for keeping public roads clean of construction traffic dirt and debris.

5. Temporary tree protection measures.

6. Site related demolition, including but not limited to, pavements, site walls, utility structures, etc.

7. Soil erosion permit and erosion control.

8. Maintain and control grades to facilitate the run-off of site surface water.

9. Supply and maintain barricading as required for the work of this contractor.

10. Responsible to follow the most stringent requirements between the architectural specifications and those listed in the recommendations of the geotechnical report.

11. Responsible for all demo and debris removal shown on drawings.

12. Responsible for filling in/grading any holes created during demo and removal.

13. Provide and install track mat.

14. Remove, haul off and deliver selected logs to Lake Center Elementary 10011 Portage Rd, Portage, MI 49002. Drop off location to be coordinated with O-A-K and District. Ref Note on CD101.

Exclude:

1. Testing will be provided for and paid for by the Owner.

GENERAL COMMENTS

Demolition:

1. Dumpsters provided by the Construction Manager for use during construction shall not be available for the disposal of the following items: debris resulting from architectural, structural, mechanical, or electrical demolition operations; site related materials; paint products, hazardous materials. Contractors generating such materials shall provide dumpsters for them and legally dispose of them off site.

2. Unless specifically noted otherwise the division of demolition work shall be as follows: sitework contractor – site demolition; general trades contractor – architectural and structural demolition; mechanical/plumbing contractor –

HVAC and plumbing demolition; fire protection contractor – fire protection demolition; electrical contractor – electrical demolition.

3. Demolition shown on the demolition plans is the responsibility of the Demolition / General Trades Contractor.

Patching of items as a result of demolition shown on the Demolition plans is the responsibility of the contractor who is responsible for similar elements throughout the building.

4. Demolition (and related patching) needed but not shown on the demolition plan is the responsibility of the contractor requiring it.

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 5 of 9

General Safety:

1. Your Firm, all employees, subcontractors, and material suppliers onsite will comply with Owen-Ames-Kimball

Co.’s Safety Policy and Requirements, INCLUDING BUT NOT LIMITED TO THESE HIGHLIGHTED ITEMS:

a. Hard hats are required.

b. Contractor safety manuals/books will be kept on-site.

c. Contractors must provide their own first aid and fire protection equipment.

d. Contractors are responsible for providing the necessary barricades for their work.

e. Contractors are responsible for their own fall protection.

f. Contractors must comply with the "Right to Know" law.

g. Contractors must comply with O.A.K.'s substance abuse policy.

h. No Smoking, Tobacco, or E-Cigarettes on School Property.

i. A designated competent/qualified person shall be required to be on site for the following but not limited to structural demolition, scaffolding, fall protection & excavations.

j. Contractors shall furnish a written job specific Silica Exposure Plan per MiOSHA requirements.

k. Contractors required to work in a masonry restricted zone must have proper training.

2. Owen-Ames-Kimball Co. Safety Manual can be viewed in its entirety here:

End of Instruction Bidders

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 6 of 9

STATEMENT OF PARTICIPATION

Owen-Ames-Kimball Co. strives to recognize and represent the community in which you reside and serve through continuous efforts to encourage local participation and inclusive practices on all our construction projects.

Owen-Ames-Kimball Co. encourages local participation. We believe we have a responsibility to support the growth of the businesses within the community in which the project resides.

Owen-Ames-Kimball Co. practices inclusion. These inclusive practices are established within our organization and in our business endeavors, and strongly promoted on our jobsites. We encourage all of our subcontractors to implement inclusive practices within their organizations and through partnering efforts on our projects.

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 7 of 9

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 8 of 9

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 9 of 9

SUBMIT IN TRIPLICATE

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 1 of 7

BID FORM

BID TO: Portage Public Schools

8107 Mustang Dr

Portage, MI 49002

BID FROM: _________________________________________

PROJECT: Angling Road Elementary – Site Clearing Package

Ladies and Gentlemen:

The undersigned, having familiarized themselves with the local conditions affecting the cost of the Work and having examined the site, and Bidding Documents prepared by TowerPinkster, 242 E. Kalamazoo Ave, Suite 100, Kalamazoo, MI 49007, hereby propose to furnish all labor, material, equipment, taxes and services required for the proper completion of each of the following categories for this Project, including all addenda issued thereto, for the sum of:

Bid Category No.____________ Title

Dollars ($ _ ), Said amount constituting the Base Bid.

TAXES: Bid sum includes all applicable taxes, including Michigan Sales Tax. Confirm that your company can pay Michigan Sales and Use Tax: ☐ Yes ☐ No

ALLOWANCES: Base bid includes applicable allowance cost(s) as set forth in Section 01020 of the General

Requirements and as identified in the Instruction to Bidders Bid Category Descriptions.

COST OF BONDS: Bid sum includes cost of furnishing a Performance Bond and Labor and a Material

Payment Bond, each in the amount of 100% of Base Bid.

ACKNOWLEDGEMENT OF ADDENDA

The following addenda have been received, are hereby acknowledged, and their execution is included in the above Base Bid:

Addendum No. Dated Addendum No. Dated Addendum No. Dated_________

Addendum No. Dated Addendum No. Dated Addendum No. Dated_________

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 2 of 7

VOLUNTARY ALTERNATES (Identify in detail on appropriate attachment any Voluntary Alternates shown here)

A

B

C

BID SECURITY

Accompanying this Bid, as required by the Instructions to Bidders, is a bid security in the form of

(Certified Check/Cashier's Check/Bidder's Bond) in the amount of:

Dollars ($ _______ ), payable to the Owner, which it is agreed, shall be retained as liquidated damages, not as a penalty, by the

Owner, if the undersigned fails to execute the Contract in conformity with the form of Contract incorporated in the Contract Documents and fails to furnish specified bonds within ten (10) days after date of issuance of Letter of Intent to the undersigned.

If awarded the Contract, the undersigned agrees to commence Work within ten (10) days after date of issuance of Notice of Pending Award, which shall be considered as the notice to proceed, and agrees to complete the Work in accordance with the Construction Progress Schedule.

CONSTRUCTION PROGRESS SCHEDULE

If awarded this Contract, the undersigned:

Endorses the Construction Progress Schedule:

Amends the Construction Progress Schedule as follows:

INSURANCE AND ENDORSEMENTS REQUIREMENTS:

(Samples are attached to the Supplement to Instructions to Bidders)

Acknowledged By:___________________________________________________________________________________________

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 3 of 7

UNIT PRICING

Contractors are to indicate the following unit prices in their proposals. Adjustments to Contracts will be made once actual units have been determined. Unit prices shall include all costs, including profit and overhead.

Unit Price No. 1: Supplemental Excavation, Satisfactory Soil Fill:

1. Description: Unit price for the removal of unforeseen unsatisfactory soil and replacement with satisfactory soil, according to Section 31 2000 "Earth Moving."

2. Unit of Measurement: Cubic yard of soil excavated, based on in-place surveys of volume before and after removal.

$________________ per Cubic yard

Unit Price No. 2: Supplemental Excavation, Engineered Fill:

engineered fill, according to Section 31 2000 "Earth Moving."

$________________ per Cubic Yard

Unit Price No. 3: Hauling Off Additional Debris:

1. Description: Unit price for the removal of additional unforeseen debris in soils, according to Section 31

2000 "Earth Moving."

2. Unit of Measurement: Cubic yard of soil/debris excavated, based on in-place surveys of volume before

$________________ per Cubic Yard

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 4 of 7

UNIT LABOR RATES

The undersigned further proposes and agrees that should the amount of work required be increased or decreased where unit prices have not been established, the following labor rates will be the basis for any change order proposal. Labor rates are to include all direct costs without mark-up as defined in Article 7.3 of the General Conditions. Prior to contract award, if requested by the Construction Manager, the successful bidder shall provide documentation substantiating the proposed labor rates.

FEES FOR ADDITIONAL WORK

1. There will be a fee of 10% applied to the total cost of materials purchased and work completed by a contractor’s own forces. This percentage represents both overhead and profit.

2. There will be a fee of 5% applied to the total cost of work completed by a subcontractor. This percentage represents both overhead and profit.

CREDIT FOR WORK DELETED

Should any work be deleted from Contract by order of the Owner, full cost savings realized thereby will be credited to Owner.

FAMILIAL DISCLOSURE

See Page 6 of this Bid Form for required statement.

AFFIDAVIT OF COMPLIANCE

See Page 7 of this Bid Form for required statement.

SAFETY SUPPLEMENT FORM

The apparent low bidder(s) will be required to complete this form and submit to the project manager no later than (3) days after the bid opening or at the time of the post bid interview. Based on the information supplied

Owen-Ames-Kimball Co. may require further safety measures at no additional cost prior to award if warranted.

Job Hourly Benefits Employer's Payroll Total

Classification Rate Liability Taxes

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 5 of 7

AGREEMENT

The undersigned agree(s) to provide the post-bid information required within (10) days after notification of the Notice of Award and to execute an agreement for work covered by this Proposal on AIA Document

A132-2019, Standard Form of Agreement Between Owner and Contractor Where the Basis of Payment is a Stipulated Sum.

In submitting this bid, it is understood that the Owner reserves the right to reject any or all bids. It is further agreed that this bid is binding for a period of sixty (60) days from the opening thereof.

Respectfully submitted, Date , 2026

Firm Name

By

Signed

Title

Official Address

(If a corporation, affix seal)

Telephone No. ( ) ext. ___

E-Mail Address

Contact Information if there are questions about bid:

Name:_____________________________________________

Direct or Mobile Phone:__________________________

E-Mail:____________________________________________

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 6 of 7

Familial Disclosure Statement

(Must be completed for bid to be considered)

In accordance with Section 1267 of the Revised School Code this bid must be accompanied by a sworn and notarized statement disclosing any familial relationship between the Owner or any employee of the

Bidder and any member of the District’s Board of Education or Superintendent of the District.

___ No, there is not a familial relationship between the Owner or any employee of the Bidder and any member of the District’s Board of Education or Superintendent of the District.

___ Yes, there is a familial relationship between the Owner or an employee of the Bidder and a member of the District’s Board of Education or Superintendent of the District. The person(s) and relationship are as follows:

Owner/Employee Name BOE member or Superintendent Name Familial Relationship

Contractor: _________________________________________________________________________________________________

(Name of Contractor)

By: _______________________________________________________________

Title: _______________________________________________________________

Date: _______________________________________________________________

County of: _______________________________________ State of: _______________________________________

This instrument was acknowledged before me on the ____________day of ____________________________, 2026, by,_________________________________________________________________________________, Notary Public

__________________________________________ County, ________________________________.

My Commission Expires: ____________________________________________

Acting in the County of: ____________________________________________

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 7 of 7

Affidavit of Compliance – Iran Economics Sanctions Act

(Must be completed for bid to be considered)

Michigan Public Act No. 517 of 2012

The undersigned, the owner or authorized office of the below-named contractor (the “Contractor”), pursuant to the compliance certification requirement provided in the Portage Public Schools (“the School

District”) Request for Proposals For Angling Road Elementary – Site Clearing Package (“the RFP”), hereby certifies, represents and warrants that the Contractor (including its officers, directors, employees) is not an

“Iran linked business” within the meaning of the Iran Economics Sanctions Act, Michigan Public Act

No.517 of 2012 (“the Act”), and that in the event Contractor will not become an “Iran linked business” at any time during the course of performing any services under this contract.

The Contractor further acknowledges that any person who is found to have submitted a false certification is responsible for a civil penalty of not more than $250,000.00 or 2 times the amount of the contract or proposed contract for which the false certification was made, whichever is greater, the cost of the School

District’s Investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to bid on a request for proposal for three (3) years form the date determined that the person had submitted the false certification.

Contractor:

(Name of Contractor)

By: _______________________________________________________________

Title: _______________________________________________________________

Date: _______________________________________________________________

County of: _______________________________________ State of: _______________________________________

This instrument was acknowledged before me on the ____________day of ____________________________, 2026, by,_________________________________________________________________________________, Notary Public

__________________________________________ County, ________________________________.

My Commission Expires: ____________________________________________

Acting in the County of: ____________________________________________

Safety Data Questionnaire Supplement to Bid Form

The Safety data listed below shall be submitted no later than three (3) days after the bid opening by the apparent low bidder, or as requested by O-A-K for evaluation. Further documentation may be requested as a part of the evaluation process. Information specified below must be current and accurate.

COMPANY INFORMATION

Company Name:

Company Type:

Address:

City: State: Zip:

Name of your Safety and Health Officer responsible for this project:

Safety Accreditations:

Length of experience in this role:

Safety and Health Officer E-mail:

Safety and Health Officer Phone:

Does your company have a written procedure to ensure that adequate safety and health program resources, such as budget, equipment, training, and manpower are included in your bid?

YES □ NO □

Does your company have a written construction safety program? YES □ NO □

I acknowledge that my company will provide a written Site-Specific safety plan? YES □ NO □

Does your company have a written Accident/Incident Investigation Procedure? YES □ NO □

Does your company provide training and proper equipment for fall protection as required by MIOSHA?

Does your company have a safety training program? YES □ NO □

What mandatory training topics have been covered in the past year?

What percent of your company’s employees have OSHA Training Certification? _______ %

Does your company have a written drug and alcohol-free workplace program that includes drug testing? YES □

NO □

Does your company conduct post-Incident drug and alcohol testing? YES □ NO □

Has your company ever been removed from a project due to safety concerns within the last 3 years?

YES □ NO □ If yes, please briefly explain:

Does your company have a written procedure to screen subcontractors based on their past safety performance and history? YES □ NO □

Explain how you will ensure that subcontractors are following the same safety standards and expectations as your company?

Please list the PPE that your company will require while on site of all of your company’s employees and subcontractors:

I acknowledge that my Employees, Company, and/or Subcontractors can be removed from the project if safety standards and requirements are not being followed. YES □ NO □

Has your company received any citations or violations from MIOSHA in the past three (3) years?

YES □ NO □ If yes, please list:

Has your company received any willful safety violations from MIOSHA in the past five (5) years?

List your company’s Workers Compensation Experience Modification Rate for each of the last three (3) years.

20____________ 20____________ 20____________

List the number of man-hours your company worked in each of the last three (3) years.

List the OSHA recordable injuries your company experienced in each of the last three (3) years.

List the Total Recordable Incident Rate (TRIR) your company experienced in each of the last three (3) years.

Calculation: TRIR = (number of OSHA Recordable Incidents) x 200,000 / Total Number of man-hours worked

PROJECT SPECIFIC

How often will your company perform documented job site safety Inspections?

Daily □ Weekly □ Bi-Weekly □ Monthly □

Does your company conduct toolbox safety talks or weekly safety huddles? YES □ NO □

Does your company have a written procedure to ensure that only employees who are qualified by training and experience are allowed to operate equipment, tools, machinery and vehicles? YES □ NO □

Do you see any potential safety hazards on this project that your company does not have experience with or are concerned about? YES □ NO □ If yes, please explain:

COMPANY ACKNOWLEDGEMENT

I certify that my response and the information provided are true and correct to the best of my personal knowledge and belief and that I have made no willful misrepresentations in the questionnaire, nor have I withheld any relevant information in my statements and answers to questions. I am aware that any information given by me in this questionnaire may be investigated and I hereby give my full permission for and such investigation and I fully acknowledge that any misrepresentations or omissions in my response and information my cause my bid to be rejected.

Furthermore, I acknowledge that O-A-K may, at no additional cost or increase to the bid, require the contractor to perform additional safety requirements if the above information is deemed incomplete, Insufficient, below industry standard, or not to level of safety commitment expected. This may include but not be limited to additional site safety audits and inspections, full time safety supervisor, etc.

Bidders full name and entity status:

Signature

Authorized Representative of Company

Printed Name

Authorized Representative of Company

Title Date

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 1 of 21

DIVISION I – GENERAL REQUIREMENTS

01010 SUMMARY OF WORK

01010.1 WORK COVERED BY CONTRACT DOCUMENTS

A. The Project consists of Angling Road Elementary – Site Clearing.

B. The Instructions to Bidders, Project Manual, Request for Proposals, dated November 4th, 2026, issued by owner, General Conditions AIA A232-2019, General Requirements and Owner-Contractor

Agreements, are a part of all divisions and all contract documents. The order of precedence for interpretation shall be the Agreement between Owner and Contractor, RFP, the Instruction to

Bidders, the Project Manual, the General Conditions and the Contractor’s Proposal. Execution of the

Contract signifies that the Contractors are fully knowledgeable with all requirements of all divisions and documents. No claims for additional compensation will be entertained or paid to any

Contractor on account of its failure to be fully informed of all requirements of all Contract

Documents.

01010.2 CONTRACTS

A. Construct the work of each contract under a separate lump-sum/fixed price contract with the

Owner. Coordination of the work will be provided as specified herein.

B. Contractors shall carefully examine all drawings and read all divisions of the specifications and

Contract Documents and shall include all Work required of them for a complete project.

C. Requirements for a specific trade or contract will generally be described in that portion of the

Specifications or Drawings related to that trade or contract. Such requirements may, however, be described in other sections of the Contract Documents. Contractors will be held responsible for having carefully examined all drawings and read all divisions of the specifications and all contract documents to avoid omissions or duplications and to ensure a complete job.

D. Each Contractor is deemed to be fully informed about conditions relating to the construction of the

Project and the employment of labor thereon by execution of the Contract. The Contractor will not be relieved of its obligation to furnish all material and labor necessary to carry out the provisions of the Contract.

E. Any claim by the Contractor of an inability to meet any requirement set forth on the Contract

Documents, or that any requirement of these documents is impractical or unreasonable, will not be recognized, unless the claim was made at the time the Contractor’s proposal was submitted, and specific provision is made for such claim in the Contract.

F. Unless otherwise specified, the Contractor shall supply all labor, supervision, materials, transportation, apparatus, fuel, energy, and tools, necessary for the entire and proper completion of the Work. It shall perform all Work herein described in a workmanlike manner in accordance with the Contract Documents and shall provide everything properly incidental thereto as shown on the drawings, stated in the specifications, or reasonably implied there from.

G. Each Contractor shall be responsible for its own Work and every part thereof, and all Work of every description used in connection therewith. It shall specifically and distinctly assume all risks of damage or injury from whatever cause to property or persons used or employee on or in connection with his Work, and undertake and promise to indemnify, defend, and hold harmless the

Owner, Architect and Construction Manager against all claims rising out and or on account of any such damage or injury.

H. Each Contractor shall be held responsible for the execution of a satisfactory and complete piece of

Work in accordance with the true intent of the drawings and specifications. It shall provide without extra charge all incidental items required as a part of its Work, even though not particularly specified or indicated. If it has good reason for objecting to the use of any material, application or method of construction as shown or specified, it shall make report of such objection to the

Construction Manager and obtain proper adjustment before the Contract is executed.

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 2 of 21

I. Should any material or workmanship be found defective or in any way contrary to the Contract, it may be rejected by the Owner regardless of its state of completion and same must be remedied or removed by the Contractor at no additional cost or expense to Owner.

01010.3 WORK BY OTHERS

A. Work on the Project which is excluded from this Contract is as follows:

Materials testing

Asbestos abatement

01010.4 WORK SEQUENCE

A. Construct Work in stages to accommodate the Owner's use of the premises during the construction period, as applicable. The Construction Manager shall (1) coordinate detailed sequencing and scheduling with the Owner, and (2) provide overall scheduling and coordination for the entire project. All Bidders shall acknowledge the Construction Manager’s right to establish and set up, or subsequently modify, the sequencing and scheduling of all work for the earliest possible completion and benefit to the Owner.

B. Initial sequencing and scheduling detail are provided in the Construction Manager's Preliminary

Project Schedule that is included at the end of these General Requirements/bound with the

Documents. This schedule represents the general order and time frames for work to be followed by the Construction Manager. Bidders are to assume that their Work will be coordinated in a manner consistent with industry practice and the efficient coordination of all trades and that are to recognize that the sequence and pace of their work may be dictated by other trades.

Calendar dates associated with the completion of work of any particular contract are not assured.

All Bidders recognize and will accept modifications to the schedule which, in the opinion of the Construction Manager, are reasonable for the general interest of the Project because of allowable time extensions (formally or informally approved) in any contract, and that such modifications are inherent to the construction process and shall not qualify as a basis for extra compensation from the Owner.

The Bidder, in submitting a proposal for a particular bid category, agrees to commit the necessary resources to complete the Work activities of the bid category within a period not longer than the planned duration. Work included in a bid category, but not specifically defined by a work activity, is to be accomplished in a reasonable manner in conjunction with other work of the bid category, and in such a way as to avoid complication of or to delay the work of other bid categories.

01010.5 CONTRACTOR USE OF PREMISES

A. Each Contractor shall limit its use of the premises for Work and for storage related specifically to the Work, to allow for Work by other Contractors.

B. Use of the premises will be coordinated by the Construction Manager.

C. Each Contractor shall assume complete responsibility for the protection and safekeeping of their products stored on site.

D. Each Contractor shall move its stored products, which interfere with operation of the Owner or separate Contractor as directed by Construction Manager.

E. Each Contractor shall obtain and pay for the use of additional storage or Work areas if needed for operations.

01010.6 PARTIAL OWNER OCCUPANCY

A. Each Contractor shall schedule his operations for completion of portions of the Work, as designated in Schedule for the Owner's occupancy prior to substantial completion of the entire work.

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 3 of 21

B. Each Contractor shall execute Certificate of Substantial Completion for portions of the work prior to

Owner occupancy.

After Owner's occupancy, each Contractor shall allow:

(a) Access for Owner's personnel

(b) Access for receiving of Owner's equipment and furnishings

(c) Operation of the HVAC and electrical systems

Upon occupancy, the Owner will provide:

(a) Operation of the HVAC and electrical systems

(b) Adjustment of insurance coverage in accordance with General Conditions Article

11, Item 11.3.9.

01026 UNIT PRICES

1026.1 SCHEDULE OF UNIT PRICES

A. Contractors are to indicate the following unit prices in their proposals. Adjustments to Contracts will be made once actual units have been determined. Unit prices shall include all costs, including profit and overhead.

(1) Supplemental Excavation, Satisfactory Soil Fill:

satisfactory soil, according to Section 31 2000 "Earth Moving."

(2) Supplemental Excavation, Engineered Fill:

engineered fill, according to Section 31 2000 "Earth Moving."

(3) Hauling Off Additional Debris:

1. Description: Unit price for the removal of additional unforeseen debris in soils, according to Section

31 2000 "Earth Moving."

2. Unit of Measurement: Cubic yard of soil/debris excavated, based on in-place surveys of volume before and after removal.

01040 PROJECT COORDINATION

01040.1 GENERAL

A. It shall be the responsibility of the Construction Manager to coordinate and expedite all phases of construction. All separate Contractors shall fully cooperate with the Construction Manager.

B. Contractors shall assist the Construction Manager in coordinating, scheduling, and timing of construction activities to ensure orderly progress of the Work.

C. Temporary Omission of Work. If any materials and finish are of such nature that it is necessary to temporarily omit certain portions of Work in order to make final installation, the Contractor whose

Work is involved shall omit such parts of this Work or finishes as are necessary until other said Work and/or materials have been installed and shall then return and install such omitted parts of its Work as part of this contract and without additional cost or expense to the Owner.

D. Equipment and Furnishings

Copies of equipment specifications and drawings shall be made available to the

Construction Manager for determining the amount of Work to be done as described herein.

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 4 of 21

Each Contractor shall receive, inventory, store, and when spaces are acceptable, shall set equipment in the rooms for which it is intended.

(a) Arrangements shall be made by Contractor to obtain storage space for equipment and furnishings. This space shall be available to him on or before date of delivery and shall be at his disposal until all the equipment is moved to the building.

(b) Contractor shall provide the Construction Manager with the name and address of the storage facility and obtain insurance coverage protecting all stored equipment from loss or damage.

(c) Contractor shall be responsible for receiving, unloading, and placing into storage all items of equipment shipped by the equipment suppliers.

(d) Contractor shall inspect bills of lading for all items of equipment received, shall inspect all equipment, and shall immediately notify the shipping company and the supplier of items damaged or missing. The Construction Manager should be notified of any damaged or missing items.

(e) When the Construction Manager determines that rooms are ready for installation or placing of equipment, the required equipment shall be set in place.

Equipment transported from the storage facility shall be insured against damage or loss by each Contractor. Each Contractor shall be responsible for receiving, unloading, and placing and installing equipment in the rooms designated for the specified items of equipment.

The Construction Manager shall cooperate with the supplier's installation personnel by providing unobstructed areas in which they may assemble and install equipment.

The responsibilities of the Electrical and Mechanical Contractors shall be as follows, unless noted otherwise in Contract Documents:

(a) Final connections of equipment to building electrical and mechanical rough-ins will be made by the Electrical and Mechanical Contractor (interconnection between items of equipment will be done by the installing personnel, not by the

Electrical or Mechanical Contractor). Equipment requiring only plug-in connections shall have outlets installed in accordance with the Contract

Documents.

E. Each Separate Contractor shall

Within ten (10) days of receipt of Notice of Pending Award of Contract, submit to the

Construction Manager a list of the Contractor's principle staff, including on-site superintendent.

Coordinate the work of its employees and Sub-contractors.

Expedite its Work to assure compliance with schedules.

Coordinate its Work with that of other separate Contractors and Work by Owner.

Contractor will prepare and submit coordination drawings wherever close and careful coordination is required.

Comply with directions and instructions of the Construction Manager.

Verify dimensions shown on the drawings and obtain all measurements required for proper execution of Work.

Place sleeves and inserts correctly for pipes, conduits and similar items required for its

Work, in forms, walls, partitions, and floors. All said Work shall be done in cooperation with the affected Contractors. All items shall be placed in ample time so as not to delay concrete operations. Do not place sleeves so they pass through beams, girders, and similar construction, unless locations are approved by the Architect.

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 5 of 21

See that sleeves and inserts are kept in their proper positions and not displaced by the placing of concrete or other construction Work. The separate Contractors of the

Mechanical and Electrical Work involved shall be responsible for inclusion of these items in the Work and shall advise the Construction Manager and Architect of all changes of sleeves and inserts locations.

01040.2 CONSTRUCTION ORGANIZATION AND START-UP

A. Construction Manager shall establish on-site lines of authority and communications. Construction

Manager will:

Conduct the pre-construction meetings.

Conduct progress meetings.

Establish procedures and lines of communication:

(a) Submittals

(b) Reports and records

(c) Recommendations

(d) Coordination drawings

(e) Schedules

Contract Documents:

(a) Consult with Architect to obtain interpretation.

(b) Assist in resolution of questions or conflicts which may arise.

(c) Transmit written interpretations to other Contractors, and to other concerned parties.

Assist in obtaining permits and approvals:

(a) Building permits and special permits required for permanent improvements or for temporary facilities.

(b) Verify that Contractors and Sub-Contractors have obtained permits for inspections and for temporary facilities.

Control the use of the Site:

(a) Supervise field engineering and site layout.

(b) Allocate space for each Prime Contractor's use for field offices, sheds, and work and storage areas.

(c) Establish access, traffic and parking allocations and regulations.

(d) Monitor the use of the site during construction.

01040.3 CONSTRUCTION MANAGER'S DUTIES

A. Construction Schedules

Prepare a detailed schedule of basic operations.

Coordinate the schedules.

(a) Each Contractor shall prepare sub-schedules to comply with critical phases.

B. Process Shop Drawings, Coordination Drawings, Product Data and Samples

Prior to submittal to Architect, Construction Manager will review for compliance with

Contract Documents.

After the shop drawings are reviewed the Construction Manager will submit to Architect for approval.

If shop drawings are incomplete or unacceptable, Construction Manager will return them to Contractor, with comments and recommendations, for revising and to be resubmitted.

C. Inspection and Testing

The Construction Manager will assist the Architect in inspecting the Work to assure that it is performed in accordance with requirements of Contract Documents.

Coordinate Testing Laboratory Services.

D. Monitor the Use of Temporary Utilities

Portage Public Schools, Angling Road Elementary – Site Clearing Package - Page 6 of 21

Verify that adequate services are provided.

Administer the use of Owner furnished utilities and…