N62470-21-R-9004 Amendment 0001 The following pertains to this Amendment:
QUESTION AND ANSWER
Q1: Please provide the referenced Attachment A for the Past Performance Questionnaire.
A1: See attached PPQ form
Q2: Is the contract estimated start date still February 2023 as stated in the synopsis?
A2: Reference page 1 of 10 that states, Estimated start date is February 2023.
Q3: Recently, our team has received multiple task orders to execute both asbestos and lead-based paint investigations in a single task order. Is it acceptable to provide a single project description that addresses both asbestos and lead-based paint scopes of work?
A3: Reference page 5 of 10 that describes the submission requirement: Provide a maximum of five projects completed or substantially completed within the past five years immediately preceding the date of issuance of this notice that best demonstrate specialized experience of the proposed team in the areas outlined above.