Amendment_No._3.docx

DOCX document 39 KB Posted

Attached to
Wharf Logs/Backing Beams
Solicitation number
BPM045152
Issued by
Baltimore City, Maryland

About this file

This document is Amendment No. 3 to Invitation for Bid (IFB) No. 224047-H for Wharf Logs/Backing Beams, issued by the Maryland Port Administration (MPA). The amendment clarifies and provides additional details regarding the scope of work, including that this is an as-needed, indefinite quantity contract with a minimum order of 10 wharf logs/backing beams per order. The MPA reserves the right to increase or decrease quantities as required, and 100% total quality is an essential part of every product delivered. Delivery requires 24-hour advanced notice and the provision of specific visitor information.

The amendment also addresses questions raised by potential bidders, including providing pictures of the current wharf logs/backing beams in stock and confirming that the MPA will commit to a minimum order of 10 per order. The MPA will also require the inclusion of 30 FRP pins with each order of 10 wharf logs/backing beams.

View the file

Other files

File Type Posted
IMG_2296.jpg JPG image
IMG_2299.jpg JPG image
IMG_2348.jpg JPG image
IMG_2351.jpg JPG image
IMG_2346.jpg JPG image
IMG_2349.jpg JPG image
IMG_2350.jpg JPG image
IMG_2352.jpg JPG image
IMG_2353.jpg JPG image
IMG_2299.jpg JPG image
IMG_2348.jpg JPG image
IMG_2349.jpg JPG image
IMG_2350.jpg JPG image
IMG_2351.jpg JPG image
Amendment_No._1.docx DOCX document
Amendment_No._4.docx DOCX document
IMG_2296.jpg JPG image
IMG_2346.jpg JPG image
IMG_2352.jpg JPG image
Amendment_No._5.docx DOCX document
IMG_2353.jpg JPG image
IMG_2296.jpg JPG image
IMG_2349.jpg JPG image
IMG_2350.jpg JPG image
IMG_2353.jpg JPG image
IMG_2299.jpg JPG image
IMG_2346.jpg JPG image
IMG_2348.jpg JPG image
IMG_2352.jpg JPG image
IMG_2351.jpg JPG image
IMG_2296.jpg JPG image
IMG_2349.jpg JPG image
IMG_2346.jpg JPG image
IMG_2351.jpg JPG image
IMG_2352.jpg JPG image
IMG_2350.jpg JPG image
IMG_2348.jpg JPG image
IMG_2299.jpg JPG image
IMG_2353.jpg JPG image
Attachment A - Excel Bid Form.xlsx XLSX spreadsheet
IMG_2296.jpg JPG image
IMG_2299.jpg JPG image
IFB 224047-H FInal 7.3.24.docx DOCX document
IFB 224047-H FInal 7.3.24.docx DOCX document
Attachment A - Excel Bid Form.xlsx XLSX spreadsheet
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT NO. 3

IFB NO. 224047-H

WHARF LOGS/BACKING BEAMS

ISSUED: August 6, 2024

Amendment No. 3 is being issued to amend certain information contained in the above-named solicitation and to provide clarification and answers to questions submitted by potential Bidders. All information contained herein is binding on all bidders who respond to this solicitation.

Changes to the scope of work or any response as provided in this Amendment supersede the original published document. Additions are in red bold underline. All items removed have a strikethrough.

2.1.5. This is an as-needed, indefinite quantity contract. MPA will order a minimum of ten wharf logs/backing beams per order. MPA reserves the right to increase or decrease quantities as required. Unit prices bid shall apply regardless of the actual amount of items ordered.

2.3.5 Three FRP pins are required for each wharf log/backing beam (minimum of 30 pins per order).

2.3.56 100% total quality shall be an essential part of every product delivered to the MPA. These are backing beams items that will lose all effect if the Contractor does not make inspection a routine part of their process. Any product which does not meet a 100% total quality standard will be rejected and returned to the Contractor.

All materials and manufacturing methods used by the Contractor shall be in accordance with the highest quality standards customarily employed for the manufacturing of Wharf Logs/Backing Beams. If products delivered fail to meet specifications as specified, it will be the responsibility of the Contractor to have the product(s) picked-up and the specified product(s) delivered at no additional cost to the Administration.

2.3.67 Delivery Requirements

Delivery requires a 24-hour advanced notice with the following information provided to the MPA:

· Company Name

· First Name, Middle Initial, Last Name (no nicknames)

· Visitor’s driver’s license number and State of Issue

· Visitor’s vehicle license tag number and State of Issue

· Visitor’s vehicle Make/Model/Color

· Other government-issued, valid Photo ID if no driver’s license

· Reason for visit.

· Terminals visiting.

· Date(s) of visit.

· Does the visitor have a TWIC?

Delivery address is:

Dundalk Marine Terminal 2700 Broening Highway Baltimore MD 21222 Attn: Rich Rehberger, Jr.

Questions/Answers Question 1: You need a footing at least 6’ or less. Also, there is no comment on the FRP pins for mounting to the dock or wharf. This just doesn’t work for bidding as a direct buy, as we can’t make one at a time, and it would be extremely expensive, which defeats the purpose of what you’re trying to accomplish. If you can lock into a quantity that we can make all at once and then ship as needed that would save you guys more money and not have to worry about minimum order quantities and color change fees.

Answer: In MPA’s opinion and based on previous shipments, the footing does not need to be 6’ or less. Provided with this Amendment are pictures of wharf logs/backing beams that are currently in stock at the MPA. The MPA will commit to an order of 10 minimum per order. Bid Form will not change.

We would like to have the FRP pins included when we purchase the wharf logs. We will order 10 wharf logs, therefore we would need to have 30 pins supplied with each order, see Section 2.3.5 added to this Amendment.

End of Amendment No. 3

Trisha O’Neal, Procurement Officer