Amendment 1~11.pdf

PDF 133 KB Posted

Attached to
RFP # 84-22, 115KV LINE PROTECTION RELAYS
Solicitation number
BD-22-1206-40000-40000-75731
Issued by
Suffolk County, Massachusetts

About this file

This document is an amendment to RFP #84-22 issued by the Massachusetts Bay Transportation Authority (MBTA) for the Furnish and Install Two (2) 115kV Line Protection Relays. The original bid submission deadline has been extended to June 24, 2022, at 2:00 PM. No other changes have been made to the original RFP.

The RFP seeks to procure two 115kV line protection relays. The contract will be awarded through the COMMBUYS procurement system under Bid BD-22-1206-40000-40000-75731. No additional details are provided about the project scope, term of the contract, or any renewal options.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MBTA Logo, Charles D. Baker, Governor, Karyn E. Polito, Lieutenant Governor, Stephanie Pollack, MassDOT Secretary & CEO, Luis Manuel Ramírez, General Manager & CEO, MassDOT logo

Massachusetts Bay Transportation Authority

Ten Park Plaza, Suite 2810, Boston, MA 02116 www.mbta.com

June 15, 2022

SUBJECT: RFP#84-22, FURNISH AND INSTALL TWO (2) 115KV LINE

PROTECTION RELAYS

COMMBUYS Bid BD-22-1206-40000-40000-75731

Amendment 1

Dear Bidders:

Please be advised that the above has been amended and/or clarified herein. All references in

RFP#84-22, Furnish and install two 115kV line protection relays; COMMBUYS Bid BD-22-

1206-40000-40000-75731.

1. Response due date is extended to 6/24/2022, 2:00 PM.

ALL ELSE REMAINS AS PREVIOUSLY STATED.

Acknowledge receipt of Amendment in the bid.

Sincerely, John de Lalla