Amendment 0006 -Page 2.pdf
PDF 111 KB Posted
- Solicitation number
- N40080
About this file
This amendment modifies a solicitation for repair and restoration of parking aprons at Naval Air Station Patuxent River in Maryland. The scope of work includes cleaning asphalt around concrete aprons, replacing full depth concrete panels with steel dowels, and applying a new fog seal coating. The amendment extends the proposal due date to February 12, 2024 and provides responses to four questions relating to phase details and square footages for cleaning, replacement, and coating areas. This opportunity is reserved for vendors holding contracts under the $750 million 8(a) Multiple Award Construction Contract managed by the Naval Facilities Engineering Command in Washington.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0006 -Page 1 -H115 H2805 Apron Repair Phased signed.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N40080-22-D-2222
Section SF 30 – BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
The purpose of this Amendment #0006 is to provide:
1) RFI responses 58 through 61 below Page 2
Proposal Due Date Has Extended To: Monday, 12 February 2024 no later than 2:00 pm (EST).
All other terms and conditions remain unchanged.
RFI LOG
H115/H2805 Repair Apron Phased
NAS PATUXENT RIVER, MD
058 QUESTION: What is 40’sf per #53? Are we to assume area for Phase 3 is now to be bid as : 40,000’sf per
‘GILSONITE’ recommendations for cleaning -which is the Fog Sealer Manufacture. & assumed to be existing on Apron Areas. Please advise.
RESPONSE: 40,000SF is 40,000 Square Feet.
059 QUESTION: Phase One: approx. 250,000’sf of existing Apron to be “cleaned” per ‘GILSONITE’ recommendation. Pls advise.
RESPONSE: You are only cleaning the Asphalt around concrete Apron. That is 40,000 Square feet.
060 QUESTION: Phase Two: 700’sf Full Depth Conc Replacement w/ Flex 650 mix utilizing 1”x20” Steel
Dowels-greased at 12”o/c into existing Conc Panels. Please advise.
RESPONSE: This is answered in the scope of work in section 1.13.
061 QUESTION: H2805: Phase Three: now is 40,000’sf of new ‘GILSONITE’ Fog Seal application on the
Outer Band of the Apron Area as indicated on RFP attached Photos w/ Red Line Arrows indicating Phases.
Please advise.
RESPONSE: Yes 40,000 Square Feet