Am-0001_Solicitation_Attachments.pdf
PDF 154 KB Posted
- Attached to
- Consolidate Cadet Prep School Dormitory Federal contract opportunity
- Solicitation number
- W9128F23R0007
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Consolidated Prepatory School Dormitories - USAFA, CO AA70
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 00.00 10
QUALITY CONTROL
11/16, CHG 2: 11/21
PART 1 GENERAL
1.1 REFERENCES
1.2 PAYMENT
1.3 SUBMITTALS
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN
3.2.1 Content of the CQC Plan
3.2.2 Additional Requirements for Design Quality Control (DQC) Plan
3.2.3 Acceptance of Plan
3.2.4 Notification of Changes
3.3 COORDINATION MEETING
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
3.4.2 CQC System Manager
3.4.3 CQC Personnel
3.4.4 Assignment of CQC System Manager, Project Superintendent, and
SSHO Responsibilities
3.4.5 Construction Quality Management Course
3.4.6 Organizational Changes
3.5 SUBMITTALS AND DELIVERABLES
3.6 CONTROL
3.6.1 Preparatory Phase
3.6.2 Initial Phase
3.6.3 Follow-up Phase
3.6.4 Additional Preparatory and Initial Phases
3.7 TESTS
3.7.1 Testing Procedure
3.7.2 Testing Laboratories
3.7.2.1 Capability Check
3.7.2.2 Capability Recheck
3.7.3 Onsite Laboratory
3.8 COMPLETION INSPECTION
3.8.1 Punch-Out Inspection
3.8.2 Pre-Final Inspection
3.8.3 Final Acceptance Inspection
3.9 DOCUMENTATION
3.10 SAMPLE FORMS
3.11 NOTIFICATION OF NONCOMPLIANCE
SECTION 01 45 00.00 10 Page 1Am #0001
-- End of Section Table of Contents --
SECTION 01 45 00.00 10 Page 2Am #0001
SECTION 01 45 00.00 10
QUALITY CONTROL
11/16, CHG 2: 11/21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D3740 (2019) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction
ASTM E329 (2021) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1110-1-12 (2006; Change 1) Engineering and Design -- Quality Management
1.2 PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable Pricing Schedule item.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" classifications;
submittals not having a "G" classification are for information only. When used, a code following the "G" classifications identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan; G, RO
Additional Requirements for Design Quality Control (DQC) Plan; G, DO
SD-05 Design Data
Discipline-Specific Checklists
Design Quality Control
SECTION 01 45 00.00 10 Page 3Am #0001
SD-06 Test Reports
Verification Statement
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Submit Quality Control Personnel experience as submitted per the requirements of Section 00 22 00. If, because of reasons beyond the control of the Contractor, the named individuals are not able to fulfill this obligation, present replacement personnel with equal or better skills and experience for acceptance by the Contracting Officer. Obtain the Contracting Officer's written consent before making any substitution for these designated personnel.
Establish and maintain an effective quality control (QC) system that complies with FAR 52.246-12 "Inspection of Construction." QC consist of plans, procedures, and organization necessary to produce an end product which complies with the Contract requirements. The QC system covers all design and construction operations, both onsite and offsite, and must be keyed to the proposed design and construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the Contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent must maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN
Submit no later than 15 calendar days after receipt of notice to proceed, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of FAR 52.246-12 "Inspection of Construction." The Government will consider an interim plan for the first 30 days of operation. Design and Construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work.
3.2.1 Content of the CQC Plan
Include, as a minimum, the following to cover all design and construction operations, both onsite and offsite, including work by subcontractors, designers of record, consultants, architect/engineers (AE), fabricators, suppliers, and purchasing agents:
a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified.
SECTION 01 45 00.00 10 Page 4Am #0001
b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.
c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the Contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Furnish copies of these letters to the Contracting Officer.
d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, designers of record, consultants, architect engineers (AE), offsite fabricators, suppliers, and purchasing agents. These procedures must be in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer are required to be used.)
f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.
g. Procedures for tracking design and construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.
h. Reporting procedures, including proposed reporting formats.
i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and is identified by different trades or disciplines, or it is work by the same trade in a different environment. Although each section of the specifications can generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.
j. Coordinate scheduled work with Special Inspections required by Section 01 45 35 SPECIAL INSPECTIONS (as provided by the DOR), the Statement of Special Inspections and the Schedule of Special Inspections. Where the applicable Code issue by the International Code Council (ICC) calls for inspections by the Building Official, the Contractor must include the inspections in the Quality Control Plan and must perform the inspections required by the applicable ICC. The Contractor must perform these inspections using independent qualified inspectors.
Include the Special Inspection Plan requirements in the QC Plan.
3.2.2 Additional Requirements for Design Quality Control (DQC) Plan
The following additional requirements apply to the Design Quality Control
SECTION 01 45 00.00 10 Page 5Am #0001
(DQC) plan:
a. Submit and maintain a Design Quality Control (DQC) Plan as an effective quality control program which assures that all services required by this contract are performed and provided in a manner that meets professional architectural and engineering quality standards.
As a minimum, all documents must be technically reviewed by competent, independent reviewers identified in the DQC Plan. The same element that produced the product may not perform the independent technical review (ITR). Correct errors and deficiencies in the design documents prior to submitting them to the Government.
b. Include the design schedule in the master project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific Contract period. This should be at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work. Include review and correction periods associated with each item. This should be a forward planning as well as a project monitoring tool. The schedule reflects calendar days and not dates for each activity. If the schedule is changed, submit a revised schedule reflecting the change within 7 calendar days. Include in the DQC Plan the discipline-specific checklists to be used during the design and quality control of each submittal. Submit at each design phase as part of the project documentation these completed discipline-specific checklists. ER 1110-1-12 provides some useful information in developing checklists.
c. Implement the DQC Plan by a Design Quality Control Manager who has the responsibility of being cognizant of and assuring that all documents on the project have been coordinated. This individual must be a person who has verifiable engineering or architectural design experience and is a registered professional engineer or architect.
Notify the Contracting Officer, in writing, of the name of the individual, and the name of an alternate person assigned to the position.
(1) The DQC Manager is responsible for reporting to the overall Project Manager of the Contractor for the design-build contract. The Project Manager will be held responsible for the quality of design on the contract and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract.
The Contracting Officer will notify the Contractor in writing of the acceptance of the DQC Plan. After acceptance, any changes proposed by the Contractor are subject to the acceptance of the Contracting Officer.
3.2.3 Acceptance of Plan
Acceptance of the Contractor's plan is required prior to the start of design and construction. Acceptance is conditional and will be predicated on satisfactory performance during the design and construction. The Government reserves the right to require the Contractor to make changes in the Contractor Quality Control(CQC) Plan and operations including removal of personnel, as necessary, to obtain the quality specified.
3.2.4 Notification of Changes
After acceptance of the CQC Plan, notify the Contracting Officer in
SECTION 01 45 00.00 10 Page 6Am #0001 writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.
3.3 COORDINATION MEETING
After the Postaward Conference, before start of design or construction, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer and discuss the Contractor's quality control system.
Submit the CQC Plan a minimum of 10 calendar days prior to the Coordination Meeting. During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations, design activities, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting Officer and will become a part of the contract file. There can be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings or address deficiencies in the CQC system or procedures which can require corrective action by the Contractor.
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
The requirements for the CQC organization are a Safety and Health Manager, CQC System Manager, a Design Quality Manager, and sufficient number of additional qualified personnel to ensure safety and Contract compliance.
The Safety and Health Manager reports directly to a senior project (or corporate) official independent from the CQC System Manager. The Safety and Health Manager will also serve as a member of the CQC Staff. Include personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly as part of the CQC organization. The Contractor's CQC staff maintains a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure Contract compliance. The CQC staff will be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC organization. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules and all other project documentation to the CQC organization. The CQC organization is responsible to maintain these documents and records at the site at all times, except as otherwise acceptable to the Contracting Officer.
3.4.2 CQC System Manager
Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor. The CQC System Manager is required to be a construction person with a minimum of 5 years in related work. This CQC System Manager is on the site at all times during construction and is employed by the prime Contractor. The CQC System Manager is assigned no other duties. Identify in the plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager.
SECTION 01 45 00.00 10 Page 7Am #0001
3.4.3 CQC Personnel
Maintain a staff under the direction of the CQC system manager to perform all QC activities. The staff must be of sufficient size to ensure adequate QC coverage of all work phases, work shifts, and work crews involved in the construction. [*Am-1] At a minimum an assistant CQC shall be provided to assist the CQCM in their duties. The assistant CQC is only required to meet the requirements of paragraph 3.4.5 of this section.
[**Am-1] These personnel may perform other duties, but must be fully qualified by experience and technical training to perform their assigned QC responsibilities and must be allowed sufficient time to carry out these responsibilities. Clearly state the duties and responsibilities of each staff member in the QC Plan. Other technical specifications may specify individuals for maintaining quality control for specific areas of work.
Identify a separate Design Quality Control Manager who is a Registered Architect or Professional Engineer. This DQC Manager is considered part of the Contractor's Quality Control staff but reports directly to the overall Project Manager for the Contractor for the design-build contract.
3.4.4 Assignment of CQC System Manager, Project Superintendent, and SSHO Responsibilities
The CQC System Manager, Project Superintendent, and SSHO may not share duties and are required to be separate individuals.
3.4.5 Construction Quality Management Course
In addition to the above experience and education requirements, the Contractor Quality Control(CQC) System Manager and [*Am-1] Alternate /Assistant [**Am-1] CQC System Manager are required to have completed the Construction Quality Management (CQM) for Contractors course.
Contractor personnel who otherwise fulfill all requirements for designation as a CQC Manager, but have not had the opportunity to obtain a CQM certificate due to COVID-19 restrictions, shall be permitted to serve as Quality Control Managers conditioned upon obtaining a CQM-C certificate within 120 days of USACE lifting current in person learning restrictions.
CQC Managers who were in possession of valid CQM certificate (i.e. not delinquent on the 5 year course renewal requirement) as of 01-Mar-2020 will have a grace period for obtaining the CQM renewal training of 6-months from the lifting of COVID-19 restrictions and USACE being able to provide face to face CQM training.
This course is periodically offered at offices indicated at the following web site:
http://www.nwo.usace.army.mil/BusinessWithUs/Contracting/QualityManagement.aspx
The exact date and location for the sessions will be determined approximately 30 calendar days in advance by the trainer (POC). Cost varies by location per student.
The Construction Quality Management Training certificate expires after 5 years. If the CQC System Manager's certificate has expired, retake the course to remain current.
The Government reserves the right to recognize certificates issued as a result of virtual training by a certified instructor as valid.
SECTION 01 45 00.00 10 Page 8Am #0001
[*Am-1] At a minimum an assistant CQC shall be provided to assist the CQCM in their duties. The assistant CQC is only required to meet the requirements of paragraph 3.4.5 of this section.
[**Am-1]
[*Am-1] Alternate /Assistant [**Am-1]
3.4.6 Organizational Changes
Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer for acceptance.
3.5 SUBMITTALS AND DELIVERABLES
Submittals, if needed, have to comply with the requirements in Section 01 33 00 SUBMITTAL PROCEDURES. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements. When Section 01 91 00.15 10 TOTAL BUILDING COMMISSIONING are included in the contract, the submittals required by those sections have to be coordinated with Section 01 33 00 SUBMITTAL PROCEDURES to ensure adequate time is allowed for each type of submittal required.
3.6 CONTROL
CQC is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control are required to be conducted by the CQC System Manager for each definable feature of the construction work as follows:
3.6.1 Preparatory Phase
This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:
a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.
b. Review of the Contract drawings.
c. Check to assure that all materials and equipment have been tested, submitted, and approved.
d. Review of provisions that have been made to provide required control inspection and testing.
e. Review Special Inspections required by Section 01 45 35 SPECIAL INSPECTIONS (as provided by the DOR), the Statement of Special Inspections and the Schedule of Special Inspections.
f. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the Contract.
g. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.
h. Review of the appropriate activity hazard analysis to assure safety
SECTION 01 45 00.00 10 Page 9Am #0001 requirements are met.
i. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.
j. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.
k. Discussion of the initial control phase.
l. Schedule all preparatory inspections two(2) weeks in advance. Include a meeting conducted by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.
3.6.2 Initial Phase
This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:
a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.
b. Verify adequacy of controls to ensure full contract compliance.
Verify required control inspection and testing are in compliance with the contract.
c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.
d. Resolve all differences.
e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.
f. The Government needs to be notified at least 48 hours in advance of beginning the initial phase for definable feature of work. Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for definable feature of work for future reference and comparison with follow-up phases.
g. The initial phase for each definable feature of work is repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.
h. Coordinate scheduled work with Special Inspections required by Section 01 45 35 SPECIAL INSPECTIONS (as provided by the DOR), the Statement of Special Inspections and the Schedule of Special Inspections.
SECTION 01 45 00.00 10 Page 10Am #0001
3.6.3 Follow-up Phase
Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work. Coordinate scheduled work with Special Inspections required by Section 01 45 35 SPECIAL INSPECTIONS (as provide by the DOR), the Statement of Special Inspections and the Schedule of Special Inspections.
3.6.4 Additional Preparatory and Initial Phases
Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.
3.7 TESTS
3.7.1 Testing Procedure
Perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements.
Upon request, furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and acceptance tests when specified. Procure the services of a Corps of Engineers approved testing laboratory or establish an approved testing laboratory at the project site. Perform the following activities and record and provide the following data:
a. Verify that testing procedures comply with contract requirements.
b. Verify that facilities and testing equipment are available and comply with testing standards.
c. Check test instrument calibration data against certified standards.
d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.
e. Record results of all tests taken, both passing and failing on the CQC report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test. If approved by the Contracting Officer, actual test reports are submitted later with a reference to the test number and date taken. Provide an information copy of tests performed by an offsite or commercial test facility directly to the Contracting Officer. Failure to submit timely test reports as stated results in nonpayment for related work performed and disapproval of the test facility for this Contract.
3.7.2 Testing Laboratories
All testing laboratories must be validated by the USACE Material Testing
SECTION 01 45 00.00 10 Page 11Am #0001
Center (MTC) for the tests to be performed. Information on the USACE MTC with web-links to both a list of validated testing laboratories and for the laboratory inspection request for can be found at:
https://mtc.erdc.dren.mil/
Click on "Lab Validation" Search for a Validation
3.7.2.1 Capability Check
The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel is required to meet criteria detailed in ASTM D3740 and ASTM E329.
3.7.2.2 Capability Recheck
If the selected laboratory fails the capability check, the Contractor will be assessed the actual cost for the recheck to reimburse the Government for each succeeding recheck of the laboratory or the checking of a subsequently selected laboratory. Such costs will be deducted from the Contract amount due the Contractor.
3.7.3 Onsite Laboratory
The Government reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests, and to check the Contractor's testing procedures, techniques, and test results at no additional cost to the Government.
3.8 COMPLETION INSPECTION
3.8.1 Punch-Out Inspection
Conduct an inspection of the work by the CQC System Manager near the end of the work, or any increment of the work established by a time stated in FAR 52.211-10 "Commencement, Prosecution, and Completion of Work", or by the specifications. Prepare and include in the CQC documentation a punch list of items which do not conform to the approved drawings and specifications, as required by paragraph DOCUMENTATION. Include within the list of deficiencies the estimated date by which the deficiencies will be corrected. Make a second inspection by the CQC System Manager or staff to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government Pre-Final inspection.
3.8.2 Pre-Final Inspection
The Government will perform the pre-final inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items noted on the Pre-Final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph need to be accomplished within the time slated for completion of the entire work or any particular increment of the work if
SECTION 01 45 00.00 10 Page 12Am #0001 the project is divided into increments by separate completion dates.
3.8.3 Final Acceptance Inspection
The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative is required to be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from Base/Post Civil Facility Engineer user groups, and major commands can also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the Contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with FAR 52.246-12 "Inspection of Construction".
3.9 DOCUMENTATION
Maintain current records providing factual evidence that required quality control activities and tests have been performed. Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the following information:
a. The name and area of responsibility of the Contractor/Subcontractor.
b. Operating plant/equipment with hours worked, idle, or down for repair.
c. Work performed each day, giving location, description, and by whom.
When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.
d. Test and control activities performed with results and references to specifications/drawings requirements. Identify the control phase (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action.
e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.
f. Submittals and deliverables reviewed, with Contract reference, by whom, and action taken.
g. Offsite surveillance activities, including actions taken.
h. Job safety evaluations stating what was checked, results, and instructions or corrective actions. Include information identified by the "Responsible Individual(s)" for Safety as outlined in Section
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS.
i. Instructions given/received and conflicts in plans and/or specifications.
SECTION 01 45 00.00 10 Page 13Am #0001
j. Provide documentation of design quality control activities. For independent design reviews, provide, as a minimum, identification of the Independent Technical Review (ITR) team, the ITR review comments, responses and the record of resolution of the comments.
k. Verification Statement.
Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the Contract. Furnish the original and one copy of these records in report form to the Contracting Officer's Representative on the first day following the date(s) covered by the report, except that reports need not be submitted for days on which no work is performed. The Government may elect to process these records electronically. Coordinate with the Contracting Officer's Representative. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period. All calendar days need to be accounted for throughout the life of the contract. The first report following a day of no work will be for that day only.
Reports need to be signed and dated by the Contractor Quality Control(CQC) System Manager. Include copies of test reports and copies of reports prepared by all subordinate quality control personnel within the CQC System Manager Report.
3.10 SAMPLE FORMS
Generate daily quality control reports using the Government-furnished Construction Contractor Module of RMS specified in Section 01 45 00.15 10
RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM).
3.11 NOTIFICATION OF NONCOMPLIANCE
The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer can issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor.
-- End of Section --
SECTION 01 45 00.00 10 Page 14Am #0001
Am #0001 Instructions to Request Additional RFP Files – FOR INFORMATION ONLY Page 1 of 1
Instructions to Request Additional RFP Files:
Due to file size limitations associated with SAM.gov, request additional RFP files by emailing the Contract Specialist, Scott Dwyer at email: Scott.Dwyer@usace.army.mil. Request must contain an email address, to which pick‐up instructions for downloading the additional files will be sent via DoD SAFE.
02 41 00AT ‐ FIO As‐Built Drawings (zip file) APPENDIX C ‐ USAFA Design Standards‐2011 – FIO
APPENDIX G ‐ USAFA INSTALLATION FACILITIES STANDARD 18 DEC 2019
| Specifications (Revised and Reissued) |
| 01 45 00.00 10 |
Instructions to Reqest Additional RFP Files - FOR INFORMATION ONLY
File details come from the government source that posted it. Updated .