This document contains a checklist for commissioning ceiling mounted patient lift systems for the Department of Veterans Affairs. The checklist outlines inspection and testing requirements for the structural components, lift unit, straps, and emergency functions of the lifts. It includes fields for the contact information, location, manufacturer, model, and serial number of the lifts. Signatures are required from the inspector, manager of the service using the lifts, and VA representative to verify completion of all installation and inspection requirements before the lifts are released for use.
The related federal contract opportunity is a combined synopsis and solicitation issued by the Southeast Louisiana Veterans Health Care System for commercial items. Quotes are due by July 29, 2022 and shall be submitted electronically to the listed contracting officer. The period of performance is a base period of 180 days after award. The document lists the applicable FAR and VAAR provisions and clauses that are incorporated into the solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25622Q1149_3.docx | DOCX document | |
| Questions and Reponses.pdf | ||
| 36C25622Q1149_2.docx | DOCX document | |
| AL14-07 Checklist for Installation and Relocation.pdf | ||
| Attachment 2 _ Overhead Lift Track Specification.pdf | ||
| AL14-07 ADDENDUM.pdf | ||
| Attachment A-C450 Inventory to be replaced-SLVHCS.pdf | ||
| Combined Synopsis-36C25622Q1149-SLVC Patient Lifts 071522.pdf | ||
| 36C25622Q1149_1.docx | DOCX document | |
| Attachment 1-Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revision 2.1 1 of 2 Serial #: ____________________
PASS FAIL
PASS FAIL
The commissioning for a patient ceiling lift system(s) shall include, but not be limited to, the following points as components of the commissioning procedures.
NOTE: Ceiling mounted patient lifts are not to be installed in treatment units with actively suicidal patients.
Lift Location:
VAMC Contact's Phone Number:
Installer:
VAMC Contact:
Manufacturer:
Model:
Facility: Work Order:
Serial Number: EE Number:
Installer's Phone Number:
Structure
Rails/Tracks and End Stops
NOTES:
Lift Unit and Straps
NOTES:
Perform a visual inspection to verify structural component sizing and physical installation to ensure that the correct structural system is in place and properly installed to support the lift.
Verification that all fasteners and set screws are properly tightened on the trollies and rails/tracks.
Ensure that the rail/track is free of gaps (unless required by design). If included in installation, verify rail turntable function, exchanger function, gate alignment, and safety block installation.
Confirm track is clean and clear of all debris. (Use manufacturer’s recommended cleaning materials to avoid damage to the motor case and other components.)
Verification that all manufacturer specified end stops or docking gates are properly installed.
Inspection of lift unit casing for cracks and alignment.
Inspection and activation of hand control for full operation (e.g., up, down, left, right) and “return to charge” function if applicable.
Corrective and Preventive Maintenance Checklist for Ceiling Mounted Patient Lifts
Mfgr Contact's Phone Number:
Date:
Mfgr Contact:
Confirm any and all lift unit indicator lights are functioning. (e.g., red service warning light, charging state light) Inspection and verification of all emergency functions of the lift unit.
Inspection of spreader bar and clips for cracks and for loose or missing rings or cotter pins.
Full extension and inspection of lift strap for loose threads or frays.
Complete
Verification that the lift unit charges properly.
Perform a visual inspection to verify proper connections of the lift's structural system to the building’s structure (including seismic bracing if applicable).
Perform a visual inspection to verify proper interface at the ceiling (hard deck or soft tile) and proper installation of all protective features around the support rods and rails/tracks.
Revision 2.1 2 of 2 Serial #: ____________________
PASS FAIL
NOTES:
After the activities listed in the above checklist and in the manufacturer's installation/operations/owner’s manual(s) have been completed, the inspector shall release the ceiling mounted lift installation to VA representative.
SIGNATURE:
After the activities listed in the above checklist and in the manufacturer's installation/operations/owner’s manual(s) have been completed, the manager of the service using the ceiling mounted lifts confirms that the current staff have received initial training on ceiling mounted lifts and that there is a process in place to provide ongoing training on the proper use of ceiling mounted lifts.
SIGNATURE:
TITLE:
Manager of the Service Using the Ceiling Mounted Lifts COMPLETE
TITLE:
VA Representative After the activities listed in the above checklist and in the manufacturer's installation/operations/owner’s manual(s) have been completed, the VA representative shall review those items with the inspector prior to releasing the ceiling mounted lift back into service to ensure completion of all requirements.
SIGNATURE:
COMPLETE
Inspector COMPLETE
DATE:
DATE:
DATE:
Verification of any “soft start” or “soft stop” features and that lifting speed does not exceed 2.5 inches per second with “zero” load.
Verification of load testing and deflection testing at the manufacturer's specified maximum rated lift capacity.
Verification of any “soft start” and “soft stop” features and that lifting speed does not exceed 1.5 inches per second under maximum rated lift capacity.
Verification of emergency lowering feature at maximum rated lift capacity.
TITLE:
Verification of function of emergency stop at maximum rated lift capacity.
NOTES:
Load Testing
Inspection