This is an Advertisement for Bids issued by the Oakland Community College Board of Education for the AH25-003 Auburn Hills Campus Chiller Replacement Project. The project involves procuring labor, materials, and equipment to complete a comprehensive chiller replacement at the Auburn Hills Campus. Bid documents will be available starting June 18th, 2025, with bids due by 2:00 pm on July 17th, 2025, through the online bidding platform Building Connected. A pre-bid meeting is scheduled for June 26th, 2025, at 10:00 am at the OCC Auburn Hills Campus, with additional site visits available upon request.
Bidders are required to submit a Familial Disclosure Form, Iran Sanctions Form, and a Bid Bond through the Building Connected platform. The college reserves the right to accept or reject any bid proposals, award the contract to a non-lowest bidder, and make awards in a manner deemed most beneficial to the owner. Interested parties can obtain bid documents online or by contacting specific Barton Malow representatives via email. The project involves replacing existing chillers with new centrifugal chillers, adding a building addition for new secondary switchgear, installing a new cooling tower, and performing mechanical and electrical upgrades.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Advertisement for Bids 1 of 1 001113
SECTION 001113
ADVERTISEMENT FOR BIDS
AH25-003 AUBURN HILLS CAMPUS
CHILLER REPLACEMENT PROJECT
The Oakland Community College Board of Education (“Owner”) will receive firm, sealed Bid Proposals for all labor, materials, equipment, and all other services to complete the AH25-003 Chiller Replacement Project. Bid documents will be available for examination and distribution on or after 12:00am local standard time on June 18th, 2025. To obtain documents go to:
https://app.buildingconnected.com/projects/68514ffb76c3d91a2f23708c/bid-packages
All bids can be submitted through the online bidding platform Building Connected by no later than 2:00pm, July 17, 2025 via Building Connected. All Bid Proposals received on or before the Due Date will be publicly opened and read aloud immediately in order of category number. Bid Proposals received after the due date will not be considered or accepted.
Alternatively, bidders may submit proposals via hard copy with bidder’s name on the outside of the envelope and as designated as follows: Project Name, Bid Package Number, Bid Category, Vendor Name/Address. To obtain hard copy of the bid form, please reach out to Nick Sesi:
Nicholas.Sesi@bartonmalow.com or Chris Schneider: Chris.Schneider@bartonmalow.com
The public bid opening may be attended virtually at 2:00pm local time on July 17, 2025 via Microsoft Teams Live Event: To attend contact Nick Sesi via email @ Nicholas.Sesi@bartonmalow.com
If you experience any issues attending this live event, please email Nicholas.Sesi@bartonmalow.com. A Pre-Bid Meeting has been scheduled for 10:00 am local standard time, June 26, 2025. Pre-Bid meeting will be held on OCC Auburn Hills Campus(Building P): 2900 Featherstone Rd, Auburn Hills MI, 48326.
Additional site visits can be accommodated upon request.
All Bidders must provide a Familial Disclosure Form, Iran Sanctions Form, and also a Bid Bond, upload this information to the Bid Proposal on Building Connected. The College will not accept a bid proposal that does not include this information.
Oakland Community College reserves the right to accept or reject any or all Bid Proposals, either in whole or in part; to award the Contract to other than the low Bidder; to waive any irregularities and/or informalities; and in general to make awards in any manner deemed to be in the best interests of the Owner.